Price guide · October 2026

The cost of renovating an 8 m² bathroom: freestanding bath, double basin and the full breakdown

With figures from our price table: an 8 m² bathroom with a freestanding bath and double basin comes to 10,763 € at a functional specification, 16,437 € at mid-range and 21,600 € for high specification, excluding VAT, opened up on the cards with the 5% below to 20% above margin our calculator uses. That is the headline of the page, and it is the end of the argument the other four pages open: the largest, best-equipped bathroom we price costs 8.5% more than the smallest. Almost three times the floor area, two more fittings and a freestanding bath, for an 846 € difference over the 9,917 € of a 3 m² bathroom.

Freestanding bath on a bed of white pebbles in front of a vertical garden, with a floor-standing tap and a glass lamp — our project in a flat in Les Tres Torres, Barcelona

Functional

10,300 € – 13,000 €

Standard finishes, layout unchanged

Mid-range

15,700 € – 19,800 €

Selected materials, possible re-planning

High specification

20,600 € – 26,000 €

Premium materials and interior design

Indicative prices · VAT not included · not a binding offer. Your exact figure comes from the free site visit, fixed and itemised.

The starting point

What an 8 m² bathroom is and what it allows that no other does

Eight square metres of bathroom do not come out of a standard flat: they come out of a house, a penthouse, a grand first-floor flat or of having joined the bathroom to a dressing room or a WC. On plan they are usually about 2.30 × 3.50 m, with two free long walls and, often, a window of their own.

What that size allows, and no other in this series does, is separating the two ways of using a bathroom: the bath stops being a place to shower standing up and becomes a freestanding piece, and the shower, if wanted, goes apart with its own tray and screen. It is the difference between a bathroom that does the job and one you spend time in.

This page’s example budget covers a freestanding bath with its taps, toilet and bidet, and a double-basin vanity unit. It does not include the separate shower: that is explained in the next section, with figures from our price table itself, because it is the question that always comes up and deserves an answer with numbers, not an estimate.

  • ~2.30 × 3.50 m: two free long walls and often a window of its own
  • Freestanding bath: the one piece that demands a set-out to the centimetre
  • The only size where bath and shower can live separately
Continuous veined marble worktop with a double basin, a walnut unit with brass handles and the bath at the far end — our project in a flat in Pedralbes, Barcelona
Typical price per m²1,345 – 2,700 €/m²
Continuous veined marble worktop with a double basin, a walnut unit with brass handles and the bath at the far end — our project in a flat in Pedralbes, Barcelona
From our price table, not a template

Itemised example budget: 8 m² bathroom, three specifications

Table anchored on the real project price of “complete bathroom renovation” in our price table, with tiling, flooring and waterproofing recalculated for 8 m² and the equipment that goes with this size: freestanding bath, toilet and bidet, and a double-basin vanity unit. The bath row replaces the shower-tray row here: the table prices one or the other, not both. And the closing row groups what the on-site price covers without itemising — demolition, building work, fitting and day rates. Excluding VAT; not a binding offer.

ItemFunctionalMid-rangeHigh spec% of total
Tiling (~34 m²)782 €1,020 €1,972 €6%
Porcelain flooring216 €320 €584 €2%
Waterproofing · wet area308 €946 €1,056 €6%
Freestanding bath and taps403 €509 €611 €3%
Toilet and bidet108 €215 €477 €1%
Vanity unit with double basin422 €578 €916 €4%
Plumbing (5 points + drains)1,474 €1,994 €2,756 €12%
Electrics and ventilation · with certificate (CIE)396 €502 €765 €3%
Demolition, building work, fitting and labour · included in the real on-site price6,654 €10,353 €12,463 €63%
Total for the example budget10,763 €16,437 €21,600 €
Equivalent per m²1,345 €/m²2,055 €/m²2,700 €/m²
The arithmetic of 8 m²

The biggest bathroom we calculate costs 8.5% more than the smallest

Here is the end of the argument the other four pages open. A 3 m² bathroom with the bare minimum costs 9,917 € at functional. This one, with 2.7 times the floor area, a bidet, double basin and freestanding bath, costs 10,763 €. The difference is 846 €, 8.5% — and a good part of those 846 € is not metres, it is the two pieces of equipment added.

The breakdown explains it: the items that do not scale come to 9,765 € of the 10,763 €, 91%. The only things that really grow with floor area are the 34 m² of tiling and the 8 m² of flooring, 998 € between them, against the 380 € of the 3 m² bathroom. The whole difference in the series fits in that line.

Put another way: in a bathroom you do not pay for space, you pay for services, waterproofing, fittings and craft — and those four things hardly know how many metres they have to cover. If you are comparing quotes, the number that tells you something is not the €/m² (here 1,345 €, on the 3 m² page 3,306 €): it is which sanitaryware goes in, how many plumbing points are redone, what it is waterproofed with and whether the installation is delivered with a certificate.

≈91%Almost fixed cost: sanitaryware, plumbing and waterproofing
≈9%The only thing that scales with the metres
Freestanding bath just placed and still wrapped between the marble wall panels, before the finishing touches — our project in Pedralbes, Barcelona
Freestanding bath just placed and still wrapped between the marble wall panels, before the finishing touches — our project in Pedralbes, Barcelona
What is particular to 8 m²

Freestanding bath and a separate shower: the one thing 8 m² really allow

Everything that fits in a 6 m² bathroom fits more comfortably in an 8. There is only one thing 8 m² allow and 6 do not: having bath and shower as two separate pieces, each with its own zone, instead of a bath with a screen over it doing both jobs by halves.

That configuration has two consequences worth knowing before falling in love with the photo. The first is technical: it means two wet areas, each with its own waterproofing, drain and taps. The second is about budget: this page’s itemised table prices the freestanding bath instead of the shower tray, not as well. The 403 to 611 € row is one or the other.

If you want both, the honest reference we can give you comes from the same price table: the tray and screen that fill that row on the 5 m² and 6 m² pages cost between 403 € and 611 € depending on range as supply. What we cannot give you in writing without seeing it is the associated work — the second waterproofing, the drain run to the stack, the taps — because it depends on where the shower falls relative to the existing stack. That is measured on the visit and fixed item by item.

And a professional warning about the freestanding bath itself. It is the one piece in a bathroom that cannot be moved afterwards: its drain comes up through the slab at a precise point, and if it is set out wrongly, correcting it means lifting newly laid flooring. That is why on our jobs, on the day the bath is set out nothing else is done, and the client signs off the position tape measure in hand. These are figures from our own closed quotes; we work with them across the whole of Catalonia.

  • Two separate wet areas: two waterproofings, two drains, two sets of taps
  • The table prices a freestanding bath OR a shower tray, never both at once
  • Tray and screen as supply: 403–611 € depending on range in our price table
  • The freestanding bath’s drain is set out once, and signed off on site with the client
Your home is not the “example”

What pushes the price up or down in your case

What pushes it up

  • A freestanding bath in the middle of the roomIt stops resting on walls: the drain comes up through the slab at the exact point, the tap is floor-standing or wall-mounted and any set-out error is paid for by chipping up the new flooring.
  • A separate shower as well as the bathIt is the configuration 8 m² allow and this page’s example budget does not include: it adds tray, screen, taps and a second waterproofed wet area.
  • Underfloor heating under the flooringAt 8 m² it starts to pay. It brings its own screed, manifold and thermostat, and forces plumbing and flooring to be coordinated in a sequence that allows no rush.
  • Large format of 120 × 280 on the wallsIn a big bathroom it shows and it is spectacular, but the pieces go in by hand between two or three fitters and may need lifting equipment in the building.

What brings it down

  • A bath built into a plinth instead of freestandingThe built plinth takes the drain at the side, allows tolerances and is lined with the same material as the rest. It is the classic option and far cheaper to install.
  • Grouping the fittings on two wallsIf toilet, bidet and basins share a wall, the plumbing is grouped and the floor work is drastically reduced.
  • Large-format flooring and walls tiled to half heightTiling 34 m² to the ceiling is the item that grows most at this size: dropping to 1.20 m on the dry walls cuts for real.
  • Giving up concealed taps at both pointsA quality exposed thermostatic costs less, is repaired without opening the wall and on a freestanding bath looks just as good.
Timescales

How long an 8 m² bathroom renovation takes

Days 1–2Demolition and slab check

The whole bathroom is emptied. In an 8 m² bathroom with a freestanding bath we check the condition and depth of the slab before any set-out: a full bath is heavy, and the point where it rests has to be known.

Days 3–6Services, drains and bath set-out

Five water points, the bath drain in its exact position, the two basin traps and the electrics with their certificate. This is where the centimetre is decided: a freestanding bath does not move afterwards.

Days 7–9Waterproofing and 34 m² of cladding

Wet area waterproofed, walls tiled and flooring laid. It is the long phase at this size, and the one that explains why the big bathroom does take a little longer.

Days 10–12Fitting and handover

Freestanding bath with its taps, toilet and bidet, vanity unit with both basins, mirror and towel rail. Test fill and drain of the bath, sealing, cleaning and a handover walk-round.

2–2.5 weeks of work · the 34 m² of tiling set the pace — Between two and two and a half weeks. It is the only size in this series where the timescale stretches a little beyond the two weeks that our 4, 5 and 6 m² jobs confirm, and it is not because of the floor area itself: it is the 34 m² of tiling, which is twice as much as in a 4 m² bathroom, and the millimetre set-out the drain of a freestanding bath demands. If a separate shower is fitted as well, there is a second wet area to waterproof and cure. The programme comes in writing with the quote.

Permits: what renovating an 8 m² bathroom needs. Prior notification of works if the renovation is internal and the structure is not touched. At 8 m² there are two situations that do change the procedure and are worth checking beforehand: the metres coming from knocking down a partition that turns out to be load-bearing, and the freestanding bath being placed where the slab will not take that point load without reinforcement. Both need technical involvement and a project. They are checked on the visit, before quoting, and never after starting.

A genuinely fixed quote

What the price includes (and what it does not)

Included

  • A dedicated site manager and a single point of contact throughout the renovation
  • Demolition of the whole bathroom, rubble removal and haulage to an authorised tip
  • New plumbing: 5 water points and the drains, with a watertightness test
  • New electrics for the room with a certificate (CIE) and forced ventilation
  • Waterproofing of the wet area before tiling
  • Freestanding bath with its taps, toilet and bidet, and a double-basin vanity unit
  • Protection of the rest of the home and a final builders’ clean

Not included

  • VAT: 10% reduced rate or 21% depending on your case — confirmed in writing in the quote
  • Council fees for the prior notification of works (passed on at cost)
  • A separate shower in addition to the bath: priced separately and explained below
  • Loose accessories, textiles and decoration
The advice we would give a friend

Where to save on 8 m² — and where never to

Not every cut has the same effect: these are the items where saving is sensible, and the ones where it ends up costing more.

Save here

  • An acrylic freestanding bath rather than stone or mineral resin: the same shape, far lighter and cheaper
  • A floor-standing tap on a single supply instead of a wall-mounted set with two concealed outlets
  • Continuous flooring and tiling only in the wet areas, with the rest skimmed and painted
  • One large mirror instead of two backlit ones over each basin

Never save here

  • Setting out the freestanding bath’s drain: correcting it later means lifting new flooring
  • Waterproofing the second wet area if there is a separate shower
  • Forced ventilation sized for 8 m²: a small bathroom extractor does not move this volume
  • Checking the slab before placing the bath: it is done once, and it is done first
Comparison

From 3 to 8 m²: the table that sums up the whole series

The five sizes we calculate, with the same price table and the equipment that goes with each. From 3 to 8 m² the functional total rises 846 €, 8.5%, while floor area is multiplied by 2.7 and a bidet, double basin and freestanding bath appear. The €/m², on the other hand, is divided by 2.5: it is the indicator that misleads most in a bathroom renovation.

Floor areaFunctionalMid-range
8 m² bathroom (freestanding bath and double basin)10,763 € · 1,345 €/m²16,437 € · 2,055 €/m²
3 m² bathroom (toilet, basin and shower)9,917 € · 3,306 €/m²15,307 € · 5,102 €/m²
6 m² bathroom (bidet and double basin)10,424 € · 1,737 €/m²15,985 € · 2,664 €/m²

* Indicative prices, excluding VAT. They vary with the starting condition of the home, the municipality and the finishes chosen.

Common questions

Questions about the cost of renovating 8 m²

The ones we are asked most before a quote is signed.

How much does it cost to renovate an 8 m² bathroom?

This page’s example budget, with a freestanding bath, bidet and double basin, comes to 10,763 € at a functional specification, 16,437 € at mid-range and 21,600 € for high specification, excluding VAT. We have no published bathroom job that reaches 8 m²: the closest in equipment is the Sabadell one, 6 m² with a bath and double basin, signed between 12,000 and 14,000 €. Your bathroom’s figure is fixed item by item on the technical visit, which is free.

How much does it cost to add a separate shower as well as the bath?

This page’s example budget does not include it, and giving you an invented figure would be no use. What we can give you is the reference from our price table itself: the tray and screen that fill the shower row on the 5 and 6 m² pages cost between 403 € at functional and 611 € for high specification as supply. On top of that comes the second waterproofed wet area, its taps and its drain, which are assessed on the visit because they depend entirely on where it falls relative to the stack.

Is an 8 m² bathroom dearer than a 4 m² one?

Yes, but much less than people assume: 677 € at functional, and that with the 8 m² one including a bidet, second basin and freestanding bath that the 4 m² one does not have. What really makes a big bathroom dearer is not the metres: it is the finish that tends to be chosen when there are eight metres to show it off.

Does the slab need reinforcing for a freestanding bath?

It always has to be checked, and it is checked on the visit and again at demolition. A full freestanding bath concentrates a lot of load on a few points of support, and in old joist-and-vault slabs that is not automatic. If reinforcement is needed, we say so before quoting and it comes as its own item with technical supervision. It is never solved on the fly.

What maintenance does an 8 m² bathroom need compared with a small one?

The same, with one nuance: ventilation. An extractor sized for a 3 m² bathroom does not renew the air in 8 m², and damp that does not leave stays in the joints and the joinery. At this size we calculate the extractor’s flow on the real volume of the room, and if there is a window of its own we use it instead of ignoring it.

Do these prices include VAT?

No: every figure on this page is excluding VAT. The rate that applies — 10% reduced or 21% — depends on your case: private use, age of the building and the weight of materials in the total. It is confirmed in writing in the quote before you sign.

Who we are

Full renovations in Barcelona and across Catalonia. A fixed, itemised quote, a dedicated site manager who keeps you informed and a written warranty.

Related services

Guides and calculators

Want your exact figure, not a range?

A free site visit, a fixed itemised quote and a written programme. What we sign is what you pay.

✆ Call✦ WhatsAppGet a quote →