How to plan a full home renovation step by step: order of works and phases

By the Tu Nuevo Piso teamPublished 9 July 202610 min read

A full home renovation is one of the most intense financial and personal projects you will ever take on. It does not matter whether it is an old flat you inherited or your first purchase; the wish to make the space your own can cloud your judgement. Very often, the initial enthusiasm pushes people into the biggest mistake of all: knocking down walls before any technical planning has been done. Doing the work in the wrong order doubles labour costs, destroys expensive materials and stretches the timescale out indefinitely. In this detailed article for 2026, we look at each phase needed to complete a radical change to your home successfully, with a technical mindset but in plain language. The secret is not to spend more; it is knowing when to fit each brick, each cable and each coat of paint. This guide will help you understand the logical sequence, so you can talk on equal terms with the site manager at Tu Nuevo Piso or with whichever company you choose, and keep control of the timetable.

Key points for planning

  • Paperwork first, always: Spending a few weeks on the design avoids costly changes during the works.
  • Renew the services: Replace old pipes and cables before the tiles cover them.
  • Agree a fixed quote: Sign a contract that spells out the scope, so unexpected costs do not wreck your finances.
  • Waterproof before you tile: Do not overlook waterproofing in a bathroom renovation, which protects the structure from damp.
  • Follow the electrical safety rules: Respect the electrical protection zones in bathrooms to comply with Spanish technical safety legislation.

Phase 1: Concept design, plans and the budget question

Before the first hammer hits a wall, your renovation should exist on paper and in a digital, interactive format from start to finish. Skipping this step because you "already know what you want" is the quickest route to financial disaster. This is the pencil phase: dimensioned plans, studying how natural light moves through the home and making the key design decisions. You need to decide where each socket goes, what kind of doors you prefer, how the windows will open and which kitchen layout will make the best use of the space. At this stage, one of the most important decisions is the type of contract you will sign with the builder. Take the time to look at fixed versus open quotes in renovations, so you understand the risks and advantages of each. The recommendation for 2026, given how volatile the prices of raw materials have become, is a fixed quote broken down item by item, with no technical gaps that could lead to annoying variation orders later. Do not leave anything to the operative's improvisation.

Phase 2: Paperwork and permits

Once you have the final plans and a costed quote, you have to deal with your local town hall. No serious full renovation can start without the correct legal authorisation. Depending on the scale of the work, you will need either a responsible declaration or a minor or major works licence. For example, if you plan to change the layout by removing dividing walls or altering the building's original structure, you will need a registered architect to sign off the project. This step is also essential for keeping the peace with your neighbours. Inform the chair of the owners' community in writing and put a notice on the building entrance giving the start date of the works and the permitted noise hours. Sorting this out in advance will spare you unexpected visits from the local police and complaints that could halt the works at the first hurdle. In this phase you will also need to book space on the public road for the skip containers. The builder usually handles this directly, but you should check it carefully to avoid heavy administrative fines.

Phase 3: Demolition and clearing the debris (where everything turns grey)

This is where reality hits. Demolition is noisy, extremely messy and produces tonnes of dust that gets into every crack imaginable. This phase strips out everything old: cracked plaster false ceilings come down, old sanitaryware is pulled out, wall and kitchen tiles are lifted and the old wooden door frames are removed. If your plan involves knocking down partitions to join spaces together, this is the moment. The operatives should work from top to bottom to avoid dangerous collapses and to make sure the load-bearing areas are secured. It is essential that the contractor carries out selective waste removal, putting plastic, metal, wood and stone rubble into authorised skips for transport to a certified recycling plant. Do not underestimate the cost of this item: landfill charges in Spain have risen considerably to encourage a circular economy and more sustainable building materials.

Phase 4: New services and interior partitions

With the home cleared and free of dust, it is time to shape the new spaces and fit the flat with its basic supply systems. Start by building the new partitions, usually using plasterboard (drywall) on a galvanised steel frame or traditional ceramic brick, depending on the thermal and acoustic insulation you want from the interior design project. Next, the installers chase out channels for the electrical, telecoms, heating, ducted air conditioning and plumbing runs. I strongly recommend replacing all the old wiring and pipes if they are more than fifteen years old. This is the time to study carefully which services need renewing when you renovate a kitchen, planning separate power points for the oven, microwave, induction hob, extractor, washing machine, dryer and dishwasher to avoid overloading the circuits later. Likewise, check that the waste pipes keep the right fall to prevent recurring blockages, and use soundproofed pipes on the drains to noticeably improve the comfort of the neighbouring rooms and the main living room.

Phase 5: Wall and ceiling finishes, insulation and preparing surfaces

Once the services are fully connected and tested under pressure (especially the water pipes, to rule out any last-minute leaks), the ceilings and walls are closed up with the final plasterboard or a traditional plaster coat. This phase lays the foundations for the look of your home: it smooths the surfaces and corrects any existing walls that are out of plumb. In wet areas such as bathrooms, this stage needs extreme care and professional work. Make sure the right barriers are in place so that moisture does not seep through the plasterboard partitions and cause damp in the rooms behind. A specific water-repellent treatment must be applied with the correct fixing technique, following the advice on waterproofing in a bathroom renovation, to protect the shower and bath areas permanently against capillary leaks. After that comes the wall tiling and the preliminary levelling of the floors with special self-levelling compounds. This matters if you plan to fit large-format porcelain tiles or engineered wood, which need a perfectly flat base so they do not creak underfoot.

