Price guide · October 2026

How much does it cost to renovate an 80 m² flat in Barcelona: the budget, item by item

The short answer, using figures from our real quotes: a complete renovation of an 80 m² flat in Barcelona runs from 41,300 to 52,100 € at a functional specification, from 59,700 to 75,300 € at mid-range, and from 85,000 € for high specification. Always excluding VAT. The itemised example budget further down comes to 43,372 € at the functional level — and the point to take away is that at 80 m² the price per metre is no longer a small flat’s price: it falls to about 542 €/m², against 660 €/m² for a 50 m² flat.

Living room of an 85 m² flat with the original terrazzo floor polished and doors lacquered black — our project in Granollers

Functional

41,300 € – 52,100 €

Standard finishes, layout unchanged

Mid-range

59,700 € – 75,300 €

Selected materials, possible re-planning

High specification

85,000 € – 107,300 €

Premium materials and interior design

Indicative prices · VAT not included · not a binding offer. Your exact figure comes from the free site visit, fixed and itemised.

The starting point

What an 80 m² flat is (and why it changes the budget)

The typical 80 m² flat in the Barcelona area has 3 bedrooms, a full bathroom and, very often, a guest WC, an 8–10 m² kitchen, a living-dining room and a long corridor that eats up floor area. It is the standard home of the metropolitan expansion districts: Gràcia, Sants, the Eixample of the 60s and 70s, Esplugues, Cornellà.

Compared with a small flat, two things change in the budget. A second wet room appears — the WC — which is a new fixed cost; and the items that do scale grow: flooring, painting, plasterboard and doors. What barely changes is the kitchen or the main bathroom, which cost practically the same as in a 50 m² flat.

That is why at 80 m² the euro per metre falls: there is more cheap floor area (bedrooms, corridor) sharing the weight of the expensive items.

  • 3 bedrooms · bathroom + WC · 8–10 m² kitchen
  • A long corridor: metres you pay for and rarely enjoy
  • Opening the living room to the kitchen and adding a second WC: the two headline changes
Doorway into the kitchen between two pine-slat partitions — our project in an old building in Vic
Typical price per m²542 – 1,117 €/m²
Doorway into the kitchen between two pine-slat partitions — our project in an old building in Vic
From our price table, not a template

Itemised example budget: 80 m², three specifications

Figures calculated item by item from our price table (real, signed quotes), for an 80 m² scope with 3 bedrooms, a full bathroom, a WC and a kitchen. Excluding VAT; not a binding offer. Your own quote is fixed and itemised after the free site visit.

ItemFunctionalMid-rangeHigh spec% of total
Demolition and rubble clearance · floor lifted + strip-out1,504 €2,012 €4,392 €3%
Building work and labouring2,624 €2,703 €3,073 €4%
Plasterboard and suspended ceilings (~32 m²)1,472 €1,728 €2,080 €3%
Plumbing (adaptation + 10 points) · bathroom, WC and kitchen3,006 €4,168 €5,795 €7%
Electrics (7 rooms) · with certificate (CIE)1,561 €2,226 €3,843 €4%
Complete bathroom (~4 m²) · building work + tiling + sanitaryware10,255 €15,759 €20,467 €25%
Second WC (~2 m²) · toilet, basin and tiling837 €1,286 €2,161 €2%
Complete kitchen (~9 m²) · units, worktop and appliances5,518 €7,650 €14,961 €12%
Flooring throughout (AC5 timber laminate)2,960 €3,440 €3,840 €5%
Internal joinery (7 doors)1,750 €4,025 €5,460 €6%
Windows (5 units) · if you keep yours, subtract this line2,765 €5,750 €11,080 €9%
Skimming and full repaint · ~240 m² of wall and ceiling surface9,120 €12,000 €12,240 €19%
Total for the example budget43,372 €62,747 €89,392 €
Equivalent per m²542 €/m²784 €/m²1,117 €/m²
The arithmetic of 80 m²

What does not scale with floor area (and why 80 m² works out better)

In this page’s functional example budget, kitchen, bathroom, WC and services come to about 21,200 € — 49% of the total. In a 50 m² flat those same items take close to 60%. It is not that they are cheaper here: there is simply more bedroom and corridor floor area sharing the bill.

