Price guide · October 2026

The cost of renovating a 5 m² bathroom: the example budget and the jump to a built-up shower tray

With figures from our price table: the example budget for a 5 m² bathroom comes to 10,255 € at a functional specification, 15,759 € at mid-range and 20,467 € for high specification, excluding VAT, and the cards open it with the same asymmetric range our calculator applies: 5% below and 20% above. That functional figure of 10,255 € is not an abstract calculation: it is exactly the project price of “complete bathroom renovation” in our price table, the one that also feeds the breakdown on the flat pages. And 5 m² is the floor area from which it stops making sense to argue about the shower tray: it is where a built-up tray with a linear drain becomes genuinely viable.

Bathroom with a walk-in shower, fixed glass screen, wall-hung toilet and timber vanity unit — our project in a ground-floor flat in La Sagrera, Barcelona

Functional

9,800 € – 12,400 €

Standard finishes, layout unchanged

Mid-range

15,000 € – 19,000 €

Selected materials, possible re-planning

High specification

19,500 € – 24,600 €

Premium materials and interior design

Indicative prices · VAT not included · not a binding offer. Your exact figure comes from the free site visit, fixed and itemised.

The starting point

What changes in a bathroom when it reaches 5 m²

5 m² bathrooms in the metropolitan area are usually long and narrow: around 1.60 × 3.10 m, with the door at one end and the window or courtyard at the other. They are the bathrooms of three-bedroom flats, and also the usual result of having joined a bathroom and an adjoining WC.

That shape is what allows the one real technical leap in the whole series: the shower stops being a piece you buy and becomes a piece you build. With 1.60 m of width there is room for a 160 × 80 built-up tray with a fall towards a linear drain against the wall, and for a fixed screen with no swing door intruding on the walkway.

There is also room for equipment that at 4 m² forces you to give something up: a 100–120 cm vanity unit, a tall cabinet, a washing machine in the space under the worktop. What does not appear is a jump in price: from the 4 m² bathroom to this one is 169 € at functional, and the built-up tray decision weighs far more than that metre.

  • ~1.60 × 3.10 m: the long bathroom of the three-bedroom flat
  • 160 × 80 built-up tray with a linear drain: now it fits
  • 100–120 cm vanity unit, tall cabinet or built-in washing machine
Walk-in shower with a linear drain, concealed taps and floor-to-ceiling marble-effect porcelain, beside the wall-hung toilet — our project in Castelldefels
Typical price per m²2,051 – 4,093 €/m²
Walk-in shower with a linear drain, concealed taps and floor-to-ceiling marble-effect porcelain, beside the wall-hung toilet — our project in Castelldefels
From our price table, not a template

Itemised example budget: 5 m² bathroom, three specifications

This is the reference table of the whole series: the 10,255 € of the functional column is the project price of “complete bathroom renovation” in our price table, as it stands, without recalculation. The 3, 4, 6 and 8 m² pages start from here and only move tiling, flooring and waterproofing. The last row collects what that price includes and is not itemised above. Excluding VAT; not a binding offer.

ItemFunctionalMid-rangeHigh spec% of total
Tiling (~21 m²)483 €630 €1,218 €4%
Porcelain flooring135 €200 €365 €1%
Waterproofing · wet area196 €602 €672 €4%
Shower tray and screen403 €509 €611 €3%
Toilet108 €215 €477 €1%
Vanity unit with basin211 €289 €458 €2%
Plumbing (5 points + drains)1,474 €1,994 €2,756 €13%
Electrics and ventilation · with certificate (CIE)396 €502 €765 €3%
Demolition, building work, fitting and labour · included in the real on-site price6,849 €10,818 €13,145 €69%
Total for the example budget10,255 €15,759 €20,467 €
Equivalent per m²2,051 €/m²3,152 €/m²4,093 €/m²
The arithmetic of 5 m²

Three of our bathrooms, of 4, 5 and 6 m², all start at the same 12,000 €

On this page there is no need to reason from a model, because we have three published bathrooms of 4, 5 and 6 m² and all three ranges start at 12,000 €. The Sants one (4 m²) reaches 13,000 €; the L’Hospitalet one (5 m², with a waterproofed built-up tray and large format), 13,500 €; the Sabadell one (6 m², with a corner bath and a double basin), 14,000 €. Two metres between the first and the last, and a thousand euros at the top.

Within the example budget, the items that do not move with the metres come to 9,637 € of the 10,255 € at functional: 94%. Tiling and flooring, the only things that grow with floor area, are 618 €. Between a 3 m² bathroom and this one there is 338 € — less than a top-range toilet costs.

That is why, when someone asks us over the phone for “the price per square metre of bathroom”, the honest answer is that the number exists but is no use: here it comes out at 2,051 €/m² and on the 3 m² page at 3,306 €/m². What decides your bill is the shower you choose, the tiling you choose and how many water points have to be redone — all three can be seen in a forty-minute visit.

≈94%Almost fixed cost: sanitaryware, plumbing and waterproofing
≈6%The only thing that scales with the metres
Base of the built-up shower tray waterproofed with the drain already sorted, before tiling — our bathroom job in L’Hospitalet de Llobregat
Base of the built-up shower tray waterproofed with the drain already sorted, before tiling — our bathroom job in L’Hospitalet de Llobregat
What is particular to 5 m²

The built-up tray: the first decision that really moves the budget

Up to 4 m², the shower is a piece you buy: a resin tray, extra-flat, resting on the slab. From 1.60 m of clear width — which is what a 5 m² bathroom brings — the real alternative appears: building it. And it is the only decision in this whole series of pages that changes the final figure more than the size of the bathroom.

A built-up tray is not “tiling the shower floor”. It means raising a base with a 1.5–2% fall towards the drain, waterproofing it in two layers that go up the wall by at least 20 cm, fitting the drain — point or linear against the wall — and lining it with cut pieces that follow that fall without breaking the joint. These are bricklayer-days that a resin tray does not consume.

In return you get two things you cannot buy: total continuity between the bathroom floor and the shower floor, with no step or profile, and an exact size for openings that do not exist in a catalogue. On our L’Hospitalet job, at 5 m², that is exactly what was done, and the waterproofing photo further up is from that job, with the drain already sorted and before anything was tiled.

The rule we give on the visit is simple: built-up tray if you want a continuous floor or the size does not exist; resin tray if timescale or budget rule. Both options last for decades if the waterproofing is well done — and that item is not negotiable in either. These are figures from our own closed quotes; we work with them across the whole of Catalonia.

  • 1.5–2% fall towards the drain, set out before waterproofing
  • Double waterproofing layer rising 20 cm up the walls
  • Linear drain against the wall: dearer than the siphon type, better tile layout
  • Made-to-measure resin: same function, goes in within hours, no fall work
Your home is not the “example”

What pushes the price up or down in your case

What pushes it up

  • A built-up tray with a linear drainForming the fall, double waterproofing layer, linear drain and mosaic or large-format tile cut to measure: it adds bricklayer days where a resin tray adds none.
  • Moving the door or making it open outwardsThe 5 m² usually come from a long, narrow bathroom. Gaining the door leaf means partition work, a new frame and painting touch-ups in the corridor.
  • A washing machine in the bathroomA water supply with its own valve, a drain with an anti-return trap and an electrical circuit able to take it: it is one water point and one power point more, not just a gap.
  • A built-in shower nicheIt is built, waterproofed and lined inside with cut pieces: a niche done properly is half a day of a skilled tradesman.

What brings it down

  • A made-to-measure extra-flat resin trayIt covers any awkward opening in a long bathroom without any fall work and goes in within hours.
  • Keeping the existing tiling on the dry wallIf it is sound and plumb, tiling over it or leaving it and painting the rest avoids chipping off a whole wall and its rubble.
  • A single basinIn 5 m² a double basin fits, but the second bowl doubles vanity unit and tap: 211 € more at functional that not everybody needs.
  • Deciding the tile layout with the tiler presentDeciding starting points and cuts before the first piece is stuck saves waste and corrections, and costs nothing.
Timescales

How long a 5 m² bathroom renovation takes

Days 1–2Demolition and trial opening

The bathroom is emptied and walls and floor chipped back. In 5 m² we take the chance to look at the slab under the old tray: it is where old leaks show up, and finding them now is cheap.

Days 3–5Services and forming the tray

Five water points, drains and the electrical line with its extractor. In parallel the built-up tray is raised with its fall towards the linear drain.

Days 6–8Waterproofing and finishes

Double layer on the wet area and over the tray, 21 m² of tiling and 5 m² of flooring. The grouting sets the pace, not the floor area.

Days 9–10Sanitaryware, screen and handover

Toilet, vanity unit with basin, concealed tap if there is one, screen, mirror and towel rail. Drain test with the shower running and a handover walk-round.

2 weeks of work · the timescale of our L’Hospitalet job — Our 5 m² bathroom in L’Hospitalet, with a built-up tray and large format, was handed over in 2 weeks, the same as the 4 and 6 m² ones on our project sheets. The built-up tray does not lengthen the programme if it is planned: it is formed during the services phase and cures while the vertical walls are tiled. What does lengthen it is choosing the finish late, because special tiling has a delivery time and the job stops waiting for it.

Permits: what renovating a 5 m² bathroom needs. Prior notification of works, as for any internal bathroom renovation that does not touch the structure or façade. There is a nuance specific to 5 m²: if these metres come from joining the bathroom to the adjoining WC by knocking down the partition that separated them, it is worth confirming first that the partition is not load-bearing — a half-hour trial opening settles it. If it were, the procedure changes and technical supervision comes in. We check it ourselves on the visit, before quoting.

