How much does it cost to renovate a 60 m² flat: the real budget, item by item

The short answer, calculated from our price table for a typical 60 m² flat with 2 bedrooms, one bathroom and a 7 m² kitchen: 36,208 € at a functional specification, 52,467 € at mid-range and 75,215 € for high specification, excluding VAT. The cards above show those same figures as an indicative range, following the logic of our calculator: the real condition of the flat and the finishes you choose move the result, and we prefer a range that holds to a round number that has to be corrected at the visit. Below is the full breakdown, and why at 60 m² the metre is still expensive: 603 €/m².

Painted corridor with white lacquered doors and new timber flooring — our 55 m² project in Les Corts, Barcelona

Functional

34,400 € – 43,500 €

Standard finishes, layout unchanged

Mid-range

49,900 € – 63,000 €

Selected materials, possible re-planning

High specification

71,500 € – 90,300 €

Premium materials and interior design

Indicative prices · VAT not included · not a binding offer. Your exact figure comes from the free site visit, fixed and itemised.

The starting point

What a 60 m² flat is (and why it shapes the budget)

The typical 60 m² flat in the metropolitan area has 2 bedrooms, a single bathroom of around 4 m², a 7 m² kitchen, a living-dining room and a short corridor: five rooms, five doors, four windows. It is the dominant format of the blocks of the sixties and seventies in Llefià, la Serraparera or Ca n’Anglada, and of much of Sants, Nou Barris and Santa Coloma.

That plan has a direct consequence for the budget: all the wet work in the flat sits in two rooms, the bathroom and the kitchen, and together they come to 15,773 € of the functional budget’s 36,208 €. The bathroom alone, 4 m² out of 60, takes 10,255 € — more than the demolition, building work, plasterboard and flooring of the whole home put together.

That is why at 60 m² layout decisions matter less than they seem, and decisions about the two wet rooms decide almost everything.

  • 2 bedrooms · 1 bathroom of ~4 m² · kitchen of ~7 m²
  • 5 rooms, 5 doors, 4 windows: the standard of the 60s–70s block
  • Swapping the bath for a shower and opening the kitchen: the two changes people ask for most
Forest mural beside the white bookcase in a 65 m² flat — our project in the Born, Barcelona
Typical price per m²603 – 1,254 €/m²
Forest mural beside the white bookcase in a 65 m² flat — our project in the Born, Barcelona
From our price table, not a template

Itemised example budget: 60 m², three specifications

Figures calculated item by item from our price table (54 items taken from real, signed quotes), for a 60 m² scope with 2 bedrooms, one full bathroom and a kitchen. Excluding VAT; not a binding offer. Your own quote is fixed and itemised after the free site visit.

ItemFunctionalMid-rangeHigh spec% of total
Demolition and rubble clearance · floor lifted + strip-out1,160 €1,550 €3,420 €3%
Building work and labouring2,048 €2,127 €2,465 €4%
Plasterboard and suspended ceilings (~24 m²)1,104 €1,296 €1,560 €2%
Plumbing (adaptation + 8 points) · bathroom and kitchen2,486 €3,440 €4,773 €7%
Electrics (5 rooms) · with certificate (CIE)1,115 €1,590 €2,745 €3%
Complete bathroom (~4 m²) · building work + tiling + sanitaryware10,255 €15,759 €20,467 €30%
Complete kitchen (~7 m²) · units, worktop and appliances5,518 €7,650 €14,961 €15%
Flooring throughout (AC5 timber laminate)2,220 €2,580 €2,880 €5%
Internal joinery (5 doors)1,250 €2,875 €3,900 €5%
Windows (4 units) · if you keep yours, subtract this line2,212 €4,600 €8,864 €9%
Skimming and full repaint · ~180 m² of wall and ceiling surface6,840 €9,000 €9,180 €17%
Total for the example budget36,208 €52,467 €75,215 €
Equivalent per m²603 €/m²874 €/m²1,254 €/m²
The arithmetic of the two-bedroom flat

Why at 60 m² the metre is still expensive

In this page’s functional budget, kitchen, bathroom, plumbing and electrics come to 19,374 €: 54% of the total. Those four items would be almost identical in a 90 m² flat, where they are spread over half as much floor again. That is why the metre falls from 603 € to 506 € without the work changing in nature.

What does grow with floor area is the cheap part: flooring, painting and plasterboard. At 60 m² those three items come to 10,164 € at the functional level — what you see, walk on and touch every day, for less than a single bathroom costs.

Compare items, not metres. If a 60 m² quote comes in well below these figures, the difference is almost never in the finishes: it is in what is done about the services, the waterproofing and who runs the site.

