Price guide · October 2026

How much does it cost to renovate a 120 m² flat: the size where joinery rules

Calculated with our price table for a 120 m² flat with 4-5 bedrooms, two full bathrooms and a 12 m² kitchen: 64,302 € at a functional specification, 93,140 € at mid-range and 128,813 € for high specification, excluding VAT; the indicative range on the cards, the same one the calculator gives, is built on those totals. The metre falls again — 536 €/m², against 590 for a 100 m² flat — because the same two bathrooms are spread over twenty more metres. But what really sets this size apart is something else: it is the first where joinery costs more than the services.

Made-to-measure dressing room with a built-in desk beside the paned window, over oak herringbone parquet — our 120 m² project in Santa Coloma de Gramenet

Functional

61,100 € – 77,200 €

Standard finishes, layout unchanged

Mid-range

88,500 € – 111,800 €

Selected materials, possible re-planning

High specification

122,400 € – 154,600 €

Premium materials and interior design

Indicative prices · VAT not included · not a binding offer. Your exact figure comes from the free site visit, fixed and itemised.

The starting point

What a 120 m² flat is (and what brief really fits)

At 120 m² the floor stops being a sum of rooms and starts to admit a brief. Our example budget assumes 4-5 bedrooms, two full bathrooms and a 12 m² kitchen: nine rooms, nine doors, seven windows. It is the principal floor of the grand period buildings of Sant Gervasi, Sarrià or the Eixample, and the large seventies flat in Sant Cugat, Pedralbes or Santa Coloma.

What changes compared with 100 m² is not the equipment — the two bathrooms and the kitchen were already there — but what can be done with the extra twenty metres. In practice they almost always go to the same place: turning the principal bedroom into a suite with its own bathroom and dressing room. It is the brief that defines this size and the one that justifies the fifteen weeks of programme.

And it has an economic consequence you will not see on any other page in this series: at 120 m², the timber items weigh more than the pipe and cable ones.

  • 4-5 bedrooms · 2 full bathrooms · ~12 m² kitchen
  • 9 rooms, 9 doors, 7 windows · 536 €/m² at functional
  • Suite with dressing room: the brief particular to this size
Entrance hall with a backlit mirror and an industrial-style glazed door over herringbone parquet — our 120 m² project in Santa Coloma de Gramenet
Typical price per m²536 – 1,073 €/m²
Entrance hall with a backlit mirror and an industrial-style glazed door over herringbone parquet — our 120 m² project in Santa Coloma de Gramenet
From our price table, not a template

Itemised example budget: 120 m², three specifications

Figures calculated item by item from our price table (real, signed quotes), for a 120 m² scope with 4-5 bedrooms, two full bathrooms and a kitchen. Made-to-measure workshop joinery — dressing rooms, wardrobe runs, bookcases — is not in this table: it is priced piece by piece. Excluding VAT; not a binding offer.

ItemFunctionalMid-rangeHigh spec% of total
Demolition and rubble clearance · floor lifted + strip-out2,256 €3,018 €6,588 €3%
Building work and labouring3,776 €3,855 €4,289 €4%
Plasterboard and suspended ceilings (~48 m²)2,208 €2,592 €3,120 €3%
Plumbing (adaptation + 13 points) · bathrooms and kitchen3,786 €5,260 €7,328 €6%
Electrics (9 rooms) · with certificate (CIE)2,007 €2,862 €4,941 €3%
Complete bathrooms (~4 m² each) · building work + tiling + sanitaryware20,510 €31,518 €40,934 €34%
Complete kitchen (~12 m²) · units, worktop and appliances5,518 €7,650 €14,961 €8%
Flooring throughout (AC5 timber laminate)4,440 €5,160 €5,760 €6%
Internal joinery (9 doors)2,250 €5,175 €7,020 €6%
Windows (7 units) · if you keep yours, subtract this line3,871 €8,050 €15,512 €9%
Skimming and full repaint · ~360 m² of wall and ceiling surface13,680 €18,000 €18,360 €19%
Total for the example budget64,302 €93,140 €128,813 €
Equivalent per m²536 €/m²776 €/m²1,073 €/m²
The arithmetic of 120 m²

The crossover: when timber overtakes pipe and cable

This whole series insists that services are the cost that does not scale. At 60 m², plumbing and electrics come to 3,601 € against 3,462 € for doors and windows: services win. At 90 m², 4,567 € against 4,515 €: they win by a whisker. At 100 m², 5,570 € against 5,318 €: still winning.

At 120 m² it flips. Internal joinery and windows come to 6,121 € at functional, against 5,793 € for plumbing and electrics. And at mid-range the gap shoots up: 13,225 € of timber against 8,122 € of services, more than one and a half times as much. At high specification, 22,532 € against 12,269 €.

The reason is simple and not at all mysterious: services are counted in points and rooms, and beyond a certain size they barely grow — the 13 plumbing points in this table are the same as in the 100 m² flat. Joinery, on the other hand, is counted in units: every room brings its door, every opening in the façade its window, every wall its run of wardrobe fronts.

The practical conclusion for anyone renovating 120 m²: the budget is won or lost in the timber chapter. That is where it pays to spend time deciding — workshop-made or off the shelf, flush or with a visible frame, oak or lacquered — and not arguing over the price of a metre of pipe.

≈49%Almost fixed cost: kitchen, bathroom and services
≈51%The only part that scales with floor area
Wall-to-wall MDF carcass just fitted before priming, in the living room of our project in Poblenou, Barcelona
Wall-to-wall MDF carcass just fitted before priming, in the living room of our project in Poblenou, Barcelona
The brief for the extra twenty metres

Suite and dressing room: what it really costs is not the space

A suite is three things at once: a bedroom, a bathroom that moves close to it and a dressing room that is stolen from something else. In a 120 m² flat all three fit, which is why almost every project of this size ends up there. What you need to understand before signing is that the cost is not in the metres, it is in what gets built inside them.

The building-work part is modest. The dividing partition, the new doorway and the adaptation of the plumbing are already spread across the building work (3,776 €) and plumbing (3,786 €) items in the table above, because they are the same metres of wall and the same thirteen points. A dressing room adds neither a stack nor a consumer unit.

The expensive part is the workshop-made joinery, and that is why we leave it out of the table instead of putting in an average figure that would mean nothing. A floor-to-ceiling wardrobe front, a dressing room with shelves, rails and visible drawers, a bookcase from wall to wall: all of it is priced by measuring your wall, not by estimating your square metres. To give you an idea of the order of magnitude from one of our own real projects: the made-to-measure bookcase in the Poblenou living room, 24 m² of room, was a job of 34,000–40,000 € including carcass, lacquering, LED lighting and sliding panel. A single piece of joinery can cost as much as half the functional budget for this flat.

Hence the rule we give everyone renovating 120 m²: decide first how much workshop-made joinery you want, then the rest. It is the only item on this page capable of doubling the bill without changing a single square metre of the floor plan.

  • The building work for a suite is already spread across the building-work and plumbing items of the example budget
  • A dressing room adds neither a stack nor a consumer unit: it adds linear metres of workshop-made joinery
  • Measurements are taken with the walls plumb, never from a drawing
Floor-to-ceiling wardrobe front in petrol blue beside the air-conditioning grille, in a principal bedroom — our project in Galvany, Barcelona
Floor-to-ceiling wardrobe front in petrol blue beside the air-conditioning grille, in a principal bedroom — our project in Galvany, Barcelona
Your home is not the “example”

What pushes the price up or down in your case

What pushes it up

  • Turning the principal bedroom into a suite with a dressing roomIt is not one item: it is three. A new partition, a bathroom that moves closer to the bedroom and floor-to-ceiling workshop-made joinery.
  • Workshop-made joinery instead of off-the-shelfBetween the standard door and the flush-fitted made-to-measure leaf there is a factor of three in this table: 2,250 € against 7,020 € for the same nine doors.
  • Seven windows instead of fourAt high specification they come to 15,512 €: more than the plumbing and electrics of the whole home put together.
  • High ceilings and balcony doors in a grand period buildingSome 360 m² of wall to skim and paint, and exterior joinery that is almost never standard.

What brings it down

  • Off-the-shelf joinery, properly fittedA catalogue door that is well hung and well hinged lasts as long as a workshop-made one; what you notice is the ironmongery and the fitting, not the catalogue.
  • Integrated wardrobes instead of a separate dressing roomA floor-to-ceiling front in the bedroom itself gives the same storage as a dressing room, without stealing metres or needing new partitions.
  • Keeping the two bathrooms where they areWith the plumbing already grouped, the 3,786 € of that item stays as adaptation and does not turn into building work.
  • Keeping the seven windowsYou subtract 3,871 to 15,512 € depending on the range, and in a grand period building restoring the timber joinery is usually better value than replacing it.
Timescales

How long a 120 m² flat renovation takes

Weeks 1–3Demolition and setting out

Removal of floors and wall finishes, stripping out the two bathrooms and the non-structural partitions, and setting out the new layout, suite included. We estimate in the order of 15 m³ of rubble.

Weeks 4–7Services and building work

Plumbing with its 13 points, electrics for the 9 rooms with a certificate, the new partitions for the suite and the plasterboard for the ~48 m² of suspended ceiling.

Weeks 8–11Bathrooms, kitchen and flooring

Waterproofing and tiling of the two rooms, fitting the bathrooms and the 12 m² kitchen, and laying the flooring throughout the home.

Weeks 12–15Joinery, painting and handover

The nine doors, the workshop-made joinery if there is any, the fittings, skimming and painting some 360 m² of walls and ceilings, the final clean and a handover walk-round with the site manager.

14–15 weeks (full renovation) · 16 weeks with full workshop-made joinery — 14 to 15 weeks is the indicative estimate for a full 120 m² renovation — our own planning, not a figure from our price table: 3 for demolition, 4 for services and building work, 4 for bathrooms, kitchen and flooring, and 3-4 for joinery, painting and snagging. If there is workshop-made joinery, the programme stops depending on the building work alone: measurements are taken when the walls are plumb — not before — and the workshop needs its weeks of manufacture, which run in parallel with everything else if the order went in on time. Our reference project at this size, the 120 m² main-floor flat in Santa Coloma, took 16 weeks with herringbone parquet, an industrial-style glazed screen and travertine bathrooms. The programme comes in writing with the quote.

Permits: what a 120 m² flat needs. Internal work that does not touch the structure: a prior notification to the council. At 120 m² there are two situations that almost always arise and are worth anticipating. The first is the suite: creating a new opening between the principal bedroom and its bathroom is trivial if the partition is not load-bearing, and a project, a lintel calculation and a major-works licence if it is — and in grand period buildings from the twenties it is more often than it looks. The second is the façade: at this size there are almost always balcony doors, and replacing them with new joinery in a building with environmental protection needs specific authorisation, with the profile and colour approved. We check it on the visit, we handle the paperwork ourselves and the cost is itemised as a line in the quote.

A genuinely fixed quote

What the price includes (and what it does not)

Included

  • A dedicated site manager running the renovation
  • Labour for every trade under a single contract
  • Materials at the specification stated against each item
  • Waste management: skip and haulage to an authorised tip
  • Protection of communal areas and a final builders’ clean
  • Certificates for the new services (electrical CIE, plumbing)
  • Filing the prior notification of works

Not included

  • VAT: 10% reduced rate or 21% depending on your case — confirmed in writing in the quote
  • Council licence fees (passed on at cost, depending on the council)
  • Loose furniture and decoration
  • Made-to-measure workshop joinery (dressing rooms, wardrobe runs, bookcases): priced piece by piece — see below
  • Extra scope decided during the works (priced separately, in writing, before it is carried out)
The advice we would give a friend

Where to save on 120 m² — and where never to

Not every cut has the same effect: these are the items where saving is sensible, and the ones where it ends up costing more.

Save here

  • Off-the-shelf joinery with good ironmongery in the secondary rooms and workshop-made only where it shows
  • Built-in wardrobes in the bedroom rather than a dressing room with its own partitions
  • Standard sanitaryware and taps in the second bathroom
  • Restoring sound timber exterior joinery rather than replacing it

Never save here

  • The measurements for workshop-made joinery: they are taken with the walls plumb, never from a drawing
  • Waterproofing both showers: that is two risks, not one
  • Skimming 360 m² of wall: it is what separates a renovated grand period flat from a merely painted one
  • Site management: 15 weeks with six trades do not coordinate themselves
Comparison

What if the flat were 100 or 90 m²?

From 100 to 120 m² the budget rises 5,334 € — 9% — while the floor area grows 20%, because the two full bathrooms were already paid for. It is the cleanest fall in €/m² in the whole series: here the new metres are cheap metres.

Floor areaFunctionalMid-range
120 m² flat (4-5 bedrooms, 2 full bathrooms)64,302 € · 536 €/m²93,140 € · 776 €/m²
100 m² flat (4 bedrooms, 2 full bathrooms)58,968 € · 590 €/m²85,767 € · 858 €/m²
90 m² flat (3-4 bedrooms, bathroom and WC)45,558 € · 506 €/m²65,453 € · 727 €/m²

* Indicative prices, excluding VAT. They vary with the starting condition of the home, the municipality and the finishes chosen.

Common questions

Questions about the cost of renovating 120 m²

The ones we are asked most before a quote is signed.

How much does it cost to renovate a 120 m² flat?

The example budget on this page comes to 64,302 € at a functional specification, 93,140 € at mid-range and 128,813 € for high specification, excluding VAT, for a scope of 4-5 bedrooms, two full bathrooms and a kitchen. Keeping the seven windows, the functional figure falls to 60,431 €. Made-to-measure workshop joinery is extra, because it is priced by measuring walls and not square metres.

Why do you say joinery rules at 120 m²?

Because it is the first size at which the timber items overtake the services. At functional, internal joinery plus windows come to 6,121 € against 5,793 € for plumbing and electrics; at mid-range, 13,225 € against 8,122 €. The reason is that services are counted in points and barely grow beyond a certain size — the 13 plumbing points are the same as in a 100 m² flat — whereas joinery is counted in units: a door per room, a window per opening.

How much does it cost to build a suite with a dressing room?

The building-work part is already inside the example budget: the partition, the new opening and the plumbing adaptation are spread across the building-work and plumbing items, because they add neither a stack nor a consumer unit. What is extra is the workshop-made joinery, which is measured on the finished wall. As a guide to the order of magnitude, a single made-to-measure living-room bookcase of ours, in Poblenou, was a job of 34,000–40,000 €.

Why does the price per metre fall compared with a 100 m² flat?

Because the two full bathrooms, which are the big step in cost, were already paid for at 100 m². The additional twenty metres are spread across bedrooms, corridor and living room, which only bring flooring, painting, plasterboard, a door and a window. The budget rises 9% while the floor area grows 20%, and the metre falls from 590 to 536 €.

Workshop-made or off-the-shelf joinery?

Both are defensible, and the honest answer is to mix them. A catalogue door with good ironmongery, properly hung, behaves the same as a workshop-made one; what you notice is the fitting. The workshop wins where the size is not standard or where the piece is the star: a floor-to-ceiling wardrobe, a dressing room, a bookcase, a glazed screen. In this table, moving the nine doors from off-the-shelf to flush workshop-made takes you from 2,250 € to 7,020 €.

How long does a 120 m² renovation take?

Indicatively, 14 to 15 weeks for a full renovation. The real timescale we can show you is that of our 120 m² main-floor flat in Santa Coloma: 16 weeks, with workshop-made joinery throughout the home. The workshop does not lengthen the programme if the order goes in on time, because it manufactures in parallel; it lengthens it when measurements are taken late, and measurements cannot be taken until the walls are plumb.

Do these prices include VAT?

No: all prices on this page exclude VAT, as in our quotes. The applicable rate (10% reduced or 21%) depends on your case — private use, age of the building and the weight of materials — and we confirm it in writing in the quote.

Who we are

Full renovations in Barcelona and across Catalonia. A fixed, itemised quote, a dedicated site manager who keeps you informed and a written warranty.

Related services

Guides and calculators

Want your exact figure, not a range?

A free site visit, a fixed itemised quote and a written programme. What we sign is what you pay.