The cost of renovating a 250 m² detached house: where the kitchen stops running the budget

The short answer, from the figures in our real quotes: a full renovation of a 250 m² detached house runs between 123,300 and 155,800 € at a functional specification, between 181,000 and 228,600 € at mid-range and between 252,400 and 318,800 € for high specification. Always excluding VAT. The itemised example budget comes to 129,757 € at functional — 519 €/m², the lowest price per metre on any of our house and detached-house pages. And there is a reason worth understanding before you ask for a quote: at 250 m², the items that do not depend on floor area drop to 45% of the total. For the first time, floor area is what drives the price.

Dark wall-to-wall bookcase with the fireplace in the centre, in the finished living room — detached-house renovation in Sarrià, Barcelona

Functional

123,300 € – 155,800 €

Standard finishes, layout unchanged

Mid-range

181,000 € – 228,600 €

Selected materials, possible re-planning

High specification

252,400 € – 318,800 €

Premium materials and interior design

Indicative prices · VAT not included · not a binding offer. Your exact figure comes from the free site visit, fixed and itemised.

The starting point

What a 250 m² detached house is and why it gets renovated

At 250 m² the brief is no longer a list of rooms: it is twelve rooms. Five bedrooms, three full bathrooms, a WC, a kitchen of about 16 m², a main living room — often double height — a separate dining room, a study and a service area with a utility room. Thirteen window openings and thirteen internal doors.

These are eighties and nineties houses in the established developments of the Vallès, the Maresme and the Collserola foothills, and they reach renovation for one of two reasons: a change of owner — bought to live in for twenty years and redone entirely — or a change of family stage, when the children leave and half the house changes use.

What sets this type apart in the budget is the inversion of weights. The fixed items fall to 45% of the functional total, the lowest percentage on these pages along with the 300 m² detached house. Put the other way round: here, for the first time, most of the budget depends on how many metres have to be painted, floored and finished, not on how many bathrooms there are.

  • 12 rooms · 3 bathrooms + WC · kitchen of about 16 m²
  • 130 m² of roof and 240 m² of façade
  • Fixed items: 45% of the total, the minimum on these pages
Kitchen island with a slatted timber shelf under a quartz worktop — detached-house renovation in Sarrià, Barcelona
Typical price per m²519 – 1,063 €/m²
Kitchen island with a slatted timber shelf under a quartz worktop — detached-house renovation in Sarrià, Barcelona
From our price table, not a template

Itemised example budget: 250 m² detached house

Figures calculated item by item from our price table (real, signed quotes), for 250 m² of living space with five bedrooms, three full bathrooms, a WC, a kitchen, 130 m² of roof and 240 m² of façade. It does not include air conditioning, home automation or the plot. Excluding VAT; not a binding offer. The bands above are these same totals with the −5% / +20% rule. At this size the upper 20% is not padding: it is the 750 m² of wall and the thirteen joinery openings, where a finishing decision gets multiplied many times over.

ItemFunctionalMid-rangeHigh spec% of total
Demolition and rubble clearance · floor lifted + strip-out4,716 €6,308 €13,788 €3%
Building work and labouring7,520 €7,599 €8,241 €4%
Plasterboard and suspended ceilings (~100 m²) · includes boxing-in on slopes4,600 €5,400 €6,500 €3%
Plumbing (adaptation + 20 points) · three bathrooms, WC and kitchen5,606 €7,808 €10,905 €4%
Electrics (12 rooms) · with certificate (CIE)2,676 €3,816 €6,588 €2%
Complete bathrooms (~4 m² each) · three rooms: building work, tiling and sanitaryware30,765 €47,277 €61,401 €25%
Second WC (~2 m²) · toilet, basin and tiling837 €1,286 €2,161 €1%
Complete kitchen (~16 m²) · units, worktop and appliances5,518 €7,650 €14,961 €4%
Roof (130 m²) · complete refurbishment12,610 €21,580 €28,860 €11%
Façade (240 m²) · four orientations6,720 €11,040 €23,040 €6%
Flooring throughout (AC5 timber laminate)9,250 €10,750 €12,000 €6%
Internal joinery (13 doors)3,250 €7,475 €10,140 €4%
Windows (13 units) · if you keep yours, subtract this line7,189 €14,950 €28,808 €8%
Skimming and full repaint · ~750 m² of wall and ceiling surface28,500 €37,500 €38,250 €20%
Total for the example budget129,757 €190,439 €265,643 €
Equivalent per m²519 €/m²762 €/m²1,063 €/m²
The inverted arithmetic