≈54%Almost fixed cost: kitchen, bathroom and services
≈46%The only part that scales with floor area
Wall chased back to the brick with the electrical chases marked in red — our project in the Eixample, Barcelona
Wall chased back to the brick with the electrical chases marked in red — our project in the Eixample, Barcelona
The format of Llefià, la Serraparera and Ca n’Anglada

A single bathroom: the risk and the opportunity of 60 m²

A 60 m² flat almost always has one bathroom, and that is that. It changes how the work is planned, not just what it costs. While that bathroom is out of action the home is not habitable, and that is 2 or 3 weeks in a row: there is no guest WC to fall back on as there is in an 80 or 90 m² flat. It is the number one reason we recommend doing everything at once at this size rather than in phases.

The upside is that the most expensive item in the budget is also the most controllable. The functional bathroom’s 10,255 € moves between 10,255 € and 20,467 € depending on quality — a difference of 10,212 €, 28% of the whole budget — and that decision is made in an afternoon, choosing the tray, the tiles and the vanity unit. No other item in the home concentrates so much room for manoeuvre in a single conversation.

The second front specific to this size is the bedroom that is too many or too few. In these blocks the second bedroom is usually 8 or 9 m² and will take a bed or a desk, not both. Deciding it before demolition costs nothing; deciding it after the electrics are in costs redoing chases, light points and plasterboard.

  • With one bathroom, doing the full renovation at once works out better than phasing
  • The bathroom is 28% of the budget and almost all of the room for decisions
  • Bedroom or study: decide before the electrician arrives
Your home is not the “example”

What pushes the price up or down in your case

What pushes it up

  • Moving the bathroomWith a single bathroom there is no plan B: if it changes wall, the waste has to be brought back to the existing stack, which involves the slab, the building work and the tiling all at once.
  • Lead or galvanised iron pipeworkIn blocks of this period it turns up more often than anyone would like. Replacing the risers for the whole flat, not just the visible runs, is a health decision, not a finish.
  • A fourth floor with no liftAll the material goes up on someone’s shoulders and the seven-plus cubic metres of rubble we estimate for this size come down the same way. You pay for it in labourer hours, and in a 60 m² flat those hours weigh proportionally more than in a large one.
  • Replacing all four windowsThis is the item that separates the two ends of this page’s range: 2,212 € at functional, 8,864 € at high specification.

What brings it down

  • Leaving the bathroom where it isWithout touching the stack or the supply points, the most expensive item in the budget (10,255 € at functional) becomes dry work: tiling, sanitaryware and a screen.
  • Keeping the windows if they insulate wellYou subtract the whole item: the functional example budget falls from 36,208 € to 33,996 €.
  • Lacquering the five doors instead of replacing themInternal joinery drops from 1,250 € to a fraction, and in a flat from the seventies the solid leaves are usually worth keeping.
  • Deciding finishes before you startChanges made on the go cost double: returned material plus a stopped site.
Timescales

How long a 60 m² flat renovation takes

Weeks 1–2Demolition and setting out

Floors and wall finishes come up, the bathroom and the non-structural partitions are removed, and the new layout is marked out.

Weeks 3–5Services and building work

Plumbing with its 8 points, electrics for the 5 rooms with a certificate, and the building work and plasterboard for the ~24 m² of suspended ceiling.

Weeks 6–8Bathroom, kitchen and flooring

Waterproofing and tiling the bathroom, fitting the 7 m² kitchen and laying the timber floor throughout the home.

Weeks 9–10Joinery, painting and handover

The five doors, the fittings, skimming and painting some 180 m² of walls and ceilings, the final clean and a handover walk-round with the site manager.

9–10 weeks (full renovation) · 3–5 weeks (refresh) — 9 to 10 weeks is our planning estimate for a complete 60 m² renovation — indicative, not a figure from our price table: 1–2 for demolition, 3 for services and building work, 3 for bathroom, kitchen and flooring, and 2 for joinery, painting and snagging. The timescales that are hard data are those of our own projects: the 55 m² flat in Les Corts, a refresh with no change to the layout, took 5 weeks, and the 65 m² interior renovation in the Born, 3. Your programme comes in writing with the quote, with start and handover dates.

Permits: what a 60 m² flat needs. For internal work that does not touch the structure, a prior notification of works to the council is enough (in Barcelona, depending on the case, an assabentat or a notification with reduced fees): you file it, pay the fee and start. At 60 m² the one scenario that tends to complicate it is opening the kitchen to the living room when the wall between them is load-bearing, which is common in blocks of the sixties: then a project, a calculated lintel and a major-works licence are needed. We deal with the paperwork, and its cost appears in the quote by name and figure from day one — never as a surprise halfway through.