That is the whole explanation of why the €/m² falls from 660 to 542 when going from 50 to 80 m², and why comparing quotes by “price per metre” leads to wrong conclusions. Compare items, not metres. If an 80 m² quote comes in well below these figures, look first at what it says about services, waterproofing and who runs the site — which is precisely what does not show in the photo.

≈49%Almost fixed cost: kitchen, bathroom and services
≈51%The only part that scales with floor area
Room stripped back to the Catalan vault with the services exposed — our project in Gràcia, Barcelona
Room stripped back to the Catalan vault with the services exposed — our project in Gràcia, Barcelona
Your home is not the “example”

What pushes the price up or down in your case

What pushes it up

  • Opening the living room to the kitchenAt 80 m² this is the headline change, and it almost always involves a load-bearing wall: the trial opening, lintel, project and technical supervision add 1,500–3,000 €.
  • Adding a second WCAdding a WC where there was no waste stack is the most underestimated item: plumbing, building work and tiling run to roughly 850–2,200 € depending on the finish.
  • Original services (60s–70s buildings)Renewing everything with certificates can add 2,000–4,000 € compared with a home that has already been updated.
  • A building with no liftMaterial goes up and rubble comes down by hand: at 80 m² there is far more rubble than in a small flat, and it adds around 5–8% to the works.

What brings it down

  • Keeping the floor if it is soundAn original terrazzo floor in good condition can be polished for a fraction of the cost of lifting it and laying timber — our Granollers project was done this way.
  • Keeping the kitchen and bathroom where they areIf waste stacks and supply points stay put, plumbing and building costs fall noticeably.
  • Keeping the windowsAt 80 m² there are usually 5 openings: if they insulate well, you take 2,700–11,000 € off, depending on the range.
  • Renovating in phases while you live thereIt does not work out cheaper per metre, but it spreads the outlay and avoids renting somewhere else. That is how we did the Gràcia flat you can see below.
Timescales

How long an 80 m² flat renovation takes

Weeks 1–2Demolition and setting out

Floors and wall finishes come up, sanitaryware and non-structural partitions are removed, and the new layout is marked out. An 80 m² flat produces close to 10 m³ of rubble.

Weeks 3–6Services and building work

New plumbing, waste and electrics with their certificates, the lintel if the living room is opened up, and the building work and plasterboard for suspended ceilings.

Weeks 7–9Wall finishes, bathroom, WC and kitchen

Tiling and waterproofing, the complete bathroom, WC and kitchen are fitted, and the flooring is laid throughout the home.

Weeks 10–12Joinery, painting and handover

The 7 doors, the fittings, skimming and painting some 240 m² of walls and ceilings, the final clean and a handover walk-round with the site manager.

10–12 weeks (full renovation) · ~4 weeks (refresh) — A complete 80 m² renovation is 10 to 12 weeks of actual work: 1–2 for demolition, 3–4 for services and building work, 3 for finishes and the bathroom, WC and kitchen, and 2–3 for joinery, painting and snagging. Our Gràcia project, 80 m² done in phases with the family still living there, took 10 weeks; a refresh that left the layout and hidden services alone, like the 85 m² flat in Granollers, was done in 4. We give you a written programme with the quote.

Permits: what an 80 m² flat needs. For internal work that does not touch the structure, a prior notification of works to the council is enough (in Barcelona, depending on the case, an assabentat or a notification with reduced fees). The difference at 80 m² is that the most common change — opening the living room to the kitchen — usually does involve a load-bearing wall, and then a technical project, a calculated lintel and a major-works licence are needed. We handle it and it is detailed as an item in the quote — never as a surprise.

A genuinely fixed quote

What the price includes (and what it does not)

Included

  • A dedicated site manager running the renovation
  • Labour for every trade under a single contract
  • Materials at the specification stated against each item
  • Waste management: skip and haulage to an authorised tip
  • Protection of communal areas and a final builders’ clean
  • Certificates for the new services (electrical CIE, plumbing)
  • Filing the prior notification of works

Not included

  • VAT: 10% reduced rate or 21% depending on your case — confirmed in writing in the quote
  • Council licence fees (passed on at cost, depending on the council)
  • Loose furniture and decoration
  • Extra scope decided during the works (priced separately, in writing, before it is carried out)
The advice we would give a friend

Where to save on 80 m² — and where never to

Not every cut has the same effect: these are the items where saving is sensible, and the ones where it ends up costing more.

Save here

  • Finishes: standard stoneware rather than large-format porcelain
  • Standard sanitaryware and taps (they work just as well and cost half as much)
  • Polishing a good original floor instead of lifting it
  • Lacquering the existing doors instead of replacing all 7

Never save here

  • Waterproofing the bathroom and WC: redoing it costs three times as much
  • Water and electrical installations: they are what the next 20 years rest on
  • The lintel when you open a load-bearing wall: it is structure, not finish
  • Site management: at 80 m² there are more trades overlapping, not fewer
Comparison

What if the flat were 70 or 90 m²?

These figures do not come from multiplying metres by an average €/m²: they are the same example budget recalculated item by item with our price table. That is why the total rises a little and the €/m² falls: from 70 to 90 m² only flooring, painting and plasterboard really grow.

Floor areaFunctionalMid-range
70 m² flat (2–3 bedrooms, 1 bathroom)38,803 € · 554 €/m²55,984 € · 800 €/m²
80 m² flat (3 bedrooms, bathroom and WC)43,372 € · 542 €/m²62,747 € · 784 €/m²
90 m² flat (3–4 bedrooms, bathroom and WC)45,558 € · 506 €/m²65,453 € · 727 €/m²

* Indicative prices, excluding VAT. They vary with the starting condition of the home, the municipality and the finishes chosen.

Common questions

Questions about the cost of renovating 80 m²

The ones we are asked most before a quote is signed.

How much does it cost to renovate an 80 m² flat in Barcelona?

From our real quotes: 38,000 to 55,000 € at a functional specification, 55,000–75,000 € at mid-range and from 90,000 € for high specification, always excluding VAT. The itemised example budget on this page comes to 43,372 € at the functional level, for a scope of 3 bedrooms, a bathroom, a WC and a kitchen. The final price is fixed and itemised after the free site visit.

What is the price per square metre of renovating 80 m²?

About 542 €/m² at functional, 784 €/m² at mid-range and 1,117 €/m² for high specification, according to this page’s example budget. That is noticeably lower than in a 50 m² flat (660 €/m² at functional) because kitchen, bathroom and services cost almost the same and here they are spread over more metres.

Why do two flats of the same size cost so differently?

Because scope sets the price, not floor area. On this very page there are two of our projects with almost identical metres: 80 m² in Gràcia for 33,000–36,000 € (mostly finishes, done in phases) and 75 m² in Vic for 59,500–62,000 € (a full renovation with made-to-measure joinery and a new bathroom and kitchen). The same metres, double the bill.

How much does it cost to add a second WC?

In this page’s example budget the guest WC of about 2 m² comes to between 837 € at functional and 2,161 € at high specification, counting toilet, basin, taps, fitting and tiling. The figure rises considerably if there is no waste stack nearby, because the drain then has to be run to one: it is the factor that adds most to the job and the first thing we look at on the visit.

Can you live in the flat during the renovation?

In a full 80 m² renovation we do not recommend doing so all at once: there are 3–4 weeks without water or a kitchen. Phasing is workable, room by room, as we did in the Gràcia flat — it does not work out cheaper per metre, but it avoids renting somewhere else. We tell you plainly at the visit which phases are compatible with living there.

Do I need a licence to renovate an 80 m² flat?

For internal work that does not touch the structure, a prior notification to the council — quick and low-fee. But at 80 m² the change people ask for most is opening the living room to the kitchen, and that usually involves a load-bearing wall: then a project, a calculated lintel and a major-works licence are needed. We handle it and its cost appears as its own item in the quote.

Do these prices include VAT?

No: all prices on this page exclude VAT, as in our quotes. The applicable rate (10% reduced or 21%) depends on your case — private use, age of the building and the weight of materials — and we confirm it in writing in the quote.

Who we are

Full renovations in Barcelona and across Catalonia. A fixed, itemised quote, a dedicated site manager who keeps you informed and a written warranty.

Related services

Guides and calculators

Want your exact figure, not a range?

A free site visit, a fixed itemised quote and a written programme. What we sign is what you pay.