With our price table and a 100 m² scope with 4 bedrooms, two full bathrooms and a 10 m² kitchen, the example budget comes to 58,968 € at a functional specification, 85,767 € at mid-range and 119,148 € for high specification, excluding VAT, with the indicative range on the cards calculated from those three totals. This page has a quirk you will not find on the others: at 100 m² the price per metre goes up, from 506 to 590 €/m². It is not a calculation error or a surcharge: it is the second full bathroom, and the whole sum is below.

Standard finishes, layout unchanged
Selected materials, possible re-planning
Premium materials and interior design
Indicative prices · VAT not included · not a binding offer. Your exact figure comes from the free site visit, fixed and itemised.
The 100 m² flat in the Barcelona area is the first one planned from the start with two full bathrooms instead of a bathroom and a guest WC: four bedrooms, eight rooms, eight doors, six windows and a 10 m² kitchen that has room for a peninsula. It is the format of the seventies blocks in Les Corts, Sant Gervasi or Sant Cugat, and of the principal floors recovered in Ciutat Vella and Gràcia.
That brief is a decision, not a fact about floor area, and it is the reason this page exists. We could have priced the 100 m² with a bathroom and a WC — as we do on the 90 m² page — and the €/m² would have gone on falling quite happily. But that would be misleading you: when someone renovates 100 m² in Barcelona, what they ask for is that the second wet room has a proper shower.
The other change specific to this size is that air conditioning stops being solved room by room. With 100 m² and 40 m² of suspended ceiling it already makes sense to consider ducts — and that is decided in week 3, not in week 11.

Figures calculated item by item from our price table (real, signed quotes), for a 100 m² scope with 4 bedrooms, TWO full bathrooms and a kitchen. The bathrooms row is double, hence its weight: it is the key to this whole page. Excluding VAT; not a binding offer.
| Item | Functional | Mid-range | High spec | % of total |
|---|---|---|---|---|
| Demolition and rubble clearance · floor lifted + strip-out | 1,912 € | 2,556 € | 5,616 € | 3% |
| Building work and labouring | 3,200 € | 3,279 € | 3,681 € | 4% |
| Plasterboard and suspended ceilings (~40 m²) | 1,840 € | 2,160 € | 2,600 € | 3% |
| Plumbing (adaptation + 13 points) · bathrooms and kitchen | 3,786 € | 5,260 € | 7,328 € | 6% |
| Electrics (8 rooms) · with certificate (CIE) | 1,784 € | 2,544 € | 4,392 € | 3% |
| Complete bathrooms (~4 m² each) · building work + tiling + sanitaryware | 20,510 € | 31,518 € | 40,934 € | 37% |
| Complete kitchen (~10 m²) · units, worktop and appliances | 5,518 € | 7,650 € | 14,961 € | 9% |
| Flooring throughout (AC5 timber laminate) | 3,700 € | 4,300 € | 4,800 € | 5% |
| Internal joinery (8 doors) | 2,000 € | 4,600 € | 6,240 € | 5% |
| Windows (6 units) · if you keep yours, subtract this line | 3,318 € | 6,900 € | 13,296 € | 8% |
| Skimming and full repaint · ~300 m² of wall and ceiling surface | 11,400 € | 15,000 € | 15,300 € | 17% |
| Total for the example budget | 58,968 € | 85,767 € | 119,148 € | |
| Equivalent per m² | 590 €/m² | 858 €/m² | 1,191 €/m² |
Every page in this series repeats the same idea: the more metres, the cheaper the metre, because kitchen, bathroom and services cost almost the same and are spread over more floor area. At 100 m² that idea stops being true, and it is better to say so out loud than to hide it behind an average.
The sum is this. In the 90 m² budget, the two wet rooms are one full bathroom (10,255 €) and a guest WC (837 €): 11,092 € at functional. In the 100 m² budget they are two full bathrooms: 20,510 €. The difference, 9,418 €, accounts for 70% of everything the budget rises by in going from 90 to 100 m² — 13,410 € in total. The other ten square metres of home explain barely 3,992 €.
And here is the proof that the culprit is the brief and not the floor area: if those same 100 m² were done with a bathroom and a WC, the functional budget would be 49,550 € and the metre would come out at 496 €/m² — below the 506 €/m² of the 90 m² flat. The curve is not broken by the metres. It is broken by the second shower.
That is why, on the site visit for a 100 m² flat, the first question we ask is not which finishes you like: it is how many showers you really need. It is the one decision on this page that moves 9,418 € at functional and 18,306 € at high specification before you have chosen a single tile.

Up to 90 m², air conditioning with splits is almost always the sensible choice: two or three indoor units cover the home and the installation does not constrain the works. From 100 m² the sum changes, because the splits needed become four or five, and each one brings its own outdoor unit, its refrigerant line, its condensate drain and its visible patch on the wall.
The alternative is a single ducted unit distributing through the suspended ceiling. This page’s example budget already includes 40 m² of plasterboard suspended ceiling, which is exactly where it would run: the building work is, to a large extent, already paid for. What it does not include — and that is why it appears under “not included” — is the unit, the ducts, the grilles and the access hatches, because their cost depends on the real routing of your floor and not on the metres.
The important thing in this section is not the price: it is the timing. The duct route is decided in week 3, when the frame of the suspended ceiling goes up, and it determines heights, the position of access hatches and even where the spotlights can go. Deciding it in week 11, with the ceiling already closed and painted, means opening the whole thing up. That is the difference between an item and a new job.

Removal of floors and wall finishes, stripping out the two bathrooms and the non-structural partitions, and setting out the new layout. We estimate in the order of 13 m³ of rubble.
Plumbing with its 13 points for the two bathrooms and the kitchen, electrics for the 8 rooms with a certificate, and the plasterboard for the ~40 m² of suspended ceiling — which is where the air conditioning will run if it is ducted.
Waterproofing and tiling of both rooms, fitting the two full bathrooms and the 10 m² kitchen, and laying the flooring throughout the home. It is the longest phase and the one that justifies the budget.
The eight doors, the fittings, skimming and painting some 300 m² of walls and ceilings, the final clean and a handover walk-round with the site manager.
12–13 weeks (full renovation, two full bathrooms) — 12 to 13 weeks is the indicative estimate for a full 100 m² renovation with two full bathrooms — our own planning, not a figure from our price table: 2 for demolition, 4 for services and building work, 4 for wet rooms, kitchen and flooring, and 2-3 for joinery, painting and snagging. The long phase is the bathrooms, and not because of the metres but because of the sequence: waterproofing, testing, tiling and fitting sanitaryware are four steps that cannot overlap within the same room, and here there are two. The real timescales that bracket this estimate are those of the two projects below: our 75 m² full renovation in Vic took 10 weeks and the 120 m² main-floor flat in Santa Coloma, 16; a 100 m² flat falls between the two. That Vic project, incidentally, came in at 59,500–62,000 € — practically the functional example budget for this size. The programme comes in writing with the quote.
Permits: what a 100 m² flat needs. Internal work that does not touch the structure: a prior notification to the council. What is specific to this size is that the second full bathroom usually means a new stack or extending an existing one, and that is no longer just a municipal formality: it needs the agreement of the owners’ community, because the stacks are communal property. We ask for it in writing before starting, not after. If a load-bearing wall is also opened to join living room and kitchen — common in 100 m² floors — a project, a lintel calculation and a major-works licence are needed. We handle all of it and it appears itemised in the quote.
Not every cut has the same effect: these are the items where saving is sensible, and the ones where it ends up costing more.
Put the three rows in order of floor area and look at the price of the metre: 506 at 90 m², 590 at 100 and 536 at 120. It is the only time in the whole series that it goes up and comes back down, and the cause is not the floor area but the brief: the 100 m² flat in this table has two full bathrooms; the 90 has a bathroom and a WC; the 120 has the same two bathrooms spread over twenty more metres.
| Floor area | Functional | Mid-range |
|---|---|---|
| 100 m² flat (4 bedrooms, 2 full bathrooms) | 58,968 € · 590 €/m² | 85,767 € · 858 €/m² |
| 90 m² flat (3-4 bedrooms, bathroom and WC) | 45,558 € · 506 €/m² | 65,453 € · 727 €/m² |
| 120 m² flat (4-5 bedrooms, 2 full bathrooms) | 64,302 € · 536 €/m² | 93,140 € · 776 €/m² |
* Indicative prices, excluding VAT. They vary with the starting condition of the home, the municipality and the finishes chosen.
Carrer de Verdaguer, Vic75 m²10 weeksReal projectFull renovation of an old-building flat in Vic (75 m²)Twenty-five square metres smaller, the same bill as the 100 m² exampleA living room with a pine-slat partition and a matching bookcaseA green herringbone-tiled bathroom and a grey metro-tile kitchenProof that scope weighs more than floor areaIndicative costindicative · excluding VAT59,500–62,000 €
Carrer Major, Santa Coloma de Gramenet120 m²16 weeksReal projectMain-floor flat in Santa Coloma (120 m²)Twenty square metres larger and double the bill: genuine high specificationOak herringbone parquet across the whole floorTravertine and microcement bathrooms, kitchen with an islandWhere the high-specification column of the table ends upIndicative costindicative · excluding VAT111,500–122,500 €The ones we are asked most before a quote is signed.
The example budget on this page comes to 58,968 € at a functional specification, 85,767 € at mid-range and 119,148 € for high specification, excluding VAT, for a scope of 4 bedrooms, two full bathrooms and a kitchen. Keeping the six windows, the functional figure falls to 55,650 €. If a bathroom and a WC are enough instead of two full bathrooms, it falls to 49,550 €.
Because the brief changes, not just the floor area. The 90 m² budget has one full bathroom and a WC (11,092 € at functional); the 100 m² one has two full bathrooms (20,510 €). That 9,418 € difference is 70% of everything the budget rises by between one size and the other, and it is what takes the metre from 506 to 590 €. With a bathroom and a WC, the same 100 m² would come to 496 €/m².
In our price table, a full bathroom of about 4 m² — building work, waterproofing, tiling, sanitaryware, taps, shower screen and vanity unit — comes to 10,255 € at functional, 15,759 € at mid-range and 20,467 € for high specification. The table on this page carries that figure twice. A guest WC without a shower, by contrast, is 837 € at functional: the difference between the two options is the most important financial decision in a 100 m² flat.
From 100 m² you need four or five splits to cover the home, and that is where a single ducted unit starts to compete on cost and wins hands down on looks and on acoustic comfort. The example budget already includes the 40 m² of suspended ceiling the route would run through; the unit, ducts and grilles are priced separately because they depend on your floor. The critical thing is to decide in week 3, before the suspended ceiling is closed.
If the new bathroom needs a new stack or an extension of an existing one, yes: stacks are communal parts of the building and the work requires the community’s agreement. We handle it and ask for it in writing before the works start, never halfway through. If the bathroom uses an existing stack and is simply connected to it, the municipal prior notification is enough.
With two full bathrooms there is a route that does not exist in smaller flats: redo one first and keep the other in use, then the other way round. It stretches the programme by a week or two and makes the logistics dearer, but it saves temporary rental. In a full renovation done in one go, no: there are four weeks without water or a kitchen.
No: all prices on this page exclude VAT, as in our quotes. The applicable rate (10% reduced or 21%) depends on your case — private use, age of the building and the weight of materials — and we confirm it in writing in the quote.
Full renovations in Barcelona and across Catalonia. A fixed, itemised quote, a dedicated site manager who keeps you informed and a written warranty.
A free site visit, a fixed itemised quote and a written programme. What we sign is what you pay.