A genuinely fixed quote

What the price includes (and what it does not)

Included

  • A dedicated site manager running the renovation
  • Labour for every trade under a single contract
  • Materials at the specification stated against each item
  • Waste management: skip and haulage to an authorised tip
  • Protection of communal areas and a final builders’ clean
  • Certificates for the new services (electrical CIE, plumbing)
  • Filing the prior notification of works

Not included

  • VAT: 10% reduced rate or 21% depending on your case — confirmed in writing in the quote
  • Council licence fees (passed on at cost, depending on the council)
  • Loose furniture and decoration
  • Extra scope decided during the works (priced separately, in writing, before it is carried out)
The advice we would give a friend

Where to save on 60 m² — and where never to

Not every cut has the same effect: these are the items where saving is sensible, and the ones where it ends up costing more.

Save here

  • Finishes: standard stoneware rather than large-format porcelain
  • Standard sanitaryware and taps (they work just as well and cost half as much)
  • Lacquering the existing doors rather than replacing them
  • Keeping the exterior joinery if it insulates well

Never save here

  • Waterproofing the only bathroom: if it fails, the whole room has to be redone
  • Water and electrical installations: they are what the next 20 years rest on
  • Skimming the walls: at 60 m² you see everything from everywhere
  • Site management: the “cheap” option without a site manager ends up dear
Comparison

What if the flat were 50 or 70 m²?

The three figures come from the same example budget recalculated item by item, not from multiplying metres by an average. Look at the per-metre column: it falls steadily while the total hardly moves, because the bathroom and kitchen are the same in all three cases.

Floor areaFunctionalMid-range
60 m² flat (2 bedrooms, 1 bathroom)36,208 € · 603 €/m²52,467 € · 874 €/m²
50 m² flat (1–2 bedrooms, 1 bathroom)32,982 € · 660 €/m²47,689 € · 954 €/m²
70 m² flat (3 bedrooms, 1 bathroom)38,803 € · 554 €/m²55,984 € · 800 €/m²

* Indicative prices, excluding VAT. They vary with the starting condition of the home, the municipality and the finishes chosen.

Common questions

Questions about the cost of renovating 60 m²

The ones we are asked most before a quote is signed.

How much does it cost to fully renovate a 60 m² flat?

The example budget on this page, calculated item by item from our price table, comes to 36,208 € at a functional specification, 52,467 € at mid-range and 75,215 € for high specification, always excluding VAT and for a scope of 2 bedrooms, one bathroom and a kitchen. If you keep the four windows, subtract that item and the functional figure falls to 33,996 €. Your exact figure is fixed and itemised after the free site visit.

What is the price per square metre of renovating 60 m²?

603 €/m² at functional, 874 €/m² at mid-range and 1,254 €/m² for high specification, according to this page’s example budget. That is lower than in a 50 m² flat (660 €/m²) and higher than in a 70 m² one (554 €/m²), because the bathroom and kitchen cost practically the same in all three and here they are spread over 60 metres.

Why does the bathroom take nearly a third of the budget?

Because in 4 m² you concentrate waterproofing, tiling, new plumbing, sanitaryware, taps, screen and vanity unit, and all of it is paid for by the unit, not by the area. In this page’s functional budget it is 10,255 € of 36,208 €, or 28%. It is also the item with the most room to move: at high specification it reaches 20,467 €, and the difference is yours to decide by choosing materials.

Can you live in the flat during a 60 m² renovation?

In a full renovation we do not recommend it: with a single bathroom there are 2–3 weeks without a WC or hot water, and there is no second WC to fall back on as in 80 or 90 m² flats. In a partial renovation room by room it is workable. We tell you plainly at the visit, depending on the scope you choose.

Is it worth replacing all four windows?

It depends what you have. The item is 2,212 € at functional and 8,864 € at high specification: it is the one that multiplies most between specifications in the whole table, four times over for the same four openings. If your current frames are aluminium with no thermal break and close badly, it pays back in comfort and in bills; if they are already PVC or thermally broken aluminium in good condition, the sensible thing is to keep them and put that money into the bathroom.

Do I need a licence to renovate a 60 m² flat?

For internal work that does not touch the structure, a prior notification to the council: quick and low-fee. If you open the kitchen to the living room and that wall turns out to be load-bearing — common in the blocks of the sixties — a project, a calculated lintel and a major-works licence are needed. We deal with the whole process and you will see it priced as one more item, with its amount, before you sign.

Do these prices include VAT?

No: all prices on this page exclude VAT, as in our quotes. The applicable rate (10% reduced or 21%) depends on your case — private use, age of the building and the weight of materials — and we confirm it in writing in the quote.

Who we are

Full renovations in Barcelona and across Catalonia. A fixed, itemised quote, a dedicated site manager who keeps you informed and a written warranty.

Related services

Guides and calculators

Want your exact figure, not a range?

A free site visit, a fixed itemised quote and a written programme. What we sign is what you pay.