The cost of renovating an 8 m² kitchen: the budget and the peninsula frontier

With figures from our price table: the project price of a complete 8 m² kitchen is 5,242 € at a functional specification, 7,278 € at mid-range and 14,451 € for high specification, excluding VAT, with units, worktop and appliances inside, and the cards open it with the 5% below to 20% above range our calculator uses. Compared with a 6 m² kitchen, that is 277 € more for 2 m² more and 0.6 more linear metres of run. And there is a question that only appears from these metres on, the one that comes up on every 8 m² visit: does a peninsula fit here?

Two-tone kitchen, finished: white base units, timber wall units, white metro-tile splashback, timber worktop and black sink — our project in Sant Andreu, Barcelona

Functional

5,000 € – 6,300 €

Standard finishes, layout unchanged

Mid-range

7,000 € – 8,800 €

Selected materials, possible re-planning

High specification

13,800 € – 17,400 €

Premium materials and interior design

Indicative prices · VAT not included · not a binding offer. Your exact figure comes from the free site visit, fixed and itemised.

The starting point

Eight square metres: the kitchen that now allows two runs

An 8 m² kitchen usually measures around 2.30 × 3.50 m and appears in three-bedroom flats of the metropolitan expansion and in houses between party walls. It is the first size at which the kitchen stops being a corridor with units.

What changes compared with 6 m² is not the 2 m² of floor: it is the 0.6 extra linear metres of run that fit — from 3.0 to 3.6 — and, above all, the width. With 2.30 m between walls the parallel layout finally appears, with two facing runs and 110 cm of walkway between them, which gives the most storage per square metre of the whole series.

And the peninsula question appears. The honest answer, which we develop below with measurements, is “it depends where the door is”: 8 m² allow a 1.20 m peninsula if the kitchen is square and the door falls in a corner, and allow nothing at all if the room is long and the door is in the middle of a long wall.

  • ~2.30 × 3.50 m: the first size that allows two facing runs
  • ~3.6 linear metres of run, 0.6 more than at 6 m²
  • A peninsula is possible, but the door decides it, not the floor area
Finished light-timber straight kitchen with a white worktop, a double sink under the window and a fridge tower — our project in Premià de Mar
Typical price per m²655 – 1,806 €/m²
Finished light-timber straight kitchen with a white worktop, a double sink under the window and a fridge tower — our project in Premià de Mar
The arithmetic of 8 m²

277 € separate an 8 m² kitchen from a 6 m² one

The functional project price goes from 4,965 € at 6 m² to 5,242 € at 8 m². That is 277 € for two more square metres and for half a long linear metre of extra run — less than any one of the four appliances in the kitchen costs.

The reason is that almost nothing that makes a kitchen dearer depends on the floor. The three water points, the sink, the hood with its extraction duct and the bulk of the electrical circuit with its certificate are the same in both. What grows is the run — half a linear metre more of units and worktop — and, behind it, a few more metres of tiling and flooring.

For anyone deciding between two flats, or whether to take a couple of metres from the gallery, the conclusion is the same as with bathrooms: the big kitchen is not the budget’s problem. What really moves the bill is the range of the units and whether or not there is partition work to open the kitchen to the living room — two decisions taken on the visit, not on the plan.

≈74%Units, worktop, sink, hood and services
≈26%Appliances, splashback tiling and flooring
Blue kitchen mid-fitting, with the fronts still under protective film and the dark metro tiles already laid — our project in Sant Andreu, Barcelona
Blue kitchen mid-fitting, with the fronts still under protective film and the dark metro tiles already laid — our project in Sant Andreu, Barcelona
What is particular to 8 m²

The peninsula frontier: the four measurements that decide it

Eight square metres is the size at which a peninsula stops being impossible and starts being debatable. It is not decided by floor area — that is the mistake — but by four measurements you can take with a tape in ten minutes. We put them here so that you can decide before we come.

The first is the clear walkway: 90 cm on each side of the projecting section. Not 80 or 85: at 85 cm, an open dishwasher blocks the kitchen and somebody has to wait. The second is the useful length of the peninsula, 120 cm at least; below that not even a stool with its knee space fits, and what is left is a unit that gets in the way.

The third is where the door is, and it overrides all the others. If the door falls in a corner, the peninsula can start from the opposite run and circulation enters and turns. If the door is in the middle of a long wall, any peninsula ends up right opposite and turns the kitchen into two halves cut off from each other. The fourth is the distance to the stack, which decides whether that peninsula can carry a sink or stays as a worksurface.

With those four measurements, the pattern is clear: a square 8 m² kitchen, about 2.80 × 2.80 m with the door in a corner, takes a peninsula comfortably. A long 8 m² kitchen, of 2.00 × 4.00 m, does not take one at all, and what it does take — and works just as well for social use — is a projecting bar resting on the base unit itself, with no water or power, which neither opens the floor nor touches the stack. These are figures from our own closed quotes; we work with them across the whole of Catalonia.

  • 90 cm of clear walkway on each side of the projecting section, measured unit to unit
  • 120 cm of useful length at least for the peninsula to be of any use
  • Door in a corner: a peninsula is possible. Door in the middle of the long wall: it is not
  • A peninsula with a sink only if the stack is close; otherwise a projecting bar with no services
Your home is not the “example”

What pushes the price up or down in your case

What pushes it up

  • Building a peninsula with a sink or hobTaking water, drain or power to a unit that touches no wall means opening the floor and working out the fall to the stack. It is the item most underestimated at 8 m².
  • Opening the kitchen to the living roomKnocking down the partition is not just demolition: the flooring junction has to be finished, a continuous suspended ceiling redone and the whole living room repainted.
  • Two-tone frontsBase units in one finish and wall units in another is the fashionable device at 8 m², and it means two series of units with their order minimums instead of one.
  • A decorative or ceiling-integrated hoodIt stops being an appliance hung on the wall and becomes an element that needs a plasterboard bulkhead, its duct and its access hatch.

What brings it down

  • Solving the kitchen as an L and leaving the fourth wall freeThe wall that carries no units is what lets you fit a table without strangling the walkway.
  • A projecting bar resting on the base unit itselfIt gives the social function of the peninsula without taking water or power to a freestanding unit.
  • Keeping the hood where it wasThe existing extraction duct is, almost always, the one point in the kitchen it is not worth moving.
  • The same front across the whole kitchenOne series of units, one order and one manufacturing lead time.
Timescales

How long an 8 m² kitchen renovation takes

Days 1–2Stripping out and demolition

The old kitchen is removed completely and the splashback and flooring chipped off. If there is to be a peninsula, now is when its position is marked on the floor in chalk.

Days 3–5Services, drains and extraction

Three water points, the electrical circuit with its power points and the smoke duct. If there is a peninsula, its drain is dealt with in this phase and not in another.

Days 6–8Tiling, flooring and suspended ceiling

Ten square metres of tiled splashback, flooring with skirting and, if the hood is built in, the plasterboard bulkhead with its access hatch.

Days 9–10Fitting and handover

Units of the 3.6 linear metres, worktop, sink, tap, hood and appliances. Each water point and each appliance is tested before the handover walk-round.

2 weeks of work · the units are ordered on signing, not on starting — Two weeks of work, like the 9 m² kitchen in Sant Cugat that we have published with its timescale confirmed on the project sheet. If a peninsula with a sink or hob is fitted, its drain is carried out within the services phase, not after: it does not lengthen the programme if it is decided from the start, and it lengthens it by a week if it is decided halfway through. The units’ lead time is separate and starts with the order, on the day of signing.

Permits: what renovating an 8 m² kitchen needs. Prior notification of works while the work is internal. The situation that does change things at 8 m² is the most requested one: opening the kitchen to the living room. If the partition is a dividing one, it is still minor work and it is enough to record it; if it is load-bearing — and in old Barcelona buildings it is more often than people think — a trial opening, a calculated lintel, a technical project and a major-works licence are needed. We check on the visit before quoting anything.

