How long does a renovation take? Timescales by type and size

By the Tu Nuevo Piso teamPublished 18 July 202610 min read

Key points for the works schedule

  • Quick partial renovations: A standard bathroom needs 1 to 2 full weeks of continuous work, while a typical kitchen usually takes 3 to 4 weeks.
  • Medium flats of 80 m²: A realistic timescale for a full renovation is 3 to 4 months, depending on the structural changes.
  • Large homes over 120 m²: Plan for 4 to 6 months in total, not counting the preliminary phase of developing the technical project.
  • The real bottleneck is paperwork: Legal procedures and getting the necessary building licence in Barcelona can add 4 to 12 weeks to the overall schedule before the first wall comes down.

Starting a home renovation brings a mix of excitement and real anxiety about timescales. Stories range from projects finished ahead of time to jobs that dragged on for months past the date in the contract. In practice, timescales are rarely a matter of luck. They depend on careful planning, on coordinating the trades and on being realistic about logistics. In 2026, building methods and materials have improved a great deal, but the time mortar needs to dry, or services need to be installed properly, cannot be cut without weakening the structure.

What really decides how many months you will spend with the house upside down? This guide looks at realistic timescales for each type of work, from a single room to a full large-scale renovation. The aim is to show you the route ahead, so you can avoid the delays that spoil the process for most people.

Phase zero: the paperwork before the first wall comes down

Many people make the serious mistake of thinking the schedule starts on the day the workers arrive with the skip. It does not. Before the first tile comes off, there is a whole invisible stage: drawing up plans, writing the detailed specification of materials and finishes, choosing suppliers and dealing with the town hall. Managed well, this stage is the best protection against last-minute problems that could stop your renovation indefinitely.

Choosing the right team takes a fair amount of time, usually three to four weeks. Do not rush this key step. You need enough time to compare different technical offers and learn how to choose a renovation company in Barcelona that gives realistic timescales based on its own team's real capacity, rather than promises it cannot keep just to win the job.

Also, depending on the type of work, town hall procedures can slow the start down considerably. Do not expect to start straight away if you are changing the layout, altering the building's main drainage or knocking down walls that could affect the structure. The city council will ask for signed technical projects, fees to be paid and licences to be issued. This can take a long time, especially in historic buildings or protected areas. Not allowing for this administrative time means risking serious inspections and an immediate stop to the work.

Partial renovations: exact timescales for the kitchen and bathroom

If you only want to improve the wet rooms, the timescales are much shorter. But be careful: small spaces pack a lot of trades into very little floor area. Coordinating plumbers, electricians, bricklayers and fitters in a room where only two people can fit at once takes a precisely timed schedule.

A standard bathroom renovation in Barcelona usually needs between 7 and 12 working days of uninterrupted work. That covers removing the old sanitaryware, stripping the walls, levelling the floor, fully replacing the outdated plumbing, a safe electrical installation that meets the electrical regulations, tiling and, finally, fitting the shower screen and new taps.

A kitchen adds another layer of complexity, with cooking and storage to plan around. A typical kitchen renovation in Barcelona, including new storage units and high-durability worktops, usually runs for 3 to 4 full weeks. Here is why that timescale cannot be shortened by magic:

  • Days 1 to 3: Full demolition of partitions, removal of the old worktops and tiles, and quick disposal of the waste at an authorised recycling point.
  • Days 4 to 10: Cutting channels into the walls and installing the complete new water and gas pipes and safe electrical wiring.
  • Days 11 to 15: Rendering, plastering and waterproofing the walls, along with laying the new ceramic or porcelain stoneware floor.
  • Days 16 to 20: Careful assembly of the made-to-measure kitchen units, and precise measuring of the chosen worktop (Silestone, porcelain or similar). Cutting the worktop usually takes 5 to 10 days from the on-site measurement to the final fitting, and during that time the fitters sometimes have to pause part of the work.
  • Days 21 to 24: Fitting the finished worktop, connecting the sink, installing the appliances and setting up the lighting.

Full renovations: duration by floor area

When the home is stripped right back to the shell, with bare beams and exposed pillars, the usable floor area has a clear effect on the timescale. However, the estimated durations also depend on how complex the existing construction is and how old the building's structure is.

For small homes under 60 m², a full home renovation usually takes 2 to 2 and a half months. With less floor space, only a few workers can work at the same time without getting in each other's way, so the phases have to run almost one after another rather than in parallel.

For the typical size in Barcelona and other Catalan cities, flats of 80 to 100 m² with three bedrooms and two bathrooms, the agreed timescale is typically 3 to 4 months in total. That gives enough room to rearrange the layout substantially, for example opening the kitchen to the living room, and to fully renovate the two existing bathrooms.

Larger homes, such as old period flats, duplexes or detached houses over 120 or 150 m², typically take 5 to 7 months of continuous work. These projects often also include a full renovation of the central heating and air conditioning, a thorough replacement of complex large external walls, and the integration of advanced home automation, which needs many tests and commissioning steps.

