Partial renovation of a flat in Les Corts, Barcelona
Carrer de Numància, Barcelona · 55 m² · 2026

Project details
- Floor area
- 55 m²
- Property type
- Flat
- Duration
- 5 weeks
- Year
- 2026
- Status
- Completed
- Budget
- 20,000–22,000 €
- What we did
- New kitchen · Microcement bathroom · Flooring throughout the flat · Painting · Lacquered doors
Indicative prices · VAT not included. Not a binding offer; every project is quoted after the site visit.
About this renovation
A complete update of a small flat: a white kitchen with a wooden worktop, a microcement bathroom, new flooring, paint and lacquered doors.
It was a small flat, very much out of date, and the brief was clear: leave it ready to move into without touching the layout. The kitchen was redone with white units up to the ceiling, a solid-wood worktop and new appliances, reusing the existing tiling where it was sound so as not to push up the item.
The bathroom went another way: microcement on the walls, new sanitaryware and accessories in black, which with a modest budget changes the feel of the room completely.
In the rest of the flat, continuous laminate flooring went in, everything was painted in a very light grey and the doors were replaced with white lacquered ones. It is the kind of renovation that does not make the magazines but multiplies the flat: same space, another decade.
If you are weighing up a flat renovation in Les Corts or elsewhere in Barcelona, to move in or to let, this job is a good example of what can be achieved without touching the layout.
The figures on this page (area, duration and budget) are guide estimates and the location is approximate: they are not the final data for this job.