At 250 m², the part that scales is already the majority

On all the earlier pages of this series the argument was the same: the fixed items — bathrooms, kitchen, services, roof — take more than half the budget, so compare items and not metres. Here that argument turns upside down.

At 250 m² the fixed items come to 58,012 € of the 129,757 € at functional: 45%. A minority. And the second item in the budget is no longer the kitchen or the roof: it is painting, at 37,500 € at mid-range over 750 m² of wall — 20% of the total, more than roof and façade together (32,620 €).

That changes which questions to ask. In a small house the useful conversation is about waterproofing and stacks. In a 250 m² detached house, on top of that, you have to talk about how many square metres have to be painted and how many different finishes there will be, because at this scale a finishing decision multiplied by 750 m² moves more money than an entire bathroom.

≈45%Almost fixed cost: kitchen, bathrooms, services and envelope
≈55%The only thing that scales with the metres
Basin under a granite worktop with palm-leaf wallpaper, in the finished WC — detached-house renovation in Sarrià, Barcelona
Basin under a granite worktop with palm-leaf wallpaper, in the finished WC — detached-house renovation in Sarrià, Barcelona
What the table cannot price

Double height and zoned climate control: two decisions taken at the start

A 250 m² detached house almost always has at least one room that does not behave like the others: the double-height living room, or a room under the roof with the ceiling following the slope. What you see in the photo is exactly that: moisture-resistant plasterboard boxing-in working out a slope in our detached house in Sarrià, before closing.

Those rooms are not dearer per metre of floor: they are dearer per metre of ceiling and high wall. Internal scaffolding or a lifting platform is needed for the plasterboard fitter, the electrician and the painter; painting a six-metre wall cannot be done from a stepladder; and any light fitting going up there has to be decided and wired before closing, because there is no going back afterwards.

The second decision is the climate, and it is not in the table either. In twelve rooms with different orientations, a single thermostat is no good: either you go by zones — ducts with motorised dampers, or underfloor heating with manifolds on each floor — or you accept that half the house is always at a temperature nobody asked for. We do not put a figure here because it would depend on the system, the number of zones and whether the house can take a raised screed; we price it separately, itemised and with the zoning scheme on the plan.

What we recommend without qualification, whatever it ends up costing: reserve the routes and leave the manifolds accessible even if the climate system is installed later. It is cheap to do with the job open and very expensive afterwards.

On home automation we will be equally clear: our price table has no figures of its own for zone control, motorised shutters or automatic irrigation, and we are not going to invent a range. We price it with a specialist installer and the quote arrives as a separate item, with brand and scope in plain view.

  • Double height: the extra cost is in the equipment, not the metres of floor
  • Zoned climate control and underfloor heating: outside the table, priced separately
  • Reserve risers and leave manifolds accessible, always
  • Home automation: no figure in our price table — it is quoted with the installer
Moisture-resistant plasterboard ceiling working out the slope in a room with a sloping ceiling, mid-works — detached-house renovation in Sarrià, Barcelona
Moisture-resistant plasterboard ceiling working out the slope in a room with a sloping ceiling, mid-works — detached-house renovation in Sarrià, Barcelona
Your home is not the “example”

What pushes the price up or down in your case

What pushes it up

  • A double-height living roomEverything around it gets dearer: internal scaffolding to work on ceilings six metres up, lifting equipment, plasterboard following the slope and painting, which at that height is no longer done from a stepladder.
  • Zoned air conditioning in a 250 m² houseTwelve rooms with different orientations and uses are not conditioned with one thermostat. Manifolds, motorised dampers and a control unit are another job and are not in the table.
  • 750 m² of wall to paintIt is the second item in the budget: 28,500–38,250 € for skimming and painting alone. At this size, choosing a finish that needs two more coats shows up in thousands of euros, not hundreds.
  • Thirteen window openings of unusual sizesBig detached houses have picture windows that are not catalogue items. The item runs from 7,189 to 28,808 € and the jump is not about quality: it is made-to-measure manufacture.

What brings it down

  • Plenty of “cheap” metresIt is what makes the €/m² the lowest on these house and detached-house pages. A hall, a dressing room or a games room cost flooring, paint and little else: they dilute the cost of the bathrooms and kitchen.
  • Keeping the kitchen where it is even if it is renewed completelyAt 250 m² the kitchen is only 4% of the mid-range budget. Moving it, on the other hand, drags plumbing, electrics and extraction along, and that does show.
  • Painting the whole house in one rangeWith 750 m² of wall, the painter’s output rules. One range, one finish and fewer colour cut-ins is the difference between 28,500 and quite a lot more.
  • Doing the four wet rooms in the same stretch of the jobThree bathrooms and a WC carried out one after another share stacking, tradesman and equipment. Spreading them through the job multiplies the trips.
Timescales

How long a 250 m² detached house renovation takes

Weeks 1–4Access, trial openings and demolition by zone

At 250 m² demolition is no longer a short phase: it is twelve rooms, more than 30 m³ of rubble and a skip logistics that is planned from day one.

Weeks 5–10Envelope: 130 m² of roof and 240 m² of façade

Six weeks of perimeter scaffolding for roof, façade and the thirteen joinery openings. In a house this size the roof usually has several pitches and some added volume.

Weeks 11–18Services, light ceiling structure and building work

Twenty plumbing points, electrics for twelve rooms with a certificate and 100 m² of suspended ceiling, including the boxing-in that follows the slope in the double-height areas. If underfloor heating or zoned climate control is going in, it is here.

Weeks 19–26Finishes, painting and handover

Three bathrooms, a WC, a 16 m² kitchen, flooring, thirteen doors and 750 m² of skimming and painting. Handover is by zone, with a signed walk-round room by room.

20–26 weeks (the house, with envelope) · the plot, separately — 20 to 26 weeks for a full renovation with the roof and four façades. Here we do have a very closely matched reference of our own: the 260 m² detached house in Sarrià, Barcelona, took 24 weeks for 113,000–124,000 €. Ten metres more than this page and a timescale within the range — although it is worth knowing that the scope recorded in its project file is interior (underfloor heating, living room, kitchen, five bathrooms and staircase) and does not include roof or façade, which is what explains its figure falling below the table. The programme is delivered by zone.

Permits: major works and, sometimes, something more. A signed-off project, technical supervision and a major-works licence, with construction tax on an execution budget that at this size is already considerable: it is better seen itemised in the quote and not hidden in “paperwork”. Two things that appear at exactly this scale: if the double-height living room is divided or closed to gain a floor, the countable floor area changes and that means amending the habitability certificate; and if aerothermal heating or a powerful outdoor unit is installed, several municipalities regulate its position relative to the boundary. We check before quoting.

A genuinely fixed quote

What the price includes (and what it does not)

Included

  • A dedicated full-time site manager and a phasing plan by zone
  • Labour for every trade under a single contract
  • Materials at the specification stated against each item
  • Perimeter scaffolding and lifting equipment for the double-height areas
  • Rubble removed in successive skips by an authorised handler
  • Protection of the garden, access routes and trees on the boundary
  • Electrical and plumbing certificates for each renewed installation
  • Signed-off project, technical supervision and all council paperwork

Not included

  • VAT is not included: the offer separates base, applicable rate and total
  • Council fees and the construction tax, itemised at cost
  • Zoned air conditioning, underfloor heating and aerothermal heating: an item of their own
  • Home automation, zone control, motorised shutters and automatic irrigation
  • Everything outside the house: garden, paving, boundary walls, drainage and swimming pool
  • Loose furniture, interior design and decoration
The advice we would give a friend

Where to save on 250 m² — and where never to

Not every cut has the same effect: these are the items where saving is sensible, and the ones where it ends up costing more.