The right order of work: why you cannot start by painting

One of the biggest sources of stress on a building site is not understanding the sequence behind the job. And yes, it is a strict sequence that cannot be skipped. Trying to speed up one phase before the previous one is properly finished usually leads to poor finishes and cracks or faults within a few months. It is key to understand the order in which a renovation is done, so you keep control of both the timescale and your nerves.

First, the flat is stripped back: unnecessary partitions, false ceilings and floors are removed, so the space is clear of anything left over. Next, the bricklayers build the new partitions in plasterboard or brick, while the hidden water, electrical and heating pipes and ducts are run at the same time. Once the services have been tested for watertightness and safety, the walls are closed up and the preparatory plastering for the tiles and floor finishes begins. Finally, once every coat has fully dried, the interior timber joinery, airtight aluminium windows, painting and the finishing electrical sockets and switches are installed.

What really delays the job: the saboteurs of the schedule

Even the most carefully planned schedule can be thrown off by several factors that often come up during a full renovation. Knowing these risks lets you protect yourself before it is too late:

  • Late or missing critical materials: Choosing a bespoke finish made to order in Italy with a minimum lead time of two months, when the tiler needs it in just three weeks, is a sure way to derail the whole project.
  • Unclear decisions at the start: Changing the position of the toilet or the shower tray, or the layout of the kitchen units, once work has begun means stopping, re-planning from scratch, undoing paid work and redoing critical services. That adds weeks to the schedule at a very high cost. This is why it is so important to avoid the most common renovation mistakes by settling the design on paper first.
  • Hidden problems behind old walls: When an old building's wall is opened, it is common to find pillars damaged by woodworm or serious structural damp caused by silent leaks from the building's shared pipes. These must be treated before work can safely continue.
  • Vague or open-ended quotes: A quote that is vague, not detailed and not fixed item by item opens the door to constant arguments with the workers about what is and is not included in the price. This leads to repeated disputes and work stoppages. To protect yourself, always ask for a clear fixed quote rather than an open one before signing any contract.

Comparison table of recommended timescales

Below is a summary table of the most typical ranges for standard renovations carried out by qualified professionals:

Type / size of renovationActual duration (estimate)Most critical phaseCommon setback
Standard bathroom renovation1 to 2 weeks (7–12 working days)Drainage and pipeworkPoor condition of shared drainage pipes
Standard kitchen renovation3 to 4 weeksServices and worktopLead time for the made-to-measure stone
Small flat (under 60 m²)2 to 2.5 monthsLayout and partitionsNot enough space for several trades at once
Medium flat (80–100 m²)3 to 4 monthsGeneral services and flooringDelays with the town hall licence
Large home (over 120 m²) or detached house5 to 7 monthsComplex climate control and joineryLate delivery of large windows

Can you live in the home during the renovation?

When planning a renovation, some people consider staying in the property to avoid the cost of temporary rent. But be fully honest with yourself: living through major works is an extreme test of anyone's wellbeing. It also slows the workers' real productivity considerably and increases the risk of everyday accidents on site.

If the work is partial (a second bathroom, painting, and so on), it is quite manageable with a bit of patience. But if you are replacing the floors and changing the whole electrical and water network, there is no reasonable case for staying, surrounded by cement dust and the noise of drilling all day. Before making a risky decision driven only by saving money, it is strongly advisable to think carefully about whether you can live at home during a renovation, so you know exactly what you are letting yourself in for day to day.

Frequently asked questions about renovation timescales

1. How does the type of contract affect the agreed timescales?

A well-drafted contract, with annexes setting out binding milestones and financial penalties for each unjustified working day of delay, is the best protection against endless timescales. To understand your rights if there are serious defects or construction delays, it is essential to find out correctly what guarantee a renovation has under the building laws currently in force in Spain.

2. When is it strictly compulsory to hire an architect or a technical architect?

Their involvement is crucial and legally required whenever you intend to alter load-bearing elements (walls, beams, pillars), substantially change the building's safety arrangements, or apply for certain major works licences from the local council. To work out which professional you need, and under what conditions, so you avoid unnecessary stoppages caused by poor paperwork, read a detailed post on when you need an architect or technical architect for a renovation in Barcelona.

3. Why does a turnkey approach shorten the overall timescale?

The turnkey model significantly shortens the work because all responsibility and technical contact sit with a single project manager. This avoids lost time between independent workers who pass responsibility between them and wait for each other to finish their part. For the full list of benefits of this unified approach, read an in-depth article on turnkey flat renovation and say goodbye to poor coordination between separate trades.

4. How does Catalonia's climate affect the work schedule?

Although it is not a direct obstacle, humid periods on the Catalan coast affect the time ordinary plaster needs to set properly and the time the final paint coats need to dry evenly. If these drying times are not fully respected, they can cause serious internal damp problems that lift the new paint within a short time and force walls to be redone.

Further reading to plan your renovation

The timescale is only one piece of the puzzle. Here are some other guides to help you avoid mistakes and get the most from your investment: