Restoring old houses in Granollers: why the price per m² misleads, what really drives the cost and how a quote is fixed item by item after the trial holes.
If you have searched for the price per m² of a full renovation of an old house, you will have seen that every website says something different. That is no coincidence. In a block flat almost everything is in view and repeatable; in an old house what is expensive is inside the walls, under the floor and above the ceiling. That is why we do not give you a figure per metre without having seen the house: it would be invented, and you would be deciding on it.
The first thing that distorts the €/m² is which metre you count. The built area includes thick walls, covered yard, staircase and storerooms; the usable area is what is really renovated. In party-wall houses in the old town, with wide load-bearing walls, the difference is large. And not every metre costs the same: a bathroom or a kitchen weighs far more than a bedroom with sound walls.
Then comes what is only seen by opening up. The state of the floor and its joists, whether the roof holds or has to be rebuilt, and the buried drainage, which in an old house may be fibre cement or broken under the slab. On top of that comes whether the house has to be stripped back to the structure or partitions and ceilings are kept, and how you get to it: access, scaffolding and rubble change the item more than you would imagine.
So here is how we do it: a technical visit, trial holes in the floor, roof and walls with damp, and only then a quote fixed item by item. Each item with its scope in writing, what is in and what is not. That number is reliable, and your house’s real €/m² comes out of it. Before the trial holes, any figure per metre is a guess with decimals. And if the home turns out to be a flat rather than a house, what we do in the city is covered in renovations in Granollers.

Indicative market ranges per square metre of floor area, VAT excluded. The final price is a fixed quote after the survey.
| Specification | What it covers | Per m² (excl. VAT) | |
|---|---|---|---|
| Functional | Standard finishes, practical solution | 520 – 650 €/m² | |
| Mid-range | Selected materials, best balance | 750 – 940 €/m² | |
| High specification / luxury | Premium materials and high-end interior design | 1,060 – 1,340 €/m² |
Indicative only. VAT excluded. The final figure is a fixed written quote after the free survey.
Full renovation of the whole property, from functional to mid-range specification, VAT excluded.
One bathroom, one kitchen. The price per square metre is higher in a small home, because the kitchen and bathroom cost almost the same whether the flat is 45 or 90 m².
The most usual size, with a kitchen, one or two bathrooms and a new layout. This is the size where opening the kitchen into the living room pays off most.
More floor and wall surface to finish and, often, two full bathrooms. Worth checking the riser capacity before planning a second wet room away from the first.
Large flats and houses. The budget depends heavily on specification and layout, and heating and cooling become a real design decision.
These figures assume the structure is sound. If the survey finds damp, aluminosis-affected concrete or a roof at the end of its life, that is a separate priced item and we will tell you before you commit, not halfway through. Damp treatment and façade work are quoted on their own.
The scope of a turnkey full renovation, and the things that genuinely sit outside it.
VAT is shown as its own line: 10% where the property is a home at least two years old, 21% where it is not, or on work billed to a company. If you are buying the flat and renovating it before you move in, the dates matter — tell us the completion date and we will tell you which rate applies.
What you find inside an old house changes with the area and with the period it was built.
One team for the whole job, in Barcelona and across Catalonia.
Price and scope of restoring an old house in Granollers, without brochure figures.
We do not give a price per m² without seeing the house, and be wary of anyone who does. In an old house the cost is set by the state of the floor and the roof, the buried drainage, how much has to be stripped out and the access to the site, and none of that can be seen from the street. After the visit and the trial holes we give you a quote fixed item by item; divided by your usable metres, that is your real €/m².
It depends on what we find, but the usual is to check structure and roof, treat damp, renew drainage, electrics with their certificate and plumbing, and then insulation, partitions, floors, kitchen and bathrooms. A restoration is not a finishes renovation: first you fix what holds the house up and what cannot be seen, and then what can. Each block goes in as its own item, with its scope in writing.
Because in an old house the walls are thick and there are yards, staircases and areas that are not renovated. If you are quoted on built metres, the €/m² looks low but you are paying for metres that are not touched, or the other way round. We measure the usable area actually worked on and break it down item by item, so you can compare quotes on the same basis and not just the final figure.
They are small, controlled openings in floor, roof, damp walls and ground to see what condition the unseen parts are in: joists, timber beams, damp, pipework. They are done with the house still standing, and they avoid the worst thing that can happen to a quote: that it falls apart halfway through the job on discovering something. With the trial holes done, the quote can really be fixed.
A lot can be kept, but it has to be decided with judgement. In buildings in the centre with mouldings, high ceilings or features of value, it makes sense to keep and renew inside. If the floor or the services are in bad shape, stripping back to the structure is cheaper and cleaner than patching. We assess it after the trial holes and put it in the quote as alternatives, with what each costs.
Yes. We work on buildings in the centre with the care they need, with old structure, mouldings and damp, and with attention to heritage around the Porxada. Site access is planned from the quote, because on a narrow street carrying material up and rubble down is part of the work too. If structure, façade or roof have to be touched, we take care of the technical project and the licence.
Because it lets you see what you are paying for and compare. Each item has a scope, materials and a price, and if something changes you know exactly what and how much. A lump sum with no breakdown hides what is left out. If something turns up after opening that the trial holes did not foresee, you are told before it is carried out, and in writing, not with the final invoice.
First comes the technical visit, then the trial holes, which are what most condition the timescale. With the results closed, the quote item by item is a matter of days. There is no point rushing it: a quick quote on an old house is almost always one that will be reopened on site. We tell you from the visit what is still to be seen and how long we need.
Practical guides to prices, materials, permits and the decisions that come up on site — so you can plan your flat refurbishment with your eyes open.
10,000 € buys a bathroom or a kitchen; a 60 m² flat starts at 34,400 € at functional level. What each budget covers up to 150,000 €, before VAT.
Read the article →Guides and adviceWhat a technical architect (aparejador) charges in Spain in 2026: fee percentages, fixed prices, what drives the cost and when hiring one is compulsory.
Read the article →Full renovationsWhat an architect charges for a renovation in 2026: typical rates, fees as a share of the PEM budget and how to keep the total under control.
Read the article →Free survey anywhere in Catalonia, in English, and a fixed written quote. We reply within 24 hours.