Price guide · October 2026

How much does it cost to renovate a 100 m² flat: the size where the price per metre rises again

With our price table and a 100 m² scope with 4 bedrooms, two full bathrooms and a 10 m² kitchen, the example budget comes to 58,968 € at a functional specification, 85,767 € at mid-range and 119,148 € for high specification, excluding VAT, with the indicative range on the cards calculated from those three totals. This page has a quirk you will not find on the others: at 100 m² the price per metre goes up, from 506 to 590 €/m². It is not a calculation error or a surcharge: it is the second full bathroom, and the whole sum is below.

Living room with the Catalan vaulted ceiling and exposed brick restored, two balcony doors and split air conditioning — our project in Poble-sec, Barcelona

Functional

56,100 € – 70,800 €

Standard finishes, layout unchanged

Mid-range

81,500 € – 103,000 €

Selected materials, possible re-planning

High specification

113,200 € – 143,000 €

Premium materials and interior design

Indicative prices · VAT not included · not a binding offer. Your exact figure comes from the free site visit, fixed and itemised.

The starting point

What a 100 m² flat is (and what brief we assume here)

The 100 m² flat in the Barcelona area is the first one planned from the start with two full bathrooms instead of a bathroom and a guest WC: four bedrooms, eight rooms, eight doors, six windows and a 10 m² kitchen that has room for a peninsula. It is the format of the seventies blocks in Les Corts, Sant Gervasi or Sant Cugat, and of the principal floors recovered in Ciutat Vella and Gràcia.

That brief is a decision, not a fact about floor area, and it is the reason this page exists. We could have priced the 100 m² with a bathroom and a WC — as we do on the 90 m² page — and the €/m² would have gone on falling quite happily. But that would be misleading you: when someone renovates 100 m² in Barcelona, what they ask for is that the second wet room has a proper shower.

The other change specific to this size is that air conditioning stops being solved room by room. With 100 m² and 40 m² of suspended ceiling it already makes sense to consider ducts — and that is decided in week 3, not in week 11.

  • 4 bedrooms · 2 full bathrooms · ~10 m² kitchen
  • 8 rooms, 8 doors, 6 windows · 590 €/m², the only size where the metre rises
  • Ducted air conditioning: viable for the first time, decidable only at the start
Living room with restored Catalan vaults, an indirect-light cornice and an open kitchen at the far end — our project in the Barri Gòtic, Barcelona
Typical price per m²590 – 1,191 €/m²
Living room with restored Catalan vaults, an indirect-light cornice and an open kitchen at the far end — our project in the Barri Gòtic, Barcelona
From our price table, not a template

Itemised example budget: 100 m², three specifications

Figures calculated item by item from our price table (real, signed quotes), for a 100 m² scope with 4 bedrooms, TWO full bathrooms and a kitchen. The bathrooms row is double, hence its weight: it is the key to this whole page. Excluding VAT; not a binding offer.

ItemFunctionalMid-rangeHigh spec% of total
Demolition and rubble clearance · floor lifted + strip-out1,912 €2,556 €5,616 €3%
Building work and labouring3,200 €3,279 €3,681 €4%
Plasterboard and suspended ceilings (~40 m²)1,840 €2,160 €2,600 €3%
Plumbing (adaptation + 13 points) · bathrooms and kitchen3,786 €5,260 €7,328 €6%
Electrics (8 rooms) · with certificate (CIE)1,784 €2,544 €4,392 €3%
Complete bathrooms (~4 m² each) · building work + tiling + sanitaryware20,510 €31,518 €40,934 €37%
Complete kitchen (~10 m²) · units, worktop and appliances5,518 €7,650 €14,961 €9%
Flooring throughout (AC5 timber laminate)3,700 €4,300 €4,800 €5%
Internal joinery (8 doors)2,000 €4,600 €6,240 €5%
Windows (6 units) · if you keep yours, subtract this line3,318 €6,900 €13,296 €8%
Skimming and full repaint · ~300 m² of wall and ceiling surface11,400 €15,000 €15,300 €17%
Total for the example budget58,968 €85,767 €119,148 €
Equivalent per m²590 €/m²858 €/m²1,191 €/m²
When the price per metre goes up

The full sum: 9,418 € that break the curve

Every page in this series repeats the same idea: the more metres, the cheaper the metre, because kitchen, bathroom and services cost almost the same and are spread over more floor area. At 100 m² that idea stops being true, and it is better to say so out loud than to hide it behind an average.

The sum is this. In the 90 m² budget, the two wet rooms are one full bathroom (10,255 €) and a guest WC (837 €): 11,092 € at functional. In the 100 m² budget they are two full bathrooms: 20,510 €. The difference, 9,418 €, accounts for 70% of everything the budget rises by in going from 90 to 100 m² — 13,410 € in total. The other ten square metres of home explain barely 3,992 €.

And here is the proof that the culprit is the brief and not the floor area: if those same 100 m² were done with a bathroom and a WC, the functional budget would be 49,550 € and the metre would come out at 496 €/m² — below the 506 €/m² of the 90 m² flat. The curve is not broken by the metres. It is broken by the second shower.

That is why, on the site visit for a 100 m² flat, the first question we ask is not which finishes you like: it is how many showers you really need. It is the one decision on this page that moves 9,418 € at functional and 18,306 € at high specification before you have chosen a single tile.

≈54%Almost fixed cost: kitchen, bathroom and services
≈46%The only part that scales with floor area
Built-in niches framed in a gold profile inside a bathroom under construction — our project in Horta, Barcelona
Built-in niches framed in a gold profile inside a bathroom under construction — our project in Horta, Barcelona
The second threshold at 100 m²

Ducts or splits: the sum that can only be done at the start

Up to 90 m², air conditioning with splits is almost always the sensible choice: two or three indoor units cover the home and the installation does not constrain the works. From 100 m² the sum changes, because the splits needed become four or five, and each one brings its own outdoor unit, its refrigerant line, its condensate drain and its visible patch on the wall.

The alternative is a single ducted unit distributing through the suspended ceiling. This page’s example budget already includes 40 m² of plasterboard suspended ceiling, which is exactly where it would run: the building work is, to a large extent, already paid for. What it does not include — and that is why it appears under “not included” — is the unit, the ducts, the grilles and the access hatches, because their cost depends on the real routing of your floor and not on the metres.

The important thing in this section is not the price: it is the timing. The duct route is decided in week 3, when the frame of the suspended ceiling goes up, and it determines heights, the position of access hatches and even where the spotlights can go. Deciding it in week 11, with the ceiling already closed and painted, means opening the whole thing up. That is the difference between an item and a new job.

  • From 100 m² you need 4-5 splits: that is where ducts start to compete
  • The 40 m² of suspended ceiling in the example budget is already the building work for the route
  • Decide it in week 3 or pay twice
Heating manifolds with their pumps installed in the plant room — our project in Diagonal Mar, Barcelona
Heating manifolds with their pumps installed in the plant room — our project in Diagonal Mar, Barcelona
Your home is not the “example”

What pushes the price up or down in your case

What pushes it up

  • Making the second bathroom a full one, with a showerThis is the decision that defines this page: going from bathroom + WC to two full bathrooms is 9,418 € more at functional and 18,306 € more at high specification.
  • Ducted air conditioningFrom 100 m² it stops being an indulgence and starts to compete with four or five splits, but it needs a continuous suspended ceiling, access hatches and a route planned from day one.
  • Two wet rooms far from the same stackEvery metre of drain that has to cross a suspended ceiling or a raised floor is paid for in building work, not in plumbing.
  • A building with no liftMaterials go up and rubble comes down by hand: in 100 m² we estimate in the order of 13 m³, and it adds around 5–8% to the job.

What brings it down

  • Leaving the second bathroom as a WCIf you do not need two showers, the functional budget falls from 58,968 € to 49,550 € and the metre drops to 496 €/m² — lower even than the 90 m² flat.
  • Grouping the two wet roomsBack-to-back bathrooms, or ones on the same service shaft, share risers and stack: fewer metres of pipe, fewer chases and less building work.
  • Keeping the six windowsYou subtract 3,318 to 13,296 € depending on the range: the functional example budget falls from 58,968 € to 55,650 €.
  • A 10 m² kitchen costs no more than a 7 m² oneThe kitchen item is the same in all our example budgets: what makes it dearer is the units and the worktop, not the metres of floor.
Timescales

How long a 100 m² flat renovation takes

Weeks 1–2Demolition and setting out

Removal of floors and wall finishes, stripping out the two bathrooms and the non-structural partitions, and setting out the new layout. We estimate in the order of 13 m³ of rubble.

Weeks 3–6Services and building work

Plumbing with its 13 points for the two bathrooms and the kitchen, electrics for the 8 rooms with a certificate, and the plasterboard for the ~40 m² of suspended ceiling — which is where the air conditioning will run if it is ducted.

Weeks 7–10The two bathrooms, kitchen and flooring

Waterproofing and tiling of both rooms, fitting the two full bathrooms and the 10 m² kitchen, and laying the flooring throughout the home. It is the longest phase and the one that justifies the budget.

Weeks 11–13Joinery, painting and handover

The eight doors, the fittings, skimming and painting some 300 m² of walls and ceilings, the final clean and a handover walk-round with the site manager.

12–13 weeks (full renovation, two full bathrooms) — 12 to 13 weeks is the indicative estimate for a full 100 m² renovation with two full bathrooms — our own planning, not a figure from our price table: 2 for demolition, 4 for services and building work, 4 for wet rooms, kitchen and flooring, and 2-3 for joinery, painting and snagging. The long phase is the bathrooms, and not because of the metres but because of the sequence: waterproofing, testing, tiling and fitting sanitaryware are four steps that cannot overlap within the same room, and here there are two. The real timescales that bracket this estimate are those of the two projects below: our 75 m² full renovation in Vic took 10 weeks and the 120 m² main-floor flat in Santa Coloma, 16; a 100 m² flat falls between the two. That Vic project, incidentally, came in at 59,500–62,000 € — practically the functional example budget for this size. The programme comes in writing with the quote.

Permits: what a 100 m² flat needs. Internal work that does not touch the structure: a prior notification to the council. What is specific to this size is that the second full bathroom usually means a new stack or extending an existing one, and that is no longer just a municipal formality: it needs the agreement of the owners’ community, because the stacks are communal property. We ask for it in writing before starting, not after. If a load-bearing wall is also opened to join living room and kitchen — common in 100 m² floors — a project, a lintel calculation and a major-works licence are needed. We handle all of it and it appears itemised in the quote.

A genuinely fixed quote

What the price includes (and what it does not)

Included

  • A dedicated site manager running the renovation
  • Labour for every trade under a single contract
  • Materials at the specification stated against each item
  • Waste management: skip and haulage to an authorised tip
  • Protection of communal areas and a final builders’ clean
  • Certificates for the new services (electrical CIE, plumbing)
  • Filing the prior notification of works

Not included

  • VAT: 10% reduced rate or 21% depending on your case — confirmed in writing in the quote
  • Council licence fees (passed on at cost, depending on the council)
  • Loose furniture and decoration
  • Ducted air conditioning: priced separately because it depends on the suspended ceiling and the routing — see below
  • Extra scope decided during the works (priced separately, in writing, before it is carried out)
The advice we would give a friend

Where to save on 100 m² — and where never to

Not every cut has the same effect: these are the items where saving is sensible, and the ones where it ends up costing more.

Save here

  • A well-finished main bathroom and a plainer second one: they do not have to be twins
  • Standard sanitaryware and taps in the guest bathroom
  • Well-placed splits rather than ducts, if the floor has no continuous suspended ceiling
  • Keeping the exterior joinery if it insulates well

Never save here

  • Waterproofing both showers: that is two risks, not one
  • The air-conditioning routing: redoing it later means opening the whole suspended ceiling
  • Water and electrical installations: they are what the next 20 years rest on
  • Site management: with two bathrooms there are more trades overlapping, not fewer
Comparison

What if the flat were 90 or 120 m²?

Put the three rows in order of floor area and look at the price of the metre: 506 at 90 m², 590 at 100 and 536 at 120. It is the only time in the whole series that it goes up and comes back down, and the cause is not the floor area but the brief: the 100 m² flat in this table has two full bathrooms; the 90 has a bathroom and a WC; the 120 has the same two bathrooms spread over twenty more metres.

Floor areaFunctionalMid-range
100 m² flat (4 bedrooms, 2 full bathrooms)58,968 € · 590 €/m²85,767 € · 858 €/m²
90 m² flat (3-4 bedrooms, bathroom and WC)45,558 € · 506 €/m²65,453 € · 727 €/m²
120 m² flat (4-5 bedrooms, 2 full bathrooms)64,302 € · 536 €/m²93,140 € · 776 €/m²

* Indicative prices, excluding VAT. They vary with the starting condition of the home, the municipality and the finishes chosen.

Common questions

Questions about the cost of renovating 100 m²

The ones we are asked most before a quote is signed.

How much does it cost to renovate a 100 m² flat?

The example budget on this page comes to 58,968 € at a functional specification, 85,767 € at mid-range and 119,148 € for high specification, excluding VAT, for a scope of 4 bedrooms, two full bathrooms and a kitchen. Keeping the six windows, the functional figure falls to 55,650 €. If a bathroom and a WC are enough instead of two full bathrooms, it falls to 49,550 €.

Why does the price per m² rise from 90 to 100 m²?

Because the brief changes, not just the floor area. The 90 m² budget has one full bathroom and a WC (11,092 € at functional); the 100 m² one has two full bathrooms (20,510 €). That 9,418 € difference is 70% of everything the budget rises by between one size and the other, and it is what takes the metre from 506 to 590 €. With a bathroom and a WC, the same 100 m² would come to 496 €/m².

How much does the second full bathroom cost?

In our price table, a full bathroom of about 4 m² — building work, waterproofing, tiling, sanitaryware, taps, shower screen and vanity unit — comes to 10,255 € at functional, 15,759 € at mid-range and 20,467 € for high specification. The table on this page carries that figure twice. A guest WC without a shower, by contrast, is 837 € at functional: the difference between the two options is the most important financial decision in a 100 m² flat.

Ducted air conditioning or splits?

From 100 m² you need four or five splits to cover the home, and that is where a single ducted unit starts to compete on cost and wins hands down on looks and on acoustic comfort. The example budget already includes the 40 m² of suspended ceiling the route would run through; the unit, ducts and grilles are priced separately because they depend on your floor. The critical thing is to decide in week 3, before the suspended ceiling is closed.

Do I need the community’s permission for the second bathroom?

If the new bathroom needs a new stack or an extension of an existing one, yes: stacks are communal parts of the building and the work requires the community’s agreement. We handle it and ask for it in writing before the works start, never halfway through. If the bathroom uses an existing stack and is simply connected to it, the municipal prior notification is enough.

Can you live in the flat during the renovation?

With two full bathrooms there is a route that does not exist in smaller flats: redo one first and keep the other in use, then the other way round. It stretches the programme by a week or two and makes the logistics dearer, but it saves temporary rental. In a full renovation done in one go, no: there are four weeks without water or a kitchen.

Do these prices include VAT?

No: all prices on this page exclude VAT, as in our quotes. The applicable rate (10% reduced or 21%) depends on your case — private use, age of the building and the weight of materials — and we confirm it in writing in the quote.

Who we are

Full renovations in Barcelona and across Catalonia. A fixed, itemised quote, a dedicated site manager who keeps you informed and a written warranty.

Related services

Guides and calculators

Want your exact figure, not a range?

A free site visit, a fixed itemised quote and a written programme. What we sign is what you pay.

✆ Call✦ WhatsAppGet a quote →