Save here

  • A single paint range across the 750 m² of wall
  • Continuous flooring in one format throughout the main floor
  • Making the fourth wet room a WC rather than a full bathroom
  • Catalogue exterior joinery in the standard openings and made-to-measure only for the picture windows

Never save here

  • Lifting equipment for double-height work: there is no safe way to save on it
  • Reserving risers and routes for the climate system, even if the system is installed later
  • Waterproofing 130 m² of roof with several pitches
  • Access to the manifolds: an inaccessible technical cupboard is a guaranteed breakdown
Comparison

What if the detached house were 200 or 300 m²?

Look at the €/m² column: between 200 and 250 m² it falls from 560 to 519 € at functional, and between 250 and 300 it stays flat. That plateau is the sign that, from 250 m², adding floor area no longer makes anything cheaper — it only adds paint, flooring and doors.

Floor areaFunctionalMid-range
250 m² detached house (3 bathrooms + WC)129,757 € · 519 €/m²190,439 € · 762 €/m²
200 m² detached house (3 bathrooms)111,937 € · 560 €/m²164,901 € · 825 €/m²
300 m² detached house (4 bathrooms)156,195 € · 521 €/m²229,210 € · 764 €/m²

* Indicative prices, excluding VAT. They vary with the starting condition of the home, the municipality and the finishes chosen.

Common questions

Questions about the cost of renovating 250 m²

The ones we are asked most before a quote is signed.

How much does it cost to renovate a 250 m² detached house?

Between 123,300 and 155,800 € at a functional specification, 181,000–228,600 € at mid-range and 252,400–318,800 € for high specification, excluding VAT. The itemised example budget comes to 129,757 € at functional, for 250 m² of living space with five bedrooms, three bathrooms, a WC, a kitchen, 130 m² of roof and 240 m² of façade.

Why is the price per m² the lowest on these pages?

Because at 250 m² the items that do not depend on floor area — bathrooms, WC, kitchen, services and roof — drop to 45% of the functional total, the minimum on these pages. There are plenty of metres of hall, dressing room and rooms that only cost flooring and paint, and that dilutes the fixed cost: 519 €/m² against the 665 €/m² of an 80 m² house.

What is the second most expensive item after the bathrooms?

Painting. With 750 m² of wall it is 37,500 € at mid-range, 20% of the budget, above roof and façade together (32,620 €). It is a good reminder that at this scale finishing decisions multiplied by floor area move more money than a whole wet room.

How much does a double-height living room cost?

It is not an item with a price of its own: the extra cost is spread across plasterboard, painting, electrics and equipment, because working at six metres requires internal scaffolding or a platform. What is critical is the order: the lighting for the upper zone has to be decided and wired before the ceilings are closed, because they are never opened again.

Is zoned air conditioning in the price?

No. There is no climate item in the table because the cost depends on the system, the number of zones and whether the house can take a raised screed for underfloor heating. We price it separately, itemised and with a zoning scheme on the plan. What we always do within the job is reserve the routes and leave the manifolds accessible, even if the climate system is installed later.

Do you have a finished 250 m² detached house?

Practically: the one in Sarrià, Barcelona, is 260 m², ten more than this page. It took 24 weeks and 113,000–124,000 €, with underfloor heating, a living room with exposed beams and a fireplace, a classic kitchen with an island and five bathrooms. Its figure falls below the table because the scope recorded in its project file is interior and does not include roof or façade. Its project page is not yet published; the site photographs on this page are from it.

Do these prices include VAT?

No. These figures are excluding VAT. Given the amount of a job this size, the applicable rate is one of the first things we check: 10% reduced if the main-residence, age and materials-weight conditions are met; 21% if not. It is written and calculated in the offer.

Who we are

Full renovations in Barcelona and across Catalonia. A fixed, itemised quote, a dedicated site manager who keeps you informed and a written warranty.

Related services

Guides and calculators

    Want your exact figure, not a range?

    A free site visit, a fixed itemised quote and a written programme. What we sign is what you pay.