Completed

Renovation of a flat for room rental in the Raval, Barcelona

Carrer del Carme, Barcelona · 115 m² · 2026

En-suite bathroom with a countertop basin on a wooden worktop, wall-mounted taps and a framed mirror

Project details

Floor area
115 m²
Property type
Flat
Duration
18 weeks
Year
2026
Status
Completed
Budget
65,000–71,500 €
What we did
Five en-suite bathrooms with the same construction solution · Shared single-run kitchen with integrated appliances · Built-in wardrobes in all the rooms · Making use of the existing mezzanine and gallery · Wood-effect flooring throughout the home

Indicative prices · VAT not included. Not a binding offer; every project is quoted after the site visit.

About this renovation

An old flat turned into a home let by the room: five en-suite bathrooms solved with the same design, a shared kitchen and built-in wardrobes in every room.

A flat to be let by the room is not renovated like a family home. What decides whether the project works is not the living room: it is how many rooms can have their own bathroom without turning the home into a corridor, and whether the services can cope with five showers at the same time.

The five en-suite bathrooms were done with a single repeated solution — wooden worktop, countertop basin, wall-mounted taps, a glass screen and a built-in niche in the shower. Repeating is not laziness in the design: it makes buying cheaper, speeds up fitting and, above all, turns future maintenance into a single list of spares instead of five.

The rest came down to making the most of what the flat already had. The outside gallery and the mezzanine over the masonry wall were kept and integrated instead of being demolished, one room solved its clear height with a raised bed and a desk underneath, and every room has built-in wardrobes up to the ceiling so that the tenant does not need to bring furniture. The kitchen and dining room stay as the shared area.

This is the renovation of an investment flat in the Raval, measured in lettable rooms and years of maintenance, not in metres of living room.

The figures on this page (area, duration and budget) are guide estimates and the location is approximate: they are not the final data for this job.