Electrical installation and lighting points in a flat in La Marina, Barcelona
Carrer del Foc, Barcelona · 60 m² · 2026

Project details
- Floor area
- 60 m²
- Property type
- Flat
- Duration
- 3 weeks
- Year
- 2026
- Status
- In progress
- Budget
- 5,900–6,100 €
- What we did
- New lighting points and switches and sockets in each room · Channel chasing · conduit and setting of boxes · Downlights and ceiling supplies · Work in a finished home · with protection
Indicative prices · VAT not included. Not a binding offer; every project is quoted after the site visit.
About this renovation
Extension of the electrical installation in a flat that was already finished: new lighting points, sockets and downlights, cutting channels only where needed and protecting the floor and skirting.
This job has a difficulty you cannot see in the photos: the home was already finished and lived in. It was not a matter of wiring an empty house, but of fitting new lighting points and sockets into painted walls and over a floor that cannot be lifted.
That is why the work starts on the wall, before the wall chaser. The whole route is marked out with tape — verticals, horizontals and the height of each box — checked with the client on site, and only then is the channel cut. Marking first costs a morning and avoids cutting more than needed, which is what you pay for later in skim plaster and paint.
The boxes are set in plaster and the channels are filled in, leaving the room ready to be skimmed and painted; the downlights are fitted and the ceiling supplies are waiting for their light fittings. The ducted air-conditioning grille was already there, so the new route had to work around the air-conditioning false ceiling.
The job is still under way, so there are no finished photos here: only the ones that explain how it is done. That is why this project carries no guide budget.
The figures on this page (area, duration and budget) are guide estimates and the location is approximate: they are not the final data for this job.