With figures from our price table: the example budget for a 4 m² bathroom comes to 10,086 € at a functional specification, 15,533 € at mid-range and 20,089 € for high specification, excluding VAT. The cards above open that figure into the range our budget calculator uses — 5% below, 20% above — which is all the honest precision that can be given before seeing your bathroom. And there is an even more useful fact: the five bathrooms of ours published with confirmed floor areas were signed between 11,000 and 17,000 €, and the order of that list looks nothing like the order of their floor areas.

Standard finishes, layout unchanged
Selected materials, possible re-planning
Premium materials and interior design
Indicative prices · VAT not included · not a binding offer. Your exact figure comes from the free site visit, fixed and itemised.
If there is a typical bathroom in the metropolitan expansion of Barcelona, this is it: about 4 m², around 1.70 × 2.30 m, in sixties and seventies flats in Sants, Gràcia, Cornellà, Esplugues or Badalona. For forty years it had a 150 bath, a pedestal basin and a mirror cabinet.
The renovation most often asked for today is the same one, and it is the one priced above: a 120 cm shower where the bath was, an 80 wall-hung vanity unit with integrated basin, a new toilet and full tiling. It is 4 m² that allow a generous shower without sacrificing the walkway, and that balance is exactly what makes it the commonest format.
What almost nobody takes into account: going from 3 to 4 m² costs 169 € at functional. An extra square metre of bathroom is worth, in our own price table, less than the tap. Everything else — plumbing, waterproofing, certificate, sanitaryware, trades — was already paid for.

Table anchored on the real project price of “complete bathroom renovation” in our price table (signed quotes), with tiling, flooring and waterproofing recalculated for 4 m². The last row collects what the on-site price includes that is not itemised above: demolition, building work, fitting and labour. Excluding VAT; not a binding offer.
| Item | Functional | Mid-range | High spec | % of total |
|---|---|---|---|---|
| Tiling (~17 m²) | 391 € | 510 € | 986 € | 3% |
| Porcelain flooring | 108 € | 160 € | 292 € | 1% |
| Waterproofing · wet area | 168 € | 516 € | 576 € | 3% |
| Shower tray and screen | 403 € | 509 € | 611 € | 3% |
| Toilet | 108 € | 215 € | 477 € | 1% |
| Vanity unit with basin | 211 € | 289 € | 458 € | 2% |
| Plumbing (5 points + drains) | 1,474 € | 1,994 € | 2,756 € | 13% |
| Electrics and ventilation · with certificate (CIE) | 396 € | 502 € | 765 € | 3% |
| Demolition, building work, fitting and labour · included in the real on-site price | 6,827 € | 10,838 € | 13,168 € | 70% |
| Total for the example budget | 10,086 € | 15,533 € | 20,089 € | |
| Equivalent per m² | 2,522 €/m² | 3,883 €/m² | 5,022 €/m² |
Of the 10,086 € of the functional budget, 9,587 € are items that do not move with floor area: the five plumbing points, the waterproofing, the electrics with their certificate, the four pieces of equipment and the trades’ labour. The remaining 499 € is tiling and flooring — the only things that grow when the bathroom grows.
That is the picture that explains why, on a project sheet, two bathrooms of very different sizes end up on the same line of the budget. And why a suspiciously cheap bathroom quote is almost never cheap because of the metres: it is because it has cut what you cannot see — the waterproofing, the number of water points, the electrical certificate — and that only shows up two years later.
When you compare, ask them to separate these four things: how many plumbing points are redone, what it is waterproofed with, whether the electrical installation is delivered with a CIE and who runs the job. If two quotes match there, then yes, compare the finish.

The itemised table above is a model. This is not: it is the four bathrooms we have published with confirmed floor areas on their project sheet, with the range that was signed on each. We have ordered them by floor area on purpose, because the order is no use at all.
Look at the extremes. The smallest bathroom, 4 m², was signed between 12,000 and 13,000 €. The biggest, a 7 m² WC, between 11,000 and 13,000 €, and it was the fastest: a single week of work. The 6 m² one, with a corner bath and a double basin, is the one that goes highest. If floor area ruled, the list would climb from top to bottom, and it does not.
What separates one range from another is always the same: how much special tiling there is, whether the tray is built-up or resin, how many pieces of sanitaryware are fitted and how much bathroom joinery goes in. They are your decisions on the technical visit, not the square metre’s.
Out go the bath or tray, sanitaryware, vanity unit and screen; the tiling is chipped off and the floor lifted until the brick is exposed, so the set-out is done on what is really there.
Five new water points, drains with their fall, the room’s electrical line and the extractor. They are tested under load before anything is covered: it is the only cheap moment to find a leak.
Wet area waterproofed, 17 m² of tiling and 4 m² of porcelain flooring, with their curing and grouting.
80 vanity unit with basin, toilet, screen, taps, mirror and towel rail; sealing, cleaning and a handover walk-round.
2 weeks of work · confirmed on our Sants job — Two weeks, and we say it with a job in front of us: the 4 m² bathroom in Carrer de Sants you will see below was handed over in 2 weeks, going from a bath with glass blocks to a built-up shower with a screen. The programme is set by curing — waterproofing mortar, forming the tray, grouting — and does not change for a metre more or less. If the bathroom is the only one in the home, we chain services and tiling to leave a single day of water shut-off.
Permits: what renovating a 4 m² bathroom needs. Prior notification of works to the council — in Barcelona, the assabentat or the reduced-fee notification, depending on the case — as long as the structure is not touched, no new openings are made and the façade is not changed. Swapping a bath for a shower, redoing the services and tiling again falls squarely within that. If the building has community rules on working hours and use of the goods lift, we deal with them through the administrator before starting. The fee appears as its own line in the quote.
Not every cut has the same effect: these are the items where saving is sensible, and the ones where it ends up costing more.
Carrer de Sants, Barcelona4 m²2 weeksReal projectA 4 m² bathroom in Sants: the same size as this pageExactly 4 m²: this page’s reference jobBath and glass blocks out, built-up shower inGrey relief tile and a glass screenSigned above the functional example budgetIndicative costindicative · excluding VAT12,000–13,000 €
Terrassa7 m²one weekReal projectTerrassa, a 7 m² WC: three metres more and a single weekThree metres more and the lowest starting price of the four jobsGlossy black tile and a decorative mosaicPorcelain basin on a timber boardBacklit mirror: the finish rules, not the floor areaIndicative costindicative range · excluding VAT11,000–13,000 €The ones we are asked most before a quote is signed.
This page’s example budget comes to 10,086 € at a functional specification, 15,533 € at mid-range and 20,089 € for high specification, excluding VAT. Our real 4 m² job in Sants, swapping a bath for a built-up shower, was signed between 12,000 and 13,000 €. The difference between one figure and the other is the specific scope, which is settled on the free technical visit.
It is not a stand-alone item that can be priced honestly over the phone: it drags in the drain, the waterproofing of the new plane, the tiling of the space the bath leaves and the junction with the flooring. In practice it is solved within a complete renovation like the one on this page. What we can tell you is that the tray and screen, as supply, run from 403 to 611 € depending on range in our price table.
Because the metre is not what pays. On our project sheets, the Sants bathroom (4 m²) was signed between 12,000 and 13,000 € and the Sabadell one (6 m², with a corner bath and a double basin) between 12,000 and 14,000 €: the gap lies in the equipment and the finish, not in the two extra metres, which in our price table are worth 338 € at functional.
That an authorised installer issues the Electrical Installation Certificate (CIE) for what they have carried out. In a bathroom it matters especially because ITC-BT-27 defines volumes around the shower and basin where only certain degrees of protection and certain fittings are allowed. A quote that does not mention the certificate is saving precisely that.
Yes, and it is the most usual case in flats with a 4 m² bathroom. It is about ten working days; the main water is shut off for only one day and the rest of the home stays in use with protection in place. What you will not have during the works is a shower, so it is worth organising beforehand: we give you the programme in writing with the quote so that you can.
No, they are excluding VAT. The rate that ends up applying — 10% reduced or 21% — depends on it being for your private use, the age of the building and the materials not exceeding 40% of the total. We confirm it in writing in the quote, before you sign anything.