A genuinely fixed quote

What the price includes (and what it does not)

Included

  • A dedicated site manager and a single point of contact throughout the renovation
  • Demolition of the old kitchen, rubble removal and haulage to an authorised tip
  • Kitchen units of about 3.6 linear metres of run, worktop and fitting
  • Plumbing for 3 points with their drains, and electrics with a certificate (CIE)
  • Tiling of the splashback wall, porcelain flooring and skirting
  • Sink, tap, hood and the smoke extraction duct
  • Protection of the rest of the home and a final builders’ clean

Not included

  • VAT: 10% reduced rate or 21% depending on your case — confirmed in writing in the quote
  • Council fees for the prior notification of works (passed on at cost)
  • Knocking down the partition between kitchen and living room: that is another item and another procedure
  • Crockery, small appliances and decoration
The advice we would give a friend

Where to save on 8 m² — and where never to

Not every cut has the same effect: these are the items where saving is sensible, and the ones where it ends up costing more.

Save here

  • A projecting bar over the existing base unit instead of a peninsula with services
  • Handleless wall units with a routed finger-pull: the same effect, no ironmongery to pay for
  • Appliances of the same brand and range: a better price as a set and a single service contact
  • Tiling the 10 m² of the working wall and leaving the rest skimmed and painted

Never save here

  • The peninsula’s drain, if there is one: under the floor it is not repaired, it is reopened
  • The cross-section of the induction hob’s circuit, which is the highest load in the home
  • The extraction duct to a courtyard or façade, with its non-return valve
  • Finishing the flooring junction if the kitchen is opened to the living room
Common questions

Questions about the cost of renovating 8 m²

The ones we are asked most before a quote is signed.

How much does it cost to renovate an 8 m² kitchen?

The project price in our price table for a complete 8 m² kitchen is 5,242 € at a functional specification, 7,278 € at mid-range and 14,451 € for high specification, excluding VAT, with units, worktop and appliances included. Our published job closest in size, 9 m² in Sant Cugat, was signed between 16,000 and 18,000 €, with a splashback of hexagons laid piece by piece: the distance between one figure and the other is the finish.

Does a peninsula fit in an 8 m² kitchen?

It depends on the shape of the room and where the door is, not on the floor area. You need 90 cm of clear walkway on each side of the projecting section and around 120 cm of peninsula for it to be of any use: that works in a square kitchen of 2.80 × 2.80 m and does not work in a long one of 2.00 × 4.00 m, even though both are 8 m². We measure it on the visit with a tape, which is the only honest way to answer.

How much does it cost to open the kitchen to the living room?

It is not in this page’s budget and it is not a minor item. If the partition is a dividing one, we are talking about demolition, finishing the flooring junction, a continuous suspended ceiling and repainting the living room. If it is load-bearing, a trial opening, a calculated lintel, a project and a major-works licence appear, with technical supervision. The first thing we do on the visit is find out which of the two is yours.

Do you give me the price broken down by item?

Yes, in your quote, once the kitchen has been measured. What we do not publish on this page is a generic breakdown, and it is a deliberate decision: a kitchen is contracted closed, and a breakdown made on a kitchen we have not seen gives a false sense of precision about the only figure that matters to you, which is yours. What we do publish is the real project price and the signed jobs we test it against.

Is an L or a parallel kitchen better in 8 m²?

A parallel layout gives more storage per square metre, but it only works if at least 110 cm of walkway remain between the two runs, which asks for a room at least 2.30 m wide. An L loses some storage to the corner unit, but leaves a free wall for a table, which in an 8 m² kitchen is often what people end up appreciating most.

Do these prices include VAT?

No, they are excluding VAT. The rate that applies depends on your case — main residence, age of the building and weight of materials in the total — and in kitchens the weight of the units means that last criterion has to be looked at carefully. We confirm it in writing in the quote.

Who we are

Full renovations in Barcelona and across Catalonia. A fixed, itemised quote, a dedicated site manager who keeps you informed and a written warranty.

Related services

Guides and calculators

Want your exact figure, not a range?

A free site visit, a fixed itemised quote and a written programme. What we sign is what you pay.