The cost of restoring a 200 m² masía, and how to do it in phases

A complete refurbishment of a 200 m² masía — the traditional Catalan stone farmhouse — runs between 123,000 and 159,500 € at a functional specification, between 204,500 and 265,000 € at mid-range and between 319,000 and 413,000 € for high specification. Always excluding VAT. These figures are built item by item: the standard trades come from our own price table, and the masía-specific work — consolidating stone walls, autonomous sewage treatment, technical fees — from 2026 market ranges, because we have not yet closed a masía of our own to test them against. It is the size at which almost nobody does the work in one go: it is rehabilitated in phases, and the order in which they are done changes the total cost more than any decision about materials.

Room mid-works with the plaster half applied in a two-storey refurbishment — our job in Santa Coloma de Gramenet

Functional

123,000 € – 159,500 €

Standard finishes, layout unchanged

Mid-range

204,500 € – 265,000 €

Selected materials, possible re-planning

High specification

319,000 € – 413,000 €

Premium materials and interior design

Indicative prices · VAT not included · not a binding offer. Your exact figure comes from the free site visit, fixed and itemised.

The starting point

What you are buying in a 200 m² masía

A masía is not renovated, it is rehabilitated: the building has stood for between one and three hundred years, several generations have altered it and almost nothing conforms to a standard measurement. That changes the budget in one specific direction — the heavy work rules and finishes weigh less — and it changes the method: first you diagnose, then you design and only then do you put a price on it.

The figures on this page are an item-by-item construction for a masía of 200 m² built over two floors, with a pitched roof and rubble-masonry walls. If your masía has annexes, a threshing floor, a hayloft or a third storey under the roof, the floor area to be rehabilitated is larger than the one the land registry gives as dwelling. We work across the whole of Catalonia, and masía renovation is concentrated in the Vallès and the inland comarcas.

  • Diagnosis before a quote: trial openings, not estimates
  • Envelope first: roof, structure and façade
  • Price by item, with the deviation assumptions written down
  • One contract for all trades and a dedicated site manager
From our price table, not a template

Example budget, item by item

Excluding VAT. The standard trades come from our price table, built from 24 of our closed quotes; the masía-specific items — stone walls, autonomous sewage treatment, technical fees and charges — from 2026 market ranges. It is an indicative construction, not a quote: on a masía the real number comes out of the pathology report.

ItemFunctionalMid-rangeHigh spec% of total
Demolition and lifting of flooring2,800 €3,800 €7,200 €2%
Rubble and waste removal · 72 m³ — a masía produces twice as much as a flat2,016 €2,952 €4,680 €1%
Consolidating and repointing stone walls · 280 m² of wall — the item that does not exist in a flat15,400 €26,600 €42,000 €11%
Structure: floors and reinforcement · 95 m² of floor; in a masía there is almost always timber to replace1,900 €6,365 €11,115 €3%
Roof (complete refurbishment) · 105 m² of pitch10,185 €17,430 €23,310 €7%
Waterproofing1,176 €3,612 €4,032 €2%
Façade: render and finish · 220 m² on four faces, not one6,160 €10,120 €21,120 €4%
Thermal and acoustic insulation3,600 €4,400 €4,800 €2%
Complete electrical installation3,793 €3,867 €3,976 €2%
Plumbing and drainage · 18 points4,680 €6,552 €9,198 €3%
Autonomous sewage treatment (septic tank or plant) · if there is no municipal network, which is the norm3,000 €5,000 €8,000 €2%
Heating (underfloor + generation) · a masía almost never comes with usable heating11,000 €15,000 €20,000 €6%
Exterior joinery · 18 openings, many of non-standard size9,954 €20,700 €39,888 €9%
Internal joinery · 14 doors3,500 €8,050 €10,920 €3%
Building work: renders and bases7,200 €7,200 €7,600 €3%
Interior flooring5,400 €8,000 €14,600 €3%
Complete bathrooms · 2 bathroom(s)20,510 €31,518 €40,934 €14%
Complete kitchen5,518 €7,650 €14,961 €3%
Skimming and painting · wall and ceiling surface, not floor7,200 €11,520 €12,000 €5%
Access equipment, scaffolding and protection906 €1,020 €1,422 €0%
Building labourers’ assistance960 €1,197 €1,923 €1%
Preliminary pathology study · compulsory in practice for a masía1,500 €2,600 €4,000 €1%
Project and technical supervision · 8-14% of the PEM (material execution budget); a masía always needs a project10,149 €22,281 €42,515 €10%
Fees and major-works licence · 1-4% depending on the municipality1,269 €5,064 €12,147 €2%
Total for the example budget139,776 €232,498 €362,341 €
Equivalent per m²699 €/m²1,162 €/m²1,812 €/m²
The order matters more than the catalogue

Rehabilitating in phases without paying twice

At 200 m², the full budget is a figure many people do not want — or cannot — commit in one go. The usual way out is to rehabilitate in phases: first what stops the building from carrying on deteriorating, then what makes it habitable, and at the end what makes it comfortable.

The expensive mistake is phasing by floors or by the pretty zones. If the roof is not in the first phase, everything you do beneath is being done twice, and the scaffolding, the access equipment and the technical supervision are paid once per phase, not once per job. A well-planned phasing concentrates the envelope — roof, façade, structure — in phase one even if the interior is left rough, because that stops the clock of deterioration and is not touched again.

A project drafted with phases in mind costs the same as one drafted all at once and lets you decide when to carry on. It is the difference between a job that is stopped and a job that is paused.

≈7%Phase 1: envelope and structure
≈93%Later phases: interiors
What we can show you

We have not finished a masía yet

We say it here and not in the small print: we have not yet delivered a masía of our own. On the rest of this site’s price pages you will see two of our jobs with their photos and real cost; on these four there are none, because we do not have them, and putting a renovated flat in their place would be selling you an experience the photos do not support.

What we have done is the heavy work that rules in a masía. In our refurbishment of a building in Santa Coloma we rebuilt floors, fitted a new steel structure and worked on two levels with the building open: these are exactly the items that take a quarter of the budget in this table. The photos on this page come from that job, and each caption says where it comes from.

For the rest, the honest answer is a visit. On a masía no serious company gives you a number over the phone: someone goes up on the roof, trial openings are made and a pathology report is written. That report costs between 1,500 and 4,000 € and is the only thing that turns the figures above into a quote. If you are weighing up a purchase, ask for it before signing, not after.

  • No masía of our own: we would rather say so than fill the gap
  • Yes to structural rehabilitation: floors, structure and roof
  • A free technical visit and, if a purchase is involved, a prior report
  • The figures on this page are no substitute for a pathology report
What changes when there is a heritage listing

If the masía is listed

Many masías in inland Catalonia appear on the register of protected buildings of their municipality. It does not mean they cannot be touched; it means that what can be touched is written down, and the council checks it.

In practice it comes down to three things: mandatory materials in whatever is seen from outside — reclaimed Arabic tile, lime renders instead of cement mortar, timber joinery in the original openings —; openings that cannot be opened or closed at will, which conditions the interior layout more than people expect; and longer timescales, because the file goes through a committee that does not meet every week.

In cost, listing does not usually blow up the total, but it does shift it towards mid-to-high specification: lime costs more than cement and a made-to-measure timber window costs more than a standard aluminium one. What does change radically is the calendar. It is worth asking for the planning record before signing the purchase, not after.

  • Ask the council for the register entry before buying
  • Reclaimed tile and lime render: compulsory on whatever is seen
  • The original openings condition the interior layout
  • Count months, not weeks, for the heritage procedure
Your home is not the “example”

What pushes the price up or down in your case

What pushes it up

  • Timber structure with no usable sectionReplacing trusses and floors instead of repairing them is the biggest possible deviation
  • A listed masíaLime instead of cement, reclaimed tile and made-to-measure timber joinery
  • No connectionsA well, a power-line extension and autonomous sewage treatment are added separately
  • Difficult accessAn unmade track, or one too narrow for a lorry, makes everything that goes in and out dearer
  • Rising dampRubble masonry wall with no barrier: perimeter drainage and remedial mortars

What brings it down

  • A sound roofRepairing and reusing tiles instead of rebuilding the pitch
  • Renovating in phasesIt spreads the cost, although it repeats the access equipment
  • Keeping the layoutNot touching load-bearing walls avoids reinforcement and makes the project cheaper
  • Treated exposed timberCheaper than replacing it, and it is what gives the masía its character
Timescales

How long does the work take?

Weeks 1-4Preliminary study and project

Survey, trial openings and a pathology report; without this any figure is a round number

Months 2-5Major-works licence

Signing-off, submission to the council and, if listed, a heritage report

Weeks 1-3 of the worksSet-up and demolition

Perimeter scaffolding, stockpiles, removal of whatever is not kept

Following 6-12 weeksStructure and roof

The phase that stops the deterioration: floors, trusses, insulation and waterproofing

After thatServices and envelope

Electrics, plumbing, autonomous sewage treatment, heating and exterior joinery

Final stretchFinishes

Flooring, tiling, bathrooms, kitchen, painting and internal joinery

40–60 weeks — A complete 200 m² refurbishment takes the building time the table above implies, but what throws almost everyone is what comes before: between the pathology study, the project and the major-works licence, three to nine months pass before anyone enters the property. Count that stretch from the start.

Licence and procedures. Major works, always: a project drafted by a competent technician, technical supervision, a health-and-safety study and council charges, which in Catalonia run from 1 to 4% of the execution budget depending on the municipality. If the masía is on the register of protected buildings, the file also goes through heritage and adds months. All of that is in the breakdown above, not hidden in the small print.

A genuinely fixed quote

What the price includes (and what it does not)

Included

  • A dedicated site manager and supervision of the works
  • Labour for every trade under a single contract
  • Materials at the specification stated against each item
  • Access equipment: perimeter scaffolding, protection and stockpiles
  • Waste management, skip and haulage to an authorised tip
  • Certificates and documentation for the new installations
  • Drafting the project and technical supervision (its own item in the table)

Not included

  • VAT: every figure on this page is the taxable base
  • Water connection or well, and extending the power line to the property
  • Furniture, non-built-in appliances and decoration
  • Exterior works: vehicle access, plot boundary walls and landscaping
  • Swimming pool, annexes and outbuildings (hayloft, threshing floor, shed)
  • Structural reinforcement that only appears once opened up and was not in the project
The advice we would give a friend

Where to save on 200 m² — and where never to

Not every cut has the same effect: these are the items where saving is sensible, and the ones where it ends up costing more.

Save here

  • Commission the pathology study before buying, not after
  • Repair and treat timber that keeps its section instead of replacing it
  • Reuse the original tiles: they are worth money and on a listed masía they are compulsory
  • Concentrate the whole envelope in the first phase
  • Keep the openings and the original layout wherever possible

Never save here

  • Leaving the roof for a later phase: whatever is beneath gets done twice
  • Quoting before anyone has climbed onto the roof or opened a trial hole
  • Taking water, power or sewerage for granted before checking them
  • Cement mortar on stone walls: it traps the damp inside the wall
  • Changing technical supervisor halfway through a multi-year job
Comparison

How it compares with other sizes

Functional and mid-range ranges, excluding VAT. The price per metre falls with floor area because the start-up items do not grow.

Floor areaFunctionalMid-range
100 m² masía71,500 – 92,500 €117,000 – 152,000 €
150 m² masía102,000 – 132,000 €169,000 – 218,500 €
300 m² masía174,000 – 225,000 €290,500 – 376,500 €
150 m² house (no stone walls)—See page

* Indicative prices, excluding VAT. They vary with the starting condition of the home, the municipality and the finishes chosen.

Common questions

Questions about the cost of renovating 200 m²

The ones we are asked most before a quote is signed.

How much does it cost to rehabilitate a 200 m² masía in phases?

The same or somewhat more than in one go, not less: the scaffolding, access equipment and technical supervision are repeated in each phase. What you gain is not money, it is time to gather it. The reasonable extra cost of phasing well is between 5 and 10%; phasing badly — leaving the roof for later — can cost far more than that.

What goes into the first phase?

The whole envelope: roof, structure, façade and sewage treatment. It is what stops the deterioration and what cannot be redone without touching what lies beneath. The interior can be left rough without that harming anything.

How do I know whether my masía is listed?

You ask the council for the planning record, and it is free. If it is listed, the record says exactly which elements are protected. Doing it before buying avoids discovering afterwards that the layout you had in mind is not possible.

Can I live in it while the work goes on?

In a complete rehabilitation, no, and in a phased one only if the phase under way is physically separate from the inhabited part, which in a 200 m² masía is sometimes possible. It has to be said in the project, because it changes the access, the protection and the timescales.

Who we are

Full renovations in Barcelona and across Catalonia. A fixed, itemised quote, a dedicated site manager who keeps you informed and a written warranty.

Related services

Guides and calculators

    Want your exact figure, not a range?

    A free site visit, a fixed itemised quote and a written programme. What we sign is what you pay.

    ✆ Call✦ WhatsAppGet a quote →