A genuinely fixed quote

What the price includes (and what it does not)

Included

  • A dedicated site manager and a single point of contact throughout the renovation
  • Demolition of the whole bathroom, rubble removal and haulage to an authorised tip
  • New plumbing: 5 water points and the drains, with a watertightness test
  • New electrics for the room with a certificate (CIE) and forced ventilation
  • Waterproofing of the wet area, with extra reinforcement under the tray
  • Forming the built-up shower tray with its fall and drain, if chosen
  • Protection of the rest of the home and a final builders’ clean

Not included

  • VAT: 10% reduced rate or 21% depending on your case — confirmed in writing in the quote
  • Council fees for the prior notification of works (passed on at cost)
  • Structural reinforcement of the floor slab if the trial opening reveals earlier damage from leaks
  • Loose accessories, textiles and decoration
The advice we would give a friend

Where to save on 5 m² — and where never to

Not every cut has the same effect: these are the items where saving is sensible, and the ones where it ends up costing more.

Save here

  • A square siphon drain instead of an 80 cm linear channel: it complies just the same and costs quite a lot less
  • Small-format mosaic on the tray, which follows the fall without impossible cuts
  • Quality exposed taps rather than concealed ones: they can be repaired without opening the wall
  • Washable emulsion on the dry wall instead of tiling the full 21 m²

Never save here

  • The second waterproofing layer under the built-up tray: it is what separates you from the neighbour below
  • The fall of the tray: if wrong, water stays and the mosaic stains for ever
  • Access to concealed taps: without it, a future repair chips out the new tiling
  • The watertightness test before tiling: it costs an afternoon and saves a whole job
Comparison

From 4 to 6 m²: 338 € separate the three most common formats

The three sizes you most often find, calculated with the same price table and the same scope. The 6 m² one also includes a bidet and double basin, and even so the difference from the 4 m² one stays at 3.4%. The €/m², meanwhile, falls 31% — which is why we never use it to compare bathrooms.

Floor areaFunctionalMid-range
5 m² bathroom (built-up tray viable)10,255 € · 2,051 €/m²15,759 € · 3,152 €/m²
4 m² bathroom (120 shower and 80 vanity unit)10,086 € · 2,522 €/m²15,533 € · 3,883 €/m²
6 m² bathroom (bidet and double basin)10,424 € · 1,737 €/m²15,985 € · 2,664 €/m²

* Indicative prices, excluding VAT. They vary with the starting condition of the home, the municipality and the finishes chosen.

Common questions

Questions about the cost of renovating 5 m²

The ones we are asked most before a quote is signed.

How much does it cost to renovate a 5 m² bathroom?

This page’s example budget comes to 10,255 € at a functional specification, 15,759 € at mid-range and 20,467 € for high specification, excluding VAT. Our published 5 m² job, in L’Hospitalet, with a built-up tray and large format, was signed between 12,000 and 13,500 €. The exact price comes out fixed item by item after the free technical visit.

Is a built-up shower tray worth it compared with a resin one?

It is, if you want total continuity with the flooring, a linear drain against the wall or a size that does not exist in a catalogue. In return it needs forming with a fall, double waterproofing and the laying of cut pieces, which are skilled-tradesman days. If your priority is timescale or a tight budget, a made-to-measure extra-flat resin tray does the same job functionally and goes in within hours.

Does a double basin fit in 5 m²?

It does, with a 120 cm vanity unit, but it is worth thinking twice: the second bowl eats the worktop space where everything gets left, and adds vanity unit and tap. In our price table the double-basin vanity unit costs 422 € against 211 € for the single at functional. From 6 m² we treat it as standard; at 5 m² it is a decision, not a given.

What happens if damp turns up in the slab when it is chipped back?

We stop, document it with photographs and call you before going on. An old leak under the old tray may have damaged the slab, and repairing it is a new item that was not in the quote because it was not visible. We never cover it up or carry it out without your written approval: it is exactly the kind of surprise that a quote itemised and fixed by item exists to avoid.

Can I stay at home during the works?

Yes, unless it is the only bathroom. It is ten working days with a single general water shut-off, and the rest of the home is protected with sheeting and tape. In flats with a second WC the job is done without leaving home; if there is only one bathroom, we talk it over on the visit and adjust the programme.

Do these prices include VAT?

No: they are excluding VAT, like our quotes. The applicable rate depends on your specific situation — main residence, age of the building, weight of the materials in the total — and we leave it confirmed in writing before you sign.

Who we are

Full renovations in Barcelona and across Catalonia. A fixed, itemised quote, a dedicated site manager who keeps you informed and a written warranty.