Fixed and variable renovation costs: which items do not depend on floor area

Bathroom, kitchen and services do not depend on floor area and make up 46 to 58% of a renovation. They set the floor below which a budget cannot go.

By the Tu Nuevo Piso teamPublished 2 November 202610 min read
Newly renovated kitchen and bathroom of a flat seen from the hallway

Indicative prices · VAT not included. Not a binding offer.

Which renovation items do not depend on floor area?

The renovation items that do not depend on floor area are the wet areas and the services: bathroom, kitchen, plumbing and electrics cost practically the same in a 50 m² flat as in a 90 m² one. In our standard quotes they make up 58% of the functional total at 50 m² and 46% at 90 m², while flooring, painting, plasterboard, rubble removal and doors grow with the surface area.

This split explains almost everything that surprises people in a renovation budget: why a small flat does not fall below a certain figure, why a large one does not shoot up, and where it makes sense to cut back. The figures come from our price table, built from real signed quotes, and are guide figures excluding VAT.

Key points

  • Bathroom, kitchen, plumbing and electrics make up between 46% and 58% of the functional budget in our seven standard types from 50 to 120 m².
  • A full bathroom of about 4 m² costs 10,255 € in functional, 15,759 € in mid-range and 20,467 € in high-end, whatever the size of the flat.
  • Bathroom plus kitchen form a floor of 15,773 € in functional, 23,409 € in mid-range and 35,428 € in high-end, before a single wall is painted.
  • In the 50 m² flat, fixed items add up to 19,083 € and variable items to 13,899 €: the bathroom, kitchen and services cost more than everything else together.

What a fixed cost and a variable cost mean in a renovation

A fixed cost is an item whose price does not change with the flat's floor area, and a variable cost is one that grows with it. A bathroom costs the same in 50 m² as in 90 m² because it has the same fittings: toilet, basin, shower, tiling and waterproofing. The floor of a 90 m² flat, on the other hand, costs more than that of a 50 m² one because there is more floor.

The classification comes from the building site, not from accounting, and the line sometimes blurs. Some variable items grow per unit rather than per metre (one more door, one more window), and fixed items jump when the flat adds another wet area. This is the table we work with:

ItemTypeWhat makes it growFunctional reference
Full bathroom (~4 m²)FixedThe number of bathrooms10,255 € per bathroom
Full kitchenFixedThe quality of units, worktop and appliances5,518 €, from 6 to 12 m²
PlumbingFixedThe water supply and drainage points2,230 € with seven points
ElectricsFixedThe number of rooms1,080 € with five rooms
Licences and techniciansFixedThe type of procedure106-2,450 €
Auxiliary equipment and protectionFixedThe building and how the works are organised151 € per unit
Demolition and rubble removalVariableThe metres taken up950 € in 50 m², 1,708 € in 90 m²
FlooringVariableThe metres of floor37 €/m² in AC5 wood flooring
Smoothing and paintingVariableThe metres of wall and ceiling5,760 € in 50 m², 10,260 € in 90 m²
Plasterboard and false ceilingsVariableThe metres of partition and ceiling46 €/m²
Interior doorsVariable per unitThe number of doors250 € each
WindowsVariable per unitThe number of openings553 € each

Guide prices · VAT not included. References from our price table and from the standard 50 and 90 m² quotes; they are not a binding offer and the fixed quote comes after the free technical visit.

Look at the third column. No fixed item grows with floor area, but almost all grow with something: bathrooms, rooms, water points or the type of procedure. That is why "fixed" does not mean "the same in every flat", but "the same in flats with the same layout".

The real split in seven standard quotes

In our seven standard quotes, fixed items make up between 46% and 58% of the total at functional quality. The maximum is in the smallest flat and the minimum in the 90 m² one, just before a second full bathroom comes in.

Floor areaWet areasFixed (functional)WeightVariable (functional)WeightWeight of fixed in mid-range
50 m²1 bathroom19,083 €58%13,899 €42%59%
60 m²1 bathroom19,374 €54%16,834 €46%54%
70 m²1 bathroom19,597 €51%19,206 €49%51%
80 m²Bathroom and WC21,177 €49%22,195 €51%50%
90 m²Bathroom and WC21,177 €46%24,381 €54%47%
100 m²2 full bathrooms31,598 €54%27,370 €46%55%
120 m²2 full bathrooms31,821 €49%32,481 €51%51%

Guide prices · VAT not included. Fixed = plumbing, electrics, bathrooms, WC and kitchen; variable = everything else. These are standard quotes with a defined scope, not binding offers.

Read the fixed column in euros, not in percentages. From 50 to 70 m² it barely moves, from 19,083 € to 19,597 €, while the variable items rise from 13,899 € to 19,206 €. That is how a fixed cost behaves: it does not grow, and it weighs less as the flat grows around it.

At 80 and 90 m² the fixed items are identical, 21,177 €, because both types have a bathroom, a WC, ten plumbing points and seven rooms with electrics. The ten metres of difference fall entirely on the variable items.

And at 100 m² the weight rises again, to 54%. This is not an effect of floor area, it comes from the second full bathroom: fixed items go from 21,177 € to 31,598 €. In mid-range quality the pattern repeats, with 59% at 50 m² and 47% at 90 m². What that curve does to the price per metre has its own article.

Empty room with newly laid light oak flooring and painted walls
Flooring and paint: items that do grow with every square metre.

Items that look variable but not entirely

Plumbing, electrics, windows and doors do not grow per metre: they grow in steps, when the flat adds a bathroom, a room or an opening in the facade. Just look at the standard quotes in pairs:

  • Plumbing: 2,486 € in 60 m² and in 70 m², with eight points; 3,006 € in 80 m² and in 90 m², with ten; 3,786 € in 100 m² and in 120 m², with thirteen. Ten more metres do not move a euro. One more bathroom does.
  • Electrics: counted by rooms. The 80 and 90 m² types have seven each and the item is the same, 1,561 € in functional.
  • Kitchen: our price table gives the same figure for a kitchen of 6, 9, 10 or 12 m², 5,518 € in functional and 7,650 € in mid-range. What changes with size is how many units and how much worktop fit, and that is decided by choosing quality, not by measuring.
  • Windows: paid per unit, 553 € in functional and 2,216 € in high-end. The 60 and 70 m² types have the same four windows, 2,212 € in functional, because the facade decides the openings, not the floor area.
  • Doors: 250 € each in functional, 575 € in mid-range and 780 € in high-end. They grow with the number of bedrooms, which does not always go with the metres.

On the technical visit we always start with the bathroom, kitchen and services: they are the items that look most alike from one flat to another. What really changes between two homes is in the other half of the table, in how many metres of floor and wall there are and how many doors and windows are kept.

And that has a confusing consequence: two flats of the same size can have very different fixed items if one has one bathroom and the other two; and two flats of different sizes can share exactly the same fixed items.

The floor of a full home renovation and where you can cut back

The floor of a full home renovation is its bathroom plus its kitchen: 15,773 € at functional quality (guide price, excluding VAT), 23,409 € in mid-range and 35,428 € in high-end, before laying a metre of flooring. With plumbing and electrics, in the 50 m² flat that floor rises to 19,083 € in functional.

Fixed itemFunctionalMid-rangeHigh-end
Full bathroom of ~4 m²10,255 €15,759 €20,467 €
Full kitchen5,518 €7,650 €14,961 €
Renovation floor15,773 €23,409 €35,428 €

Guide prices · VAT not included. Not a binding offer: the fixed quote by item comes after the free technical visit.

That floor explains why a small flat does not fall below a certain figure. The functional budget for 50 m² is 32,982 €, and more than half is committed before counting a single metre. If you receive a full renovation quote far below these figures, it is not a bargain: check what it says about services, waterproofing and who runs the works, because something is missing.

Where you can cut back without cheating yourself:

  1. What is paid per unit. Every window that insulates well and is kept is 553 € less in functional and 2,216 € in high-end. The same goes for doors that can be lacquered or an original floor that is sanded instead of lifted.
  2. Quality within the fixed item. The bathroom goes from 10,255 € to 15,759 € between functional and mid-range, and the kitchen from 5,518 € to 7,650 €. Going down a range in sanitaryware, taps or units shows in the total without putting the works at risk; what goes behind the tiling is not touched.
  3. Not moving the wet areas. Moving the kitchen to another wall adds 2,212 € in functional, 2,929 € in mid-range and 4,161 € in high-end, on top of the price of the kitchen itself. Leaving kitchen and bathroom where they are is the cleanest saving of the three.

What is never cut: bathroom waterproofing, new services with their certificate and site management. Redoing them once the work is finished means tearing up what is already done, and they are exactly the first things to disappear from a quote that comes out too low.

Frequently asked questions about fixed and variable renovation costs

Which renovation items do not depend on floor area?

Full bathroom, full kitchen, plumbing and electrics, plus licences and auxiliary equipment. In our standard quotes, the first four make up 58% of the functional total in a 50 m² flat and 46% in a 90 m² one. They grow with the number of bathrooms, rooms or water points, not with floor area.

What is the minimum cost of a full flat renovation?

Our smallest standard quote, for 50 m², comes to 32,982 € at functional quality, as a guide price excluding VAT. Of that, 19,083 € are fixed items, and the bathroom and kitchen alone add up to 15,773 €. A smaller flat does not fall in the same proportion: the fixed quote for yours comes after the free technical visit.

Why does a kitchen cost the same in a small flat as in a large one?

Because the full kitchen item includes the same in both: units, worktop, appliances and the work to fit them. Our price table gives the same figure for kitchens from 6 to 12 m², 5,518 € in functional and 7,650 € in mid-range. What moves the price of a kitchen is the quality chosen, not the metres.

Which items should you never cut in a renovation?

Bathroom waterproofing, new electrical and plumbing services with their certificate, and site management. They are the ones you do not see when the work is finished, the hardest to redo if they fail and the first to be missing from a quote that is too low. You can go down a range on finishes, not on what goes behind them.

If you are trying to understand why your quote does not fall below a certain figure, this is the logical reading order.