The cost of renovating a 200 m² detached house: the Vallès standard, item by item

The short answer, from the figures in our real quotes: a full renovation of a 200 m² detached house runs between 106,400 and 134,400 € at a functional specification, between 156,700 and 197,900 € at mid-range and between 218,800 and 276,400 € for high specification. Always excluding VAT. The itemised example budget comes to 111,937 € at functional, with three bathrooms, 105 m² of roof and 200 m² of façade on four orientations. This is the standard detached house of Valldoreix, Matadepera, Bellaterra and La Floresta, built between 1975 and 1995 and today with its envelope worn out.

Living room with an exposed-beam ceiling and the picture window open to the pool — detached-house renovation in Sarrià, Barcelona

Functional

106,400 € – 134,400 €

Standard finishes, layout unchanged

Mid-range

156,700 € – 197,900 €

Selected materials, possible re-planning

High specification

218,800 € – 276,400 €

Premium materials and interior design

Indicative prices · VAT not included · not a binding offer. Your exact figure comes from the free site visit, fixed and itemised.

The starting point

What the 200 m² detached house of the Vallès is

It is a very recognisable profile: a freestanding two-storey home on a plot of 400 to 800 m², four or five bedrooms, three full bathrooms, a kitchen of about 15 m² and eleven window openings. Valldoreix, Matadepera, Bellaterra, La Floresta, Mira-sol, Cabrils, Alella: the developments of the Vallès and the Maresme are made of these houses, almost all built between 1975 and 1995.

What usually leads owners to renovate them is not the layout, which generally works: it is that the envelope has reached the end of its life all at once. Displaced tiles, rusted gutters, aluminium joinery without a thermal break and a façade that has had two repaints. And inside, bathrooms and a kitchen of the period.

The fact that best sums up this type: it has 200 m² of façade and only 105 m² of roof. It is the largest façade area of any 200 m² home in this series — a house between party walls of the same size has 180 — and that changes where it pays to put the money.

  • 4-5 bedrooms · 3 full bathrooms · kitchen of about 15 m²
  • 200 m² of façade against 105 m² of roof: almost double
  • Built between 1975 and 1995: worn-out envelope, layout still valid
The interior staircase with textured wallpaper and natural light coming in from above — detached-house renovation in Sarrià, Barcelona
Typical price per m²560 – 1,152 €/m²
The interior staircase with textured wallpaper and natural light coming in from above — detached-house renovation in Sarrià, Barcelona
From our price table, not a template

Itemised example budget: 200 m² detached house

Figures calculated item by item from our price table (real, signed quotes), for 200 m² of two-storey living space with five bedrooms, three full bathrooms, a kitchen, 105 m² of roof and 200 m² of façade on four orientations. It does not include air conditioning or the plot. Excluding VAT; not a binding offer. The upper ranges apply to these totals the −5% / +20% rule shared by all our pricing tools. It is asymmetric on purpose: a quote that has to be raised after the technical visit costs trust; one that ends up slightly under does not.

ItemFunctionalMid-rangeHigh spec% of total
Demolition and rubble clearance · floor lifted + strip-out3,760 €5,030 €10,980 €3%
Building work and labouring6,080 €6,159 €6,721 €4%
Plasterboard and suspended ceilings (~80 m²)3,680 €4,320 €5,200 €3%
Plumbing (adaptation + 18 points) · three bathrooms and kitchen5,086 €7,080 €9,883 €4%
Electrics (10 rooms) · with certificate (CIE)2,230 €3,180 €5,490 €2%
Complete bathrooms (~4 m² each) · three rooms: building work, tiling and sanitaryware30,765 €47,277 €61,401 €29%
Complete kitchen (~15 m²) · units, worktop and appliances5,518 €7,650 €14,961 €5%
Roof (105 m²) · complete refurbishment10,185 €17,430 €23,310 €11%
Façade (200 m²) · four orientations5,600 €9,200 €19,200 €6%
Flooring throughout (AC5 timber laminate)7,400 €8,600 €9,600 €5%
Internal joinery (11 doors)2,750 €6,325 €8,580 €4%
Windows (11 units) · if you keep yours, subtract this line6,083 €12,650 €24,376 €8%
Skimming and full repaint · ~600 m² of wall and ceiling surface22,800 €30,000 €30,600 €18%
Total for the example budget111,937 €164,901 €230,302 €
Equivalent per m²560 €/m²825 €/m²1,152 €/m²
The arithmetic of the 200 m² detached house

What you cannot see in a detached house faces the weather on four sides

The items that do not move with the metres — three bathrooms, kitchen, services and roof — come to 53,784 € of the 111,937 € at functional: 48%. Exactly the same percentage as in a 200 m² house between party walls, because wet rooms and kitchens do not know whether the house is detached or not.

What does know it is detached is the envelope. Four exposed faces mean four times as many junctions, four times as many finishing details and four orientations with different needs: the north face asks for insulation, the south asks for sun protection, and the two sides are usually the ones nobody looks at until the stain appears.

That is why, on this type of house, the useful question is not what a square metre of home costs: it is what a square metre of skin costs. And the answer in the table is 46 €/m² of façade at mid-range over the 200 m² of exterior wall — before deciding whether to insulate as well.

≈48%Almost fixed cost: kitchen, bathrooms, services and envelope
≈52%The only thing that scales with the metres
Underfloor heating circuits laid beside the new joinery of the picture window — detached-house renovation in Sarrià, Barcelona
Underfloor heating circuits laid beside the new joinery of the picture window — detached-house renovation in Sarrià, Barcelona
What being detached costs

Four façades open to the air: 200 m² of skin and 105 of roof

This is the only size in the series where the façade almost doubles the roof: 200 m² of exterior wall against 105 m² of roof. In a single-storey village house the proportion is the opposite, and in a flat the problem simply does not exist because the party walls belong to someone else.

What that proportion means in euros: façade and exterior joinery come to 21,850 € at mid-range — 13% of the budget, against 17,430 € for the roof. The skin costs more than the roof, and in a detached house that gap only widens.

And it means something more important than money: in a detached house, most of the energy is lost through the wall, not through the top. If the aim of the renovation is for the house to stop being expensive to heat, the rational order is joinery first, façade second and climate last — and not the other way round, which is the order in which it is usually planned.

A practical note on the eleven windows: in a detached house they face four orientations and should not all be solved the same way. The south face welcomes sun protection; the north, the best thermal performance you can afford; and the sides, the ones nobody looks at, are the ones that fail most because they are the ones least inspected.

  • 200 m² of façade against 105 m² of roof
  • Façade + joinery at mid-range: 21,850 €, 13% of the total
  • The roof, at 17,430 €, comes in below the wall
  • Rational order to stop paying for heating: windows, façade, climate
Finished room with the new window and the radiator under the opening — detached-house renovation in Sarrià, Barcelona
Finished room with the new window and the radiator under the opening — detached-house renovation in Sarrià, Barcelona
Your home is not the “example”

What pushes the price up or down in your case

What pushes it up

  • Four façades with poor thermal orientationAn eighties detached house with an uninsulated cavity wall loses heat through 200 m² of enclosure. Insulating from outside solves the problem at the root, but it is not in the table and it is a project decision.
  • Eleven exterior joinery openingsIt is the item that jumps most between specifications: from 6,083 € in functional aluminium to 24,376 € at high specification. In a detached house those openings face four different directions and none has the same solution.
  • A four-pitch roof with valleysThe roof of a detached house is rarely a clean slope: every valley, every dormer and every chimney is a junction that has to be solved and where water tries to get in.
  • A development with its own ordinanceIn Valldoreix, Bellaterra or Matadepera, the colour of the façade, the roofing material and the plot boundary wall are often regulated. It does not make the job dearer, but it can force specific materials.

What brings it down

  • Keeping the joinery that is soundWith eleven openings, keeping half is the most immediate saving in the table, and in a nineties detached house with thermally broken aluminium it is usually justified.
  • Doing the four façades from a single scaffoldPerimeter scaffolding is half the logistics of the job. Putting it up once for roof, façade and joinery is what keeps the envelope at 16% of the budget.
  • Three bathrooms on two verticalsIf two of the three share a stack, the plumbing stays as adaptation instead of needing new risers.
  • A plot with vehicle access to the façadeLorry at the foot of the job, skip inside the plot and material unloaded once: it is not an item, it is a discount spread across the whole job.
Timescales

How long a 200 m² detached house renovation takes

Weeks 1–3Access, trial openings and demolition

Site track, stacking area, protection of the garden and the trees. A trial opening in the roof and services, and demolition of the ten rooms spread over two floors.

Weeks 4–9The full envelope

105 m² of roof with its junctions, 200 m² of façade on four faces and the eleven joinery openings. Six weeks during which the house is closed to the outside and cannot be lived in.

Weeks 10–16Services, building work and ceilings

Eighteen plumbing points for the three bathrooms and the kitchen, electrics for ten rooms with a certificate, 80 m² of suspended ceiling. If ducted air conditioning or underfloor heating is going in, it is done here.

Weeks 17–24Finishes, painting and handover

Three complete bathrooms, a 15 m² kitchen, flooring, eleven doors, 600 m² of skimming and painting, the final clean and a room-by-room handover walk-round.

18–24 weeks (the house, with envelope) · the plot, separately — 18 to 24 weeks for a full renovation with the roof and four façades. Our own reference is the 260 m² detached house in Sarrià, Barcelona: 24 weeks of work for underfloor heating, living room, kitchen, five bathrooms and staircase. Within this page’s 18-24 weeks there are six in which the house is closed up on the outside and cannot be lived in; the rest can be planned floor by floor if there is somewhere to stay. The programme comes in writing and by phase, never as a single date.

Permits: the development’s ordinance rules. A signed-off technical project, technical supervision and a major-works licence, because the roof and façade are touched. The particularity of this type is the planning: in Valldoreix, Bellaterra, Matadepera and a good part of the Vallès developments there are ordinances of their own that regulate the colour and material of the façade, the type of tile, the height of the plot boundary wall and sometimes even the species of the trees on the boundary. It does not make the job dearer, but it conditions decisions that are better taken before quoting, not after. We check with the council and handle the paperwork.

A genuinely fixed quote

What the price includes (and what it does not)

Included

  • A dedicated site manager and a plan for access and stacking inside the plot
  • Labour for every trade under a single contract
  • Materials at the specification stated against each item
  • Perimeter scaffolding on all four façades, put up and taken down
  • Rubble removal in successive skips, with an authorised handler
  • Protection of the garden, the exterior paving and the trees on the boundary
  • CIE certificate and plumbing certificates for everything newly installed
  • Technical project, technical supervision and licence handling

Not included

  • VAT is separate, with the rate confirmed in writing before you sign
  • Council fees and the construction tax, passed on at cost
  • Air conditioning, aerothermal heating or underfloor heating: an item of its own and a design decision
  • External thermal insulation of the four façades
  • The whole plot: garden, paving, boundary walls, drainage and swimming pool
  • Loose furniture and decoration
The advice we would give a friend

Where to save on 200 m² — and where never to

Not every cut has the same effect: these are the items where saving is sensible, and the ones where it ends up costing more.

Save here

  • Keeping the joinery openings that retain their watertightness
  • Coloured single-coat render on the faces that do not face the main façade
  • A guest WC instead of the third full bathroom
  • Leaving the garden and exterior paving for a second phase

Never save here

  • Junctions and valleys on a four-pitch roof
  • Watertightness of the eleven openings: badly finished joinery ruins the new façade
  • The consumer unit and earthing in eighties installations
  • Certified perimeter scaffolding: on four façades there is no safe way to improvise
Comparison

What if it were 150, 250 m² — or a house between party walls?

Look at the last row: a 200 m² house between party walls comes out 1,113 € cheaper at functional, and that difference is exactly twenty more square metres of façade and one more window opening. Being detached costs, but not much; what is expensive about a detached house is the plot, which is in none of these rows.

Floor areaFunctionalMid-range
200 m² detached house (3 bathrooms, 200 m² façade)111,937 € · 560 €/m²164,901 € · 825 €/m²
150 m² detached house (2 bathrooms + WC)85,499 € · 570 €/m²126,130 € · 841 €/m²
250 m² detached house (3 bathrooms + WC)129,757 € · 519 €/m²190,439 € · 762 €/m²
200 m² house between party walls110,824 € · 554 €/m²162,831 € · 814 €/m²

* Indicative prices, excluding VAT. They vary with the starting condition of the home, the municipality and the finishes chosen.

Common questions

Questions about the cost of renovating 200 m²

The ones we are asked most before a quote is signed.

How much does it cost to renovate a 200 m² detached house?

Between 106,400 and 134,400 € at a functional specification, 156,700–197,900 € at mid-range and 218,800–276,400 € for high specification, excluding VAT. The itemised example budget comes to 111,937 € at functional, for 200 m² of living space with five bedrooms, three full bathrooms, a kitchen, 105 m² of roof and 200 m² of façade. It does not include air conditioning or the plot.

How much more does a detached house cost than a 200 m² house between party walls?

1,113 € at functional: 111,937 € against 110,824 €. That difference is exactly twenty more square metres of façade and one more window opening. It is little, and it surprises almost everyone: what is expensive about a detached house is not standing free, it is the plot, which is in neither table.

What costs more in a detached house, the façade or the roof?

The façade, and it is the only size in this series where that happens. At mid-range it is 9,200 € of façade plus 12,650 € of exterior joinery, 21,850 € in all, against 17,430 € for the roof. The reason is geometry: 200 m² of wall against 105 m² of roof.

Is external thermal insulation included?

No. The façade figures on this page are for render and finish. An external insulation system on all four faces is a different job: it changes thicknesses, sills, window finishing and gutters, and it is decided before the scaffolding goes up. We price it separately and with measurements, never as a percentage added on.

What do the ordinances of Valldoreix, Bellaterra or Matadepera say?

That in many of those developments the colour and material of the façade, the type of roof and the height of the plot boundary wall are regulated, and that changing them needs prior approval. It is not a surcharge, but it is a restriction on materials worth knowing before you choose finishes. We check with the council before quoting.

Do you have a renovated detached house of this size to show?

The closest is the 260 m² one in Sarrià, Barcelona: 113,000–124,000 € and 24 weeks, with underfloor heating, five bathrooms, a classic kitchen with an island and a living room with exposed beams. It is sixty metres more than this page and its scope was interior, so it is a reference for level and timescale, not for price. Its project page is not yet published; the site photographs on this page are from it.

Do these prices include VAT?

No. They are base prices. The applicable VAT rate is determined case by case — 10% reduced for a home in private use at least two years old with materials below 40%, 21% otherwise — and appears itemised in the quote, with its base and its total.

Who we are

Full renovations in Barcelona and across Catalonia. A fixed, itemised quote, a dedicated site manager who keeps you informed and a written warranty.

Related services

Guides and calculators

    Want your exact figure, not a range?

    A free site visit, a fixed itemised quote and a written programme. What we sign is what you pay.