Price guide · October 2026

The cost of renovating a 150 m² house: what the budget includes and what it does not

The short answer, from the figures in our real quotes: a full renovation of a 150 m² house runs between 79,200 and 100,000 € at a functional specification, between 116,400 and 147,100 € at mid-range and between 163,900 and 207,000 € for high specification. Always excluding VAT. The itemised example budget comes to 83,309 € at functional, with 80 m² of roof and 150 m² of façade inside it. From this size a question appears that does not exist in smaller homes: what do we do about the garage, the basement and the exteriors. They are not in the table, and below we explain why and how we price them.

Finished entrance hall with the door out to the terrace and textured wallpaper — detached-house renovation in Sarrià, Barcelona

Functional

79,200 € – 100,000 €

Standard finishes, layout unchanged

Mid-range

116,400 € – 147,100 €

Selected materials, possible re-planning

High specification

163,900 € – 207,000 €

Premium materials and interior design

Indicative prices · VAT not included · not a binding offer. Your exact figure comes from the free site visit, fixed and itemised.

The starting point

What a 150 m² house is (and what there is besides the 150 m²)

The 150 m² house in the Barcelona area is usually a two-storey single-family home with four bedrooms, two full bathrooms and a kitchen of about 12 m², nine rooms counted for the installations. Between party walls in the town centres of Terrassa, Granollers or Mataró; terraced or semi-detached in the nineties developments of the Vallès and the Baix Llobregat.

The practical difference from a 120 m² house is not the layout: from here on there is almost always floor area that does not count as living space. A garage, a basement, a storage room under the stairs, a porch, a back yard with its drainage. Those metres exist, they cause problems and they cost money — but they are not within the 150 m² priced below.

We say it right at the top because it is the most expensive misunderstanding of this type: comparing a quote that includes the garage with one that does not, and concluding that one is cheaper.

  • 4 bedrooms · 2 full bathrooms · kitchen of about 12 m²
  • 80 m² of roof and 150 m² of façade, over two levels
  • Garage, basement, porch and garden: outside the table, inside the house
Passage between rooms with lacquered doors and continuous large-format flooring — detached-house renovation in Sarrià, Barcelona
Typical price per m²555 – 1,150 €/m²
Passage between rooms with lacquered doors and continuous large-format flooring — detached-house renovation in Sarrià, Barcelona
From our price table, not a template

Itemised example budget: 150 m² house, two bathrooms

Figures calculated item by item from our price table (real, signed quotes), for 150 m² of two-storey living space with four bedrooms, two full bathrooms, a kitchen, 80 m² of roof and 150 m² of façade. It does not include garage, basement or exteriors. Excluding VAT; not a binding offer. The ranges above apply our calculator’s −5% / +20% rule to these totals. With garage, basement and exteriors outside the table, that upper margin is also the room for the surprises this type of house tends to give.

ItemFunctionalMid-rangeHigh spec% of total
Demolition and rubble clearance · floor lifted + strip-out2,804 €3,752 €8,172 €3%
Building work and labouring4,640 €4,719 €5,201 €4%
Plasterboard and suspended ceilings (~60 m²)2,760 €3,240 €3,900 €3%
Plumbing (adaptation + 13 points) · two bathrooms and kitchen3,786 €5,260 €7,328 €4%
Electrics (9 rooms) · with certificate (CIE)2,007 €2,862 €4,941 €2%
Complete bathrooms (~4 m² each) · two rooms: building work, tiling and sanitaryware20,510 €31,518 €40,934 €26%
Complete kitchen (~12 m²) · units, worktop and appliances5,518 €7,650 €14,961 €6%
Roof (80 m²) · complete refurbishment7,760 €13,280 €17,760 €11%
Façade (150 m²) · render and finish4,200 €6,900 €14,400 €6%
Flooring throughout (AC5 timber laminate)5,550 €6,450 €7,200 €5%
Internal joinery (9 doors)2,250 €5,175 €7,020 €4%
Windows (8 units) · if you keep yours, subtract this line4,424 €9,200 €17,728 €8%
Skimming and full repaint · ~450 m² of wall and ceiling surface17,100 €22,500 €22,950 €18%
Total for the example budget83,309 €122,506 €172,495 €
Equivalent per m²555 €/m²817 €/m²1,150 €/m²
The arithmetic of 150 m²

At 150 m², painting already costs more than the roof

This is the size where the curve crosses. The items that do not depend on the metres — the two bathrooms, the kitchen, the services and the roof — come to 39,581 € of the 83,309 € at functional: 48%, already less than half. And at the same time painting, at 450 m² of wall, reaches 17,100 €: for the first time in this series of pages, an item purely proportional to floor area overtakes the roof.

That changes where it pays to look. In a small house the budget is won or lost on the bathroom and the roof. From 150 m², the surface decisions — what gets painted, which flooring is lifted and which kept — move as much money as the services decisions.

What does not change is the order of the technical priorities. That painting costs more than the roof does not mean it matters more: it means there is a lot of wall. The roof remains the item that, badly done, takes all the others down with it.

≈48%Almost fixed cost: kitchen, bathroom, services and roof
≈52%The only thing that scales with the metres
Complete bathroom with a built-in shower and a two-leaf screen, finished — detached-house renovation in Sarrià, Barcelona
Complete bathroom with a built-in shower and a two-leaf screen, finished — detached-house renovation in Sarrià, Barcelona
Honesty about scope

Garage, basement and exteriors: what this table does not include

The figures on this page cover 150 m² of living space: what is heated, lived in and counted on the habitability certificate. In a house this size there are almost always more metres than that, and we prefer to tell you what is left out before you find out by comparing quotes.

Left out are the garage (and the change of use if you want to bring it into the home), the basement and its damp, the porch and exterior paving, the plot boundary walls and the buried drainage and sewerage network. None of them has a per-square-metre figure we can honestly give you: the drainage of a basement depends on the water table and the condition of the buried wall, not on the metres of the house.

What we do is price them as their own visible items, after the trial opening, and tell you which are urgent and which can wait. In our experience the sensible order is almost always the same: first the water that comes in — drainage and roof — then the home, and last the exteriors you enjoy.

A specific warning about the quotes you are going to compare: if one comes in noticeably cheaper, check whether it counts the garage within the metres. Renovating 150 m² of living space and “150 m² including garage” are two different commissions with the same number on the cover.

  • Inside the table: 150 m² of living space, roof and façade
  • Outside: garage, basement, porch, garden, boundary walls and drainage
  • The basement is priced after a trial opening: there is no honest €/m² without seeing it
  • Recommended order: water first, then the home, exteriors last
Finished utility room with washer, dryer and a dark worktop — detached-house renovation in Sarrià, Barcelona
Finished utility room with washer, dryer and a dark worktop — detached-house renovation in Sarrià, Barcelona
Your home is not the “example”

What pushes the price up or down in your case

What pushes it up

  • A damp basementIt is the most expensive and most frequent problem of this type. Perimeter drainage, pumping and treatment of buried walls are not in the table and are priced after a trial opening.
  • Bringing the garage into the homeChanging the use of a garage means insulating it, ventilating it, raising the slab and, almost always, applying for a change of use at the council. It is work that needs a project.
  • Nine rooms with separate servicesAt 150 m² there is no longer a single circuit of anything: electrics rise to 2,007–4,941 € and plumbing to 3,786–7,328 €, with thirteen water points.
  • Painting: 450 m² of wallIt is the item that grows most with the metres, and on this page it is already 17,100–22,950 €, 18% of the mid-range budget. More than the roof.

What brings it down

  • Keeping the flooring of a whole storeyIf the stoneware or timber upstairs is in good condition, lifting it is throwing money away. The flooring item drops from 5,550 € at functional to half.
  • Leaving the basement as a basementDealing with damp and ventilating it costs a fraction of converting it into living space, and deals with most of the real problems a house this size has.
  • Grouping the two bathrooms on the same verticalAt 150 m² there is room to choose where they go: putting them in line saves riser, stack and metres of boxing-in.
  • Doing everything in one jobIn a 150 m² house the temptation to go in phases is strong, and it is expensive: every new round of scaffolding, skips and site management is paid in full again.
Timescales

How long a 150 m² house renovation takes

Weeks 1–3Trial openings, demolition and clearance

Trial openings in the roof and slab and — if there is a basement — for damp in the buried wall. Then the removal of floors and wall finishes in all nine rooms: at 150 m² that is more than 20 m³ of rubble.

Weeks 4–7Roof, façade and exterior joinery

80 m² of roof and 150 m² of façade from a single scaffolding set-up, and the eight window openings replaced and finished in the same step.

Weeks 8–12Services and building work

Plumbing with thirteen points, electrics for nine rooms with a certificate, building work for the two bathrooms and about 60 m² of suspended ceiling.

Weeks 13–18Finishes, painting and handover

The two complete bathrooms, the 12 m² kitchen, flooring, nine doors, 450 m² of skimming and painting, the final clean and a handover walk-round.

14–18 weeks (full renovation with envelope) · 11–13 weeks (interior only) — 14 to 18 weeks for a full renovation with roof and façade. Our closest reference is the 140 m² house in Cerdanyola del Vallès: 12 weeks for a thorough interior refresh, without touching the envelope. Adding roof, façade and the eight window openings is what takes the programme to those 14-18 weeks. If the house also has a damp basement, add two or three weeks of remedial work before the finishes can start. We give the programme in writing with the quote.

Permits: what a 150 m² house needs. With roof and façade in scope, a technical project and a major-works licence, with construction tax on the material execution budget. There are two additional procedures that appear at exactly this size and are worth anticipating: the change of use if the garage is brought into the home, which is settled at the council and can affect the habitability certificate; and the occupation of the public highway for scaffolding and skip, with a daily charge. We handle them and they are itemised as their own lines.

A genuinely fixed quote

What the price includes (and what it does not)

Included

  • A dedicated site manager and planning by zones of the home
  • Labour for every trade under a single contract
  • Materials at the specification stated against each item
  • Certified scaffolding for the roof and façade work
  • Rubble skips and haulage to an authorised handler
  • Protection of the areas kept in use and a final clean
  • CIE certificate and plumbing certificate for each renewed installation
  • Filing the project and whichever building licence applies

Not included

  • VAT is separate: the rate that applies to you is confirmed in writing
  • Council fees and the construction tax, passed on at cost
  • Garage and basement: floor area not counted in the 150 m² of this table
  • Garden, exterior paving, plot boundary walls and drainage network
  • Ducted air conditioning or aerothermal heating: priced separately
  • Loose furniture and decoration
The advice we would give a friend

Where to save on 150 m² — and where never to

Not every cut has the same effect: these are the items where saving is sensible, and the ones where it ends up costing more.

Save here

  • Painting the whole house off-white and saving colour for two rooms
  • Keeping the flooring of the storey that is in better condition
  • Dealing with the basement rather than converting it
  • Smooth lacquered doors finished on site instead of premium catalogue doors

Never save here

  • Perimeter drainage if there is a basement and damp appears
  • Waterproofing the roof over 80 m² of pitch
  • Forced ventilation in interior bathrooms
  • Site management: nine rooms and five trades at once do not coordinate themselves
Comparison

What if it were a 120 or 200 m² house?

From 120 to 150 m² the total rises 13% and the €/m² falls: flooring, painting and façade grow, but the two bathrooms and the kitchen are exactly the same. From 150 to 200 m² the jump is bigger because a third full bathroom appears.

Floor areaFunctionalMid-range
150 m² house (2 bathrooms, 80 m² of roof)83,309 € · 555 €/m²122,506 € · 817 €/m²
120 m² house (2 bathrooms, 65 m² of roof)73,774 € · 615 €/m²109,017 € · 908 €/m²
200 m² house (3 bathrooms, 105 m² of roof)110,824 € · 554 €/m²162,831 € · 814 €/m²

* Indicative prices, excluding VAT. They vary with the starting condition of the home, the municipality and the finishes chosen.

Common questions

Questions about the cost of renovating 150 m²

The ones we are asked most before a quote is signed.

How much does it cost to renovate a 150 m² house?

Between 79,200 and 100,000 € at a functional specification, 116,400–147,100 € at mid-range and 163,900–207,000 € for high specification, excluding VAT. The itemised example budget comes to 83,309 € at functional, for 150 m² of living space with four bedrooms, two bathrooms, a kitchen, 80 m² of roof and 150 m² of façade. It does not include garage, basement or exteriors.

Are the garage and basement in the price?

No, and it matters: the figures on this page cover the 150 m² of living space. The garage, basement, porch, garden and drainage are priced as their own items after the visit. If you are comparing two quotes, the first thing to check is whether they count the same metres, because “150 m² including garage” is a different commission.

How much does it cost to fix damp in a basement?

We do not give a figure on this page because it would be invented. The cost depends on the water table, the condition of the buried wall and whether perimeter drainage with an inspection chamber and pumping is needed or an internal treatment is enough. We assess it after a trial opening and it appears as its own item in the quote, never diluted into “sundries”.

Why does the price per m² fall compared with a 120 m² house?

From 615 to 555 €/m² at functional, because the items that do not depend on floor area — the two bathrooms, the kitchen and the services — are almost the same in both houses and here they are spread over thirty more metres. What does grow is the painting, which at 450 m² of wall is already 17,100 € and overtakes the roof.

Have you renovated a 150 m² house?

The closest is the 140 m² one in Cerdanyola del Vallès, ten metres below this page: 50,000–54,000 € and 12 weeks. It is important to know that the scope there was interior only, with no roof, no façade and no exterior joinery, which is why the figure is well below the table. The figures on this page come from our price table applied to 150 m², not from that job.

How long does it take, and can you live in it?

14 to 18 weeks with the envelope included. Living in the house is possible floor by floor during the interior phase, but not during the four weeks of scaffolding: with the roof open and the façade chipped back, the house is not habitable. In a 150 m² house with two wings or two well-separated storeys, it is usual to stay for the second half of the job and not the first.

Do these prices include VAT?

No. Everything you see here is excluding VAT. The rate — 10% or 21% — depends on three conditions: private use, a building at least two years old and materials below 40% of the budget. We check it against your case and put it in the offer.

Who we are

Full renovations in Barcelona and across Catalonia. A fixed, itemised quote, a dedicated site manager who keeps you informed and a written warranty.

Related services

Guides and calculators

Want your exact figure, not a range?

A free site visit, a fixed itemised quote and a written programme. What we sign is what you pay.

✆ Call✦ WhatsAppGet a quote →