Phase 6: Floors, joinery and complex fittings

With the surfaces levelled and waterproofed, the flat finally starts to look like a proper home rather than a bare concrete shell. The floor coverings go down first (natural wood parquet, floating laminate or ceramic tiles). It is vital to protect these delicate materials straight away with thick corrugated card or bubble wrap, so they are not scratched or damaged by the later trades. Once the floors are protected, the wood and aluminium joiners can move in to fit the double or triple glazed windows with thermal-break frames, the hinged or sliding internal doors, built-in wardrobes made to measure and, of course, the long-awaited kitchen furniture. If you want to keep costs under control, it is worth reading the comparison of kitchen renovation materials. It will help you choose a hard-wearing porcelain or compact quartz worktop, fingerprint-resistant laminate doors and full-extension drawer runners with soft-close brakes, without breaking the family budget.

Phase 7: Painting, lighting and the final reveal

This is the final stretch of the renovation. Painting cleans up and finishes all the technical work that came before it. The cleanest result comes from applying the first coat of paint, over a high-adhesion primer, before the fine joinery and skirting boards go in. That way the skirting boards and frames sit neatly against the wall, with no unwanted marks or rough edges. After that first coat, the permanent electrical fittings go in (switches, sockets and data points), along with the recessed low-energy LED lights and the wall-hung sanitaryware with its single-lever taps. Once all this is fitted, the painter applies the final coat in a matt or satin finish to make good any scuffs picked up while the kitchen furniture or the toughened glass shower screens went in. To keep your project in Barcelona on budget and on time, you can read our specialist guide to bathroom renovation in Barcelona, which covers average rates and realistic labour timescales.

Budget control in the key areas

The kitchen and the bathroom account for close to sixty per cent of the total cost of any full renovation. They are complex rooms that combine careful demolition, water and gas supply installations subject to strict regulations, high-density wall coverings and made-to-measure furniture with variable prices. For this reason, if you do not plan with a calculator in hand, these two rooms will use up almost all of your monthly savings.

The sound way to stay within your limit is to break down each item of work in detail. It is worth reviewing a detailed kitchen renovation budget to prioritise spending on functional joinery and A+++ energy-efficient appliances, rather than on purely cosmetic items you can add gradually.

Likewise, if you are tackling the other big challenge in the home, go through a bathroom renovation budget in detail. It will show you how to choose durable ceramic-body taps and shower screens with factory anti-limescale treatment, without overspending on unnecessary luxury brands. In the end, the right balance is to put more of the budget into what is hidden behind the wall (copper and multilayer pipes, rock wool acoustic insulation, perimeter waterproofing) and to be more strategic about what you see in the room.

Professional site clean: the final polish

Do not underestimate this final phase. A professional builder's clean is demanding work that needs special equipment: industrial fine-dust vacuums, cement removers and cleaners made for limescale and silicone marks. Trying to do it with ordinary household products will only scratch the new glass or leave a white film on the design flooring. Once this deep clean is finished, the contractor carries out a technical check of the flat, writing a detailed list of small touch-ups to correct any imperfections in the joints or the paintwork.

Summary of the phase order and estimated costs

PhaseKey worksDuration (85 m2 flat)Share of the cost
Design and permitsPlans, choice of materials, municipal fees3 to 4 weeks5% of the total
DemolitionKnocking down partitions, selective removal to landfill1 to 2 weeks10% of the total
ServicesFull renewal of cables, copper pipes and drains3 to 4 weeks25% of the total
Plaster and floorsSmoothing, self-levelling screed and technical waterproofing2 to 3 weeks20% of the total
FinishesFitting kitchen furniture, skirting boards and smooth painting3 to 5 weeks40% of the total

Renovation timeline at a glance

The table below sets out the stages of the renovation, how long each one takes and the key points to watch:

Renovation phaseMain worksEstimated durationCritical point to watch
1. PlanningDesign and quotes4-8 weeksAvoid budget overruns
2. DemolitionRemoving partitions1-2 weeksProtect neighbouring areas
3. ServicesPlumbing and electrics2-3 weeksWatertightness tests
4. Building workPartitions and wet plaster2-3 weeksDrying times
5. FinishesJoinery and painting3-4 weeksAvoid accidental scratches

This timeline is a general guide for planning your full renovation in Barcelona.

Frequently asked questions about organising a renovation

What is the most common mistake when planning a full renovation?
The main error is getting the order of purchases wrong. Buying shower trays or recessed designer taps before the technical project and the plans are final holds up the operatives. If the measurements do not match the real flat, you will be forced to pay unplanned extra costs for urgent returns of goods, supplier delays and time lost while the bricklayers wait, all of which push the overall budget above the plan.

Do I have to apply for permits to change the internal layout?
Yes. You must always file a prior works notification or an urban planning licence with your local town hall. Even if you are not planning to touch pillars, main beams or load-bearing walls, any change to the bedroom partitions requires compliance with municipal rules and payment of the relevant fees.

What goes first, painting the rooms or fitting the wooden doors?
The sealing primer and the first coat of smooth paint must be applied before the fine wooden joinery, skirting boards or new laminate flooring go in, to avoid accidental paint splashes from the painters. Once the internal doors and the floating parquet are carefully in place, the operative applies the final matt coat to correct any scuffs left by the fitting work.

How long does a full renovation of a standard flat take?
For a standard flat of around eighty square metres, the realistic work period is three to five months of continuous work. This covers not only demolition and the renewal of services, but also the required curing times for plaster and wet mortars, as well as the workshop manufacture of the external windows